D4- Work Order Tracking (Invited)
Status Report on the Progress and Achievement at Individual Work Order Level

Clear
Rs. in Lakh
Sl No. District
As per Census (2011)
Scheme SM Code Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Type
Type of Scheme as per PHED-MIS
Name of JE entrusted SLSSC Date
Date of SLSSC in which the Scheme has been Approved
FHTC Involved
Approved FHTC Count Modified after the appropriation in YDU considered under the Schemes for which Work Order has been Issued as per PHED-MIS
Estimated Cost AAFS Cost
Approved Implementation as mentioned in AAFS considered under the Schemes for which Work Order has been Issued as per PHED-MIS
Resource Material Date of First Work Order
Total No. of Work Orders Issued under the Scheme as per PHED-MIS
No. of Work Orders Issued
Total No. of Work Orders Issued under the Scheme as per PHED-MIS
Work Value
Total Cost for all the Issued Work Order under the Scheme as per PHED-MIS
Payment
Total Payment made for these Work Orders as per PHED-MIS
Payment % Physical Progress %
173 67,062 72,816.28 72,816.28 0 # 525 67,751.79 8,692.92 # #
1 KALIMPONG SM/07872 Retrofitting for FHTC & Improvement of piped water supply scheme for Pedong Bazar & adjoining areas in connection with (JJM & Jal swapno) Retrofitting 04/12/2020 625 72.63 72.63 0.00 12/10/2020 5 67.79 49.50 73.02 0
2 KALIMPONG SM/08693 Retrofitting of Neorakhola piped water supply scheme to provide Functional Household Tap Connection to the enroute villages of the scheme in Kalimpong Block I & II in Kalimpong District under JJM & JAL SWAPNA Programme Retrofitting Junior Engineer I,Junior Engineer IV 10/02/2021 1,000 99.42 99.42 0.00 06/09/2021 4 99.17 97.95 98.77 100
3 KALIMPONG SM/09539 PWS SCHEME FROM HARI KHOLA TO UPPER LOWER GUMTI New Junior Engineer-4 29/09/2021 121 151.50 151.50 0.00 14/01/2022 2 147.73 33.81 22.89 100
4 KALIMPONG SM/09540 PWS SCHEME FROM BARA SUKAY KHOLA TO CHOTTA MANZING New Junior Engineer-4 29/09/2021 61 91.94 91.94 0.00 14/01/2022 2 89.37 71.94 80.5 90
5 KALIMPONG SM/09541 PWS SCHEME FROM GAIRIBAS KHOLA& GEET KHOLA TO JHANDI New Junior Engineer III 29/09/2021 400 568.83 568.83 0.00 04/04/2022 3 553.22 170.48 30.82 86
6 KALIMPONG SM/09542 PWS SCHEME FROM CHINDAY JHORA TO YONZON, BOMZON, LAMA GAON New Junior Engineer III 29/09/2021 87 108.18 108.18 0.00 28/03/2022 2 96.64 76.60 79.26 80
7 KALIMPONG SM/09543 PWS SCHEME FROM CHAR CHAREY JHORA TO PUBUNG BUSTY New Junior Engineer-4 29/09/2021 213 365.16 365.16 0.00 21/02/2022 2 355.16 107.46 30.26 65
8 KALIMPONG SM/09544 PIPED WATER SUPPLY SCHEME FROM CHISO PANI PEEPAL DHARA TO LAMINI,RAI, DHAJEY GOAN. New Junior Engineer-2,Junior Engineer-I 29/09/2021 147 198.74 198.74 0.00 14/01/2022 2 193.65 97.35 50.27 100
9 KALIMPONG SM/09545 PWSS SCHEME FROM NIMBONG KHOLA TO UPPER AND LOWER GESHOK AND GAIRIGAON New Junior Engineer-4 29/09/2021 125 160.48 160.48 0.00 07/01/2022 3 160.58 17.77 11.07 100
10 KALIMPONG SM/09546 PWS SCHEME FROM MAWATAR TO UPPER DABLING New Junior Engineer-2 29/09/2021 50 192.44 192.44 0.00 07/01/2022 4 186.52 89.68 48.08 100
11 KALIMPONG SM/09547 PWS SCHEM FROM OKHERBOTEY KHOLA TO UPPER PEDONG New Junior Engineer-3,Junior Engineer-II 29/09/2021 300 237.68 237.68 0.00 14/01/2022 6 239.34 121.78 50.88 80
12 KALIMPONG SM/09548 PWS from Samphong Khola to Kagey Busty District Kalimpong New Junior Engineer-3,Junior Engineer-III 29/09/2021 641 679.86 679.86 0.00 21/02/2022 3 675.69 339.93 50.31 85
13 KALIMPONG SM/09584 PWS SCHEME FROM JHOLUNG KHOLA TO 45 DHURA New Junior Engineer-4,Junior Engineer-I 08/10/2021 160 138.09 138.09 0.00 14/01/2022 2 134.78 69.04 51.22 90
14 KALIMPONG SM/09594 PWS SCHEME FROM THUKCHUK KHOLA TO 20TH MILE New Junior Engineer IV 29/09/2021 480 776.35 776.35 0.00 04/04/2022 2 743.50 169.18 22.75 70
15 KALIMPONG SM/09595 PWS SCHEME FROM UNEAK KHOLA TO DABLING New Junior Engineer-2 29/09/2021 95 126.98 126.98 0.00 07/01/2022 2 123.18 59.27 48.12 100
16 KALIMPONG SM/09596 PWS SCHEME FROM DHATURAY JHORA TO DEWARLI GAON, GUMBA GAON, BICH GAON New 29/09/2021 320 314.39 314.39 0.00 27/01/2022 5 316.24 202.20 63.94 100
17 KALIMPONG SM/09597 PWS SCHEME FROM HIGHEST POINT JHORA TO UGEN MINDRU SAMTENLING GUMBA New Junior Engineer-4,Junior Engineer-III 29/09/2021 74 199.67 199.67 0.00 14/01/2022 2 193.29 83.81 43.36 100
18 KALIMPONG SM/09598 PWS SCHEME FROM OKHERBOTEY JHORA TO DARA GAON New Junior Engineer-3 29/09/2021 56 96.33 96.33 0.00 07/01/2022 2 93.59 0.00 0 100
19 KALIMPONG SM/09599 PIPED WATER SUPPLY SCHEME FROM DHOBI KHOLA TO KASHYONE. New Junior Engineer III 29/09/2021 502 312.00 312.00 0.00 21/02/2022 3 308.40 156.00 50.58 90
20 KALIMPONG SM/09600 PWS SCHEME FROM SISNEY AND ANKUREY JHORA TO NOKDARA New Junior Engineer-2,Junior Engineer-II 29/09/2021 234 169.19 169.19 0.00 14/01/2022 4 165.26 60.00 36.31 90
21 KALIMPONG SM/09601 PWS SCHEME FROM CHAMUNG KHOLA TO GITDABLING BAZAR New Junior Engineer-3,Junior Engineer-III 29/09/2021 245 206.39 206.39 0.00 07/01/2022 5 199.21 88.49 44.42 100
22 KALIMPONG SM/09602 Pws scheme from 7th Mile Jhora to Algarah New Junior Engineer IV 29/09/2021 450 321.38 321.38 0.00 21/02/2022 3 303.02 159.32 52.58 97
23 KALIMPONG SM/09603 PWS SCHEME FROM 9TH MILE JHORA TO 18TH MILE New Junior Engineer III 29/09/2021 120 258.69 258.69 0.00 21/02/2022 5 257.42 163.51 63.52 100
24 KALIMPONG SM/09605 PWS SCHEME FROM JHOLUNGAY KHOLA(BANDUKEY) TO DOKAN DARA New Junior Engineer-4,Junior Engineer-I 29/09/2021 220 164.46 164.46 0.00 14/01/2022 2 160.83 130.66 81.24 100
25 KALIMPONG SM/09606 PWS SCHEME BHERI POSHYER KHOLA TO KOTHI LINE New Junior Engineer-4 29/09/2021 230 198.35 198.35 0.00 07/01/2022 2 193.36 75.76 39.18 100
26 KALIMPONG SM/09607 PWS SCHEME FROM BHUPALEY KHOLA TO PAREN New Junior Engineer-4,Junior Engineer-I 29/09/2021 208 108.86 108.86 0.00 14/01/2022 2 106.77 54.43 50.98 80
27 KALIMPONG SM/09608 PWS SCHEME FROM AMBIOK KHOLA (PARBALAKHA) TO GORUBATHAN TAR New Junior Engineer-4,Junior Engineer-I 29/09/2021 448 367.78 367.78 0.00 21/02/2022 4 361.24 22.42 6.21 90
28 KALIMPONG SM/09609 PWS SCHEME FROM REON KHOLA TO LOWER PEMBLING New Junior Engineer-3,Junior Engineer-I 29/09/2021 75 98.66 98.66 0.00 07/01/2022 2 95.48 49.33 51.67 100
29 KALIMPONG SM/09610 PWS SCHEME FROM CHAWA KHOLA TO RELLI New Junior Engineer-4 29/09/2021 125 122.01 122.01 0.00 07/01/2022 2 180.95 115.11 63.61 100
30 KALIMPONG SM/09611 PWS SCHEME FROM BICHRI DHARA TO LOWER SUNGDUNG New Junior Engineer-3,Junior Engineer-II 29/09/2021 70 80.80 80.80 0.00 07/01/2022 2 78.77 18.52 23.51 100
31 KALIMPONG SM/09612 PWS SCHEME FROM SAMTHARA KHOLA TO CENTRE GAON, PINTALAY GAON, GUDARA GAON, BICH GAON, CHETTRI GAON New Junior Engineer III 29/09/2021 110 180.96 180.96 0.00 28/02/2022 1 154.60 0.00 0 80
32 KALIMPONG SM/09613 PWSS SCHEME FROM SISNEY KHOLA TO UPPER AND LOWER KAMBAL & DINGALI GAON New Junior Engineer IV 29/09/2021 88 110.68 110.68 0.00 28/02/2022 2 107.88 26.16 24.25 100
33 KALIMPONG SM/09614 PWS SCHEME FROM KAIJARBOTEY JHORA TO LOWER POSHYER BHASMEY New Junior Engineer-2,Junior Engineer-II 29/09/2021 61 88.27 88.27 0.00 14/01/2022 2 86.02 44.14 51.31 100
34 KALIMPONG SM/09615 PWS SCHEME FROM CHAGEY KHOLA TO KATAREY GAON New Junior Engineer-4 29/09/2021 55 118.44 118.44 0.00 14/01/2022 3 117.29 108.04 92.11 100
35 KALIMPONG SM/09616 PWS SCHEME FROM KAMZER KHOLA TO LOLAY DOKAN DARA New Junior Engineer-2,Junior Engineer-II 29/09/2021 50 143.99 143.99 0.00 07/01/2022 2 139.12 60.00 43.13 100
36 KALIMPONG SM/09617 PWSS FROM MALI KHOLA TO KASHMI FOREST VILLAGE New Junior Engineer-4,Junior Engineer-I 29/09/2021 99 100.06 100.06 0.00 15/05/2023 4 91.96 32.28 35.1 100
37 KALIMPONG SM/09664 PWS SCHEME FROM CHAGEY KHOLA TO SAURENI New 29/09/2021 60 137.62 137.62 0.00 07/01/2022 2 133.81 99.98 74.72 100
38 KALIMPONG SM/09665 PIPED WATER SUPPLY SCHEME FROM SISNEY JHORA TO NORTH PEDONG New Junior Engineer-3,Junior Engineer-II 29/09/2021 221 142.76 142.76 0.00 14/01/2022 2 139.48 45.78 32.82 80
39 KALIMPONG SM/09666 PWS SCHEME FROM THAKALEY JHORA TO VATTY DARA 3RD MILE New Junior Engineer-II 29/09/2021 140 138.81 138.81 0.00 07/01/2022 2 135.39 34.30 25.33 75
40 KALIMPONG SM/09667 PWS SCHEME FROM JHOLUNG KHOLA TO UPPER, LOWER AND MIDDLE DHAP New 29/09/2021 350 476.50 476.50 0.00 21/02/2022 2 528.15 339.12 64.21 100
41 KALIMPONG SM/09668 PWS SCHEME FROM ARDHALI JHORA TO TINKATAREY, CHAPLATEY, BARAL, GURDAY GAON New Junior Engineer-4,Junior Engineer-I 29/09/2021 140 182.37 182.37 0.00 14/01/2022 5 179.08 40.96 22.87 80
42 KALIMPONG SM/09669 PWSS SCHEME FROM KHANI KHOLA TO WEST SAMALBONG New Junior Engineer-4,Junior Engineer-I 29/09/2021 56 125.27 125.27 0.00 07/01/2022 2 121.87 85.86 70.45 100
43 KALIMPONG SM/09670 PWS SCHEME FROM NIMBONG KHOLA TO SALDARA New Junior Engineer-2,Junior Engineer-II 29/09/2021 65 122.05 122.05 0.00 07/01/2022 2 118.14 7.93 6.71 100
44 KALIMPONG SM/10052 Augmentation of Neorakhola Water Supply Scheme for extending FHTC Facility to the enroute habitations under Kalimpong Block-I & Block-II under Neorakhola W/S & Mtc Division ,PHE Dte., Kalimpong Augmentation Junior Engineer III,Junior Engineer IV 15/09/2021 0 4,402.74 4,402.74 0.00 28/02/2022 25 2,084.64 581.57 27.9 47
45 KALIMPONG SM/10265 Functional household tap connection under Jal Swapno Programme, 14 Nos. existing schemes to be provided with FHTC under GTA. Retrofitting 08/01/2021 1,475 228.22 228.22 0.00 14/12/2022 14 199.13 161.25 80.98 0
46 KALIMPONG SM/10266 Functional household tap connection under Jal Swapno Programme, 10 Nos. existing schemes to be provided with FHTC under GTA. Retrofitting 08/01/2021 1,769 187.99 187.99 0.00 14/12/2022 12 163.77 110.68 67.58 0
47 KALIMPONG SM/10267 Functional household tap connection under Jal Swapno Programme, 8 Nos. existing schemes to be provided with FHTC under GTA. Retrofitting 08/01/2021 1,116 127.68 127.68 0.00 14/12/2022 9 116.84 102.69 87.89 0
48 KALIMPONG SM/10512 Detail Project Report on Extension of pipeline by way of Retrofitting of Neorakhola Piped water Scheme to provide Functional Household Tap Connection to the remaining households of en-route villages of the Scheme in Kalimpong Block I-II , under Kalimpong Retrofitting Junior Engineer I,Junior Engineer III,Junior Engineer IV 17/02/2022 677 504.20 504.20 0.00 13/04/2022 5 483.72 270.68 55.96 95
49 KALIMPONG SM/10562 Gravity based piped water supply scheme for Bokhim khasmahal & paygang khasmahal (PC) under Gitdabling G.P. Kalimpong Blick-II in the District of Kalimpong in connection under Neorakhola Water Supply & Maintenance Division, P.H.E Directorate. New Junior Engineer IV 16/03/2022 67 132.05 132.05 0.00 24/05/2022 1 124.76 0.00 0 95
50 KALIMPONG SM/10563 Gravity based piped water supply scheme for pemling forest under Kaffer - Kankebong G.P. Kalimpong Block-I, Dist-Kalimpong in connection under Neorakhola W/S & Mtc, Div. PHE. Dte. Kalimpong. New 16/03/2022 34 62.89 62.89 0.00 26/05/2022 3 60.98 0.00 0 100
51 KALIMPONG SM/10575 Gravity based piped water supply scheme for BIRIK FOREST VILLAGE under G.P. Kalimpong Block-I, District- Kalimpong in Connection under Neorakhola Water Supply & Maintenance Division, P.H.E Directorate. New Junior Engineer IV 16/03/2022 43 49.33 49.33 0.00 26/05/2022 3 47.61 0.00 0 90
52 KALIMPONG SM/10576 Gravity based piped water supply scheme for Paren forest Village under Paten Godak GP in Gorubathan Block in connection with implementation in the district of Kalimpong under Neorakhola W/S & Mtc, Div. PHE. Dte. Kalimpong. New 16/03/2022 45 49.14 49.14 0.00 26/05/2022 2 48.22 0.00 0 50
53 KALIMPONG SM/10599 Gravity based piped water supply scheme for chumang forest under Gitdabling G.P Kalimpong Block-II, Dist- Kalimpong in connection under Neorakhola W/S & Mtc, Div. PHE. Dte. Kalimpong. New Junior Engineer IV 16/03/2022 28 67.06 67.06 0.00 26/05/2022 1 61.94 0.00 0 100
54 KALIMPONG SM/10600 Gravity based piped water supply scheme for Tashiding forest Village under Tashiding GP in Kalimpong Block I in connecion with implementation in the district of Kalimpong under Neorakhola W/S & Mtc, Div. PHE. Dte., Kalimpong. New 16/03/2022 13 10.62 10.62 0.00 26/05/2022 2 10.28 0.00 0 100
55 KALIMPONG SM/10601 Gravity based piped water supply scheme for Dalapchand slip reserve forest Village under Dalapchand GP in Kalimpong Block II in connecion with implementation in the district of Kalimpong under Neorakhola W/S & Mtc, Div. PHE. Dte. Kalimpong. New Junior Engineer IV 16/03/2022 10 9.66 9.66 0.00 26/05/2022 2 9.29 4.35 46.82 0
56 KALIMPONG SM/10602 Gravity based piped water supply scheme for Rissium forest Village under Santook GP in Kalimpong Block-II, in the District of Kalimpong in connecion with implementation under Neorakhola W/S & Mtc, Div. PHE. Dte. Kalimpong. New Junior Engineer IV 16/03/2022 27 25.25 25.25 0.00 26/05/2022 1 21.57 0.00 0 100
57 KALIMPONG SM/10603 Gravity based piped water supply scheme for Noam forest Village under Pokhriabong GP in Gorubathan Block in connecion with implementation in the district of Kalimpong under Neorakhola W/S & Mtc, Div. PHE. Dte. Kalimpong. New 16/03/2022 55 41.32 41.32 0.00 15/05/2023 3 46.86 0.00 0 10
58 KALIMPONG SM/10623 Gravity based piped water supply scheme for Kolbong Forest Village under Lava Gitbeong G.P. Kalimpong Block-II, in the District of Kalimpong in Connection under Neorakhola Water Supply & Maintenance Division, P.H.E Directorate. New Junior Engineer III 16/03/2022 28 41.40 41.40 0.00 25/05/2022 1 38.82 20.70 53.32 95
59 KALIMPONG SM/10624 Gravity based piped water supply scheme for Icha forest Village under Sangsey GP Kalimpong Block-II, in the District of Kalimpong in connecion with implementation under Neorakhola W/S & Mtc, Div. PHE. Dte. Kalimpong. New 16/03/2022 42 40.13 40.13 0.00 25/05/2022 1 60.93 20.06 32.92 0
60 KALIMPONG SM/10625 Gravity based piped water supply scheme for Paiengoan forest Village under Santook GP in Kalimpong Block-II in the district of Kalimpong in connecion with implementation under Neorakhola W/S & Mtc, Div. PHE. Dte. Kalimpong. New Junior Engineer I 16/03/2022 62 49.50 49.50 0.00 26/05/2022 3 51.49 0.00 0 90
61 KALIMPONG SM/10635 PROPOSED SURFACE WATER BASED YAKPRINTAM KHASMAHAL (part) PWSS TO ACCOMMODATE FHTC IN KALIMPONG-I BLOCK WITHIN KALIMPONG DISTRICT UNDER NEORAKHOKA W/S & MTC. DIVISION, PHE DTE. New Junior Engineer III 16/03/2022 70 143.53 143.53 0.00 30/06/2022 2 137.52 70.74 51.44 85
62 KALIMPONG SM/10694 PIPED WATER SUPPLY SCHEME FROM NEROLA JHORA TO LOWER ECHHEY UNDER KALIMPONG BLOCK - I UNDER JJM AND JAL SWAPNO PROGRAMME New Junior Engineer-2,Junior Engineer-II 17/02/2022 105 94.15 94.15 0.00 25/05/2022 2 93.09 47.07 50.56 75
63 KALIMPONG SM/10695 PIPED WATER SUPPLY SCHEME FROM GURUNG JHORA TO PACHIM KABI GAON UNDER KALIMPONG BLOCK - I UNDER JJM AND JAL SWAPNO PROGRAMME New Junior Engineer-3,Junior Engineer-II 17/02/2022 136 138.07 138.07 0.00 26/05/2022 1 133.86 69.04 51.58 100
64 KALIMPONG SM/10696 PIPED WATER SUPPLY SCHEME FROM AGINGAREY KHOLCHA TO 8 12 AND KHOTILINE UNDER GORUBATHAN BLOCK UNDER JJM AND JAL SWAPNO PROGRAMME New Junior Engineer-4,Junior Engineer-I 17/02/2022 135 115.09 115.09 0.00 25/05/2022 2 107.89 54.67 50.67 100
65 KALIMPONG SM/10697 PIPED WATER SUPPLY SCHEME FROM KATHAREY KHOLA TO BHUTIA BUSTY UNDER GORUBATHAN BLOCK UNDER JJM AND JAL SWAPNO PROGRAMME New Junior Engineer-4,Junior Engineer-I 17/02/2022 100 126.09 126.09 0.00 01/08/2022 1 120.90 22.25 18.4 100
66 KALIMPONG SM/10698 PIPED WATER SUPPLY SCHEME FROM DORKHOLA TO LUNGSEL UNDER GORUBATHAN BLOCK UNDER JJM AND JAL SWAPNO PROGRAMME New Junior Engineer-4,Junior Engineer-I 17/02/2022 169 206.41 206.41 0.00 25/05/2022 1 196.26 93.39 47.58 100
67 KALIMPONG SM/10699 PIPED WATER SUPPLY SCHEME FROM DADALEY JHORA TO BURMAIK UNDER SANGSEY G.P BLOCK-II, KALIMPONG UNDER JJM AND JAL SWAPNO PROGRAMME New Junior Engineer-2,Junior Engineer-II 17/02/2022 350 152.76 152.76 0.00 25/05/2022 1 147.75 0.00 0 90
68 KALIMPONG SM/10700 PIPED WATER SUPPLY SCHEME FROM SIRISE KHOLA TO ROCKY ISLAND UNDER KALIMPONG GORUBATHAN BLOCK UNDER JJM AND JAL SWAPNO PROGRAMME New Junior Engineer-4,Junior Engineer-I 17/02/2022 242 173.31 173.31 0.00 24/05/2022 1 164.25 0.00 0 100
69 KALIMPONG SM/10701 PIPED WATER SUPPLY SCHEME FROM SETHI KHOLA TO UPPER KHANI UNDER KALIMPONG BLOCK - I UNDER JJM AND JAL SWAPNO PROGRAMME New Junior Engineer-4,Junior Engineer-III 17/02/2022 90 114.57 114.57 0.00 30/06/2022 1 104.88 26.84 25.59 100
70 KALIMPONG SM/10702 PIPED WATER SUPPLY SCHEME FROM HARISEY JHORA TO LOWER BHAGEY UNDER SANGSEY G.P BLOCK-II, KALIMPONG UNDER JJM AND JAL SWAPNO PROGRAMME New Junior Engineer-3,Junior Engineer-II 17/02/2022 131 113.56 113.56 0.00 13/05/2022 1 100.81 52.04 51.62 75
71 KALIMPONG SM/10703 PIPED WATER SUPPLY SCHEME FROM BULBULEY JHORA TO SURUK UNDER SAMTHAR G.P BLOCK-I, KALIMPONG UNDER JJM AND JAL SWAPNO PROGRAMME New Junior Engineer-4 17/02/2022 407 286.37 286.37 0.00 26/05/2022 1 277.69 252.26 90.84 100
72 KALIMPONG SM/10704 PIPED WATER SUPPLY SCHEME FROM BURMAIK JHORA TO MAHAKAL DARA UNDER BHALUKHOP G.P BLOCK-I, KALIMPONG UNDER JJM AND JAL SWAPNO PROGRAMME New Junior Engineer-2,Junior Engineer-III 17/02/2022 226 338.99 338.99 0.00 05/08/2022 2 328.86 7.41 2.25 80
73 KALIMPONG SM/10705 Augmentation of Lolaygoan Bazar Water Supply Scheme (IMIS Code-0001723403) for providing Functional Household Tap Connections (FHTC) in connection with Jal Jeevan Mission (JJM) under Neorakhola Water Supply & Maintenance Division, P.H.E Directorate. Augmentation Junior Engineer III 27/01/2022 105 99.21 99.21 0.00 13/04/2022 1 95.54 0.00 0 80
74 KALIMPONG SM/10729 Chunabhatti Bazar D.I.F & Lish Forest Piped Water Supply Scheme. New Junior Engineer I 16/03/2022 197 136.35 136.35 0.00 26/05/2022 8 137.80 89.20 64.73 100
75 KALIMPONG SM/10739 Gravity based piped water supply scheme for Mangber forest Village under Teesta GP in Kalimpong Block-I in connection with implementation in the district of Kalimpong under Neorakhola W/S & Mtc, Div. PHE. Dte. Kalimpong. New 16/03/2022 7 5.37 5.37 0.00 26/05/2022 1 4.77 2.69 56.39 100
76 KALIMPONG SM/10741 PWS SCHEME FROM CHIP CHHIPEY JHORA TO CFC FOREST VILLAGE New Junior Engineer-4,Junior Engineer-I 17/02/2022 80 92.28 92.28 0.00 26/05/2022 3 84.35 14.16 16.79 100
77 KALIMPONG SM/10742 PWS SCHEME FROM SISNEY JHORA TO SAMTHAR BAZAR New Junior Engineer-4,Junior Engineer-II 17/02/2022 252 197.78 197.78 0.00 25/05/2022 1 191.91 106.48 55.48 100
78 KALIMPONG SM/10743 PWS SCHEME FROM UTISHEY JHORA TO LOWER YOGDA New Junior Engineer-2,Junior Engineer-II 17/02/2022 87 79.81 79.81 0.00 25/05/2022 1 76.69 25.28 32.96 90
79 KALIMPONG SM/10744 PWS SCHEME FROM PARANG KHOLA TO MUNSONG CINCHONA PLANTATION New Junior Engineer-3,Junior Engineer-I 17/02/2022 405 225.47 225.47 0.00 25/05/2022 1 294.49 177.46 60.26 100
80 KALIMPONG SM/10745 PWS SCHEME FROM OKHERBOTEY JHORA TO DUN New Junior Engineer-2,Junior Engineer-II 17/02/2022 90 91.35 91.35 0.00 26/05/2022 1 88.59 29.25 33.02 100
81 KALIMPONG SM/10746 PWS SCHEME FROM PAREN KHOLA TO RANGPO DIVISON New 17/02/2022 205 194.83 194.83 0.00 25/05/2022 2 348.09 145.77 41.88 100
82 KALIMPONG SM/10747 PWS SCHEME FROM BHADRA JHORA TO CHOTTA SURUK New Junior Engineer-2,Junior Engineer-II 17/02/2022 135 72.57 72.57 0.00 30/06/2022 1 70.29 34.47 49.04 100
83 KALIMPONG SM/10748 PWS SCHEME FROM PHENTO SOURCE TO DUKA New Junior Engineer-3,Junior Engineer-III 17/02/2022 143 165.77 165.77 0.00 25/05/2022 1 155.54 32.83 21.11 55
84 KALIMPONG SM/10749 PWS SCHEME FROM KHARKHOLA TO SARDAR AND LOWER TOP LINE New Junior Engineer-4,Junior Engineer-I 17/02/2022 105 105.72 105.72 0.00 25/05/2022 1 102.55 83.48 81.4 100
85 KALIMPONG SM/10750 PWS SCHEME FROM BANGLA JHORA TO JOGITAR New Junior Engineer-4,Junior Engineer-I 17/02/2022 60 65.73 65.73 0.00 25/05/2022 1 48.43 0.00 0 100
86 KALIMPONG SM/10751 PWS SCHEME FROM MANDIR KHOLA TO TANYANG New Junior Engineer-3,Junior Engineer-III 17/02/2022 195 214.24 214.24 0.00 26/05/2022 1 211.87 0.00 0 97
87 KALIMPONG SM/10752 PWS SCHEME FROM SISNEY KHOLA TO NAJOK BUSTY New Junior Engineer-2,Junior Engineer-II 17/02/2022 72 75.91 75.91 0.00 30/06/2022 1 73.59 12.51 17 100
88 KALIMPONG SM/10753 PWS SCHEME FROM KHANI KHOLA TO CHUKIM New Junior Engineer-4,Junior Engineer-III 17/02/2022 122 138.36 138.36 0.00 25/05/2022 1 134.25 65.72 48.95 100
89 KALIMPONG SM/10754 PWS SCHEME FROM KAMZER KHOLA TO LOWER LOLAY New Junior Engineer-2,Junior Engineer-II 17/02/2022 160 176.39 176.39 0.00 26/05/2022 1 174.61 17.64 10.1 100
90 KALIMPONG SM/10755 PWS SCHEME FROM DHOBI KHOLA TO LOWER DALEP New Junior Engineer-3,Junior Engineer-II 17/02/2022 160 201.10 201.10 0.00 25/05/2022 1 199.10 90.50 45.45 75
91 KALIMPONG SM/10756 PWS SCHEME FROM KHARKHOLA TO LOWER REON New Junior Engineer-2,Junior Engineer-I 17/02/2022 102 105.07 105.07 0.00 25/05/2022 1 101.69 24.38 23.97 75
92 KALIMPONG SM/10787 Proposed surface water based Nabgaon Khasmahal PWSS to accommodate FHTC in Kalimpong-I Block within Kalimpong District under Neorakhola W/S & Mtc Division P.H.E Dte. New Junior Engineer III 16/03/2022 613 975.33 975.33 0.00 12/07/2022 3 958.85 386.73 40.33 95
93 KALIMPONG SM/10791 PROPOSED SURFACE WATER BASED KANKE BONG KHASMAHAL PWSS TO ACCOMMODATE FHTC IN KALIMPONG-I BLOCK WITHIN KALIMPONG DISTRICT UNDER NEORAKHOKA W/S & MTC. DIVISION, PHE DTE. New Junior Engineer IV 16/03/2022 373 470.31 470.31 0.00 30/06/2022 1 448.31 35.18 7.85 85
94 KALIMPONG SM/10792 PROPOSED SURFACE WATER BASED SAMALBONG KHASMAHAL PWSS TO ACCOMMODATE FHTC IN KALIMPONG-I BLOCK WITHIN KALIMPONG DISTRICT UNDER NEORAKHOKA W/S & MTC. DIVISION, PHE DTE. New Junior Engineer IV 16/03/2022 457 606.74 606.74 0.00 12/07/2022 2 587.18 92.06 15.68 70
95 KALIMPONG SM/10793 PROPOSED SURFACE WATER BASED NIMBONG KHASMAHAL PWSS TO ACCOMMODATE FHTC IN KALIMPONG-I BLOCK WITHIN KALIMPONG DISTRICT UNDER NEORAKHOKA W/S & MTC. DIVISION, PHE DTE. New Junior Engineer IV 16/03/2022 342 731.44 731.44 0.00 12/07/2022 6 694.24 150.64 21.7 75
96 KALIMPONG SM/10820 Mini Piped Water Supply Scheme for Lehti Forest Village under Block Gorubathan District Kalimpong New 16/03/2022 48 47.33 47.33 0.00 30/06/2022 2 179.68 0.00 0 0
97 KALIMPONG SM/11312 PURBA KABI GAON GRAVITY BASED PIPE WATER SUPPLY SCHEME New Junior Engineer IV 16/03/2022 98 100.81 100.81 0.00 30/06/2022 1 96.46 0.00 0 98
98 KALIMPONG SM/11313 SURFACE WATER BASED PARINAGAR KHASMAHAL PWSS TO ACCOMMODATE FHTC IN KALIMPONG-I BLOCK WITHIN KALIMPONG DISTRICT UNDER NEORAKHOKA W/S & MTC. DIVISION, PHE DTE. New Junior Engineer I 16/03/2022 462 829.30 829.30 0.00 12/07/2022 7 763.43 267.21 35 70
99 KALIMPONG SM/11340 PWS SCHEME FROM SAWRENI KHOLA TO NIM BUSTY New Junior Engineer-4,Junior Engineer-I 17/02/2022 280 220.09 220.09 0.00 30/06/2022 1 174.02 0.00 0 85
100 KALIMPONG SM/11341 PWS SCHEME FROM DEORALI KHOLA TO PAKANG New Junior Engineer-2,Junior Engineer-II 17/02/2022 150 117.19 117.19 0.00 30/06/2022 1 113.45 55.66 49.06 100
101 KALIMPONG SM/11342 PWS SCHEME FROM DALDALEY JHORA TO PASSABONG New Junior Engineer-2,Junior Engineer-II 17/02/2022 65 100.52 100.52 0.00 30/06/2022 1 96.00 45.23 47.11 100
102 KALIMPONG SM/11343 PWSS FROM BHARKHOP JHORA TO LOWER KAFFER New Junior Engineer-2,Junior Engineer-II 17/02/2022 85 99.53 99.53 0.00 30/06/2022 1 96.58 47.28 48.95 100
103 KALIMPONG SM/11354 PWS SCHEME FROM HARESAY JHORA TO MUNSI DHURA and KARBUTAR New Junior Engineer-3,Junior Engineer-III 16/03/2022 106 143.23 143.23 0.00 21/09/2022 1 135.69 0.00 0 50
104 KALIMPONG SM/11376 RIYONG FOREST & RIYANG RAILWAY STATION PIPED WATER SUPPLY SCHEME UNDER TEESTA G.P, BLOCK:-KALIMPONG-I, P.S:-KALIMPONG, DISTRICT:KALIMPONG. New Junior Engineer IV 30/03/2022 147 191.02 191.02 0.00 12/07/2022 6 189.16 72.89 38.53 74
105 KALIMPONG SM/11377 SUNTALAY KHASMAHAL PIPED WATER SUPPLY SCHEME UNDER TEESTA G.P, BLOCK:-KALIMPONG-I, P.S:-KALIMPONG, DISTRICT:KALIMPONG New Junior Engineer III 30/03/2022 55 89.16 89.16 0.00 12/07/2022 2 92.09 0.00 0 56
106 KALIMPONG SM/11577 DETAIL PROJECT REPORT OF SEPKHOLA PIPED WATER SUPPLY SCHEME (PWSS) UNDER MAZEOK FOREST, SAMTHAR G.P, BLOCK:-KALIMPONG-I, P.S:-KALIMPONG, DISTRICT:KALIMPONG. New Junior Engineer-4,Junior Engineer-II 30/03/2022 32 47.54 47.54 0.00 28/09/2022 2 46.76 0.00 0 60
107 KALIMPONG SM/11578 DETAIL PROJECT REPORT OF SURUK KHASMAHAL (THREE HABITATION) PIPED WATER SUPPLY SCHEME (PWSS) UNDER SAMTHAR G.P, BLOCK:-KALIMPONG-I, P.S:-KALIMPONG, DISTRICT:KALIMPONG New Junior Engineer-3,Junior Engineer-III 30/03/2022 296 393.32 393.32 0.00 14/10/2022 2 374.22 88.17 23.56 95
108 KALIMPONG SM/11579 DETAIL PROJECT REPORT OF LOWER DARA GAON AND UPPER & LOWER GAIRI GAON PIPED WATER SUPPLY SCHEME (PWSS) UNDER SAMTHAR G.P, BLOCK:-KALIMPONG-I, P.S:-KALIMPONG, DISTRICT:KALIMPONG. New Junior Engineer-3,Junior Engineer-III 30/03/2022 249 312.68 312.68 0.00 14/10/2022 1 306.11 0.00 0 95
109 KALIMPONG SM/11806 Mayrong Forest & Tendrabong Village ( Partly) Piped Water Supply Scheme (PWSS) under Sakyong G.P, Block- Kalimpong-II, P.S- Kalimpong, District: Kalimpong. New Junior Engineer III 16/03/2022 139 204.57 204.57 0.00 12/08/2022 2 186.80 79.75 42.69 65
110 KALIMPONG SM/11955 DETAIL PROJECT REPORT OF Dr. GRAHAM'S HOME (PART) PIPED WATER SUPPLY SCHEME (PWSS) UNDER DR. GRAHAM'S HOME G.P, BLOCK:-KALIMPONG-I, P.S:-KALIMPONG, DISTRICT:KALIMPONG New Junior Engineer-2,Junior Engineer-II 20/05/2022 221 242.62 242.62 0.00 04/11/2022 1 229.27 0.00 0 100
111 KALIMPONG SM/12180 GRAVITY BASED WATER SUPPLY SCHEME FOR SEOKBIR KHASMAHAL PWSS IN KALIMPONG-1 BLOCK, UNDER KALIMPONG DISTRICT New Junior Engineer-2,Junior Engineer-II 20/05/2022 295 520.75 520.75 0.00 18/10/2022 1 400.34 0.00 0 100
112 KALIMPONG SM/12181 GRAVITY BASED WATER SUPPLY SCHEME FOR SINGI KAHSMAHAL PWSS IN KALIMPONG-I BLOCK New Junior Engineer-2,Junior Engineer-II 20/05/2022 514 695.67 695.67 0.00 03/11/2022 2 662.05 0.00 0 100
113 KALIMPONG SM/12629 PROPOSED GRAVITY BASED & PUMPING BASED PIPED WATER SUPPLY SCHEME FOR PEDONG KHASMAHAL (PART) UNDER PEDONG G.P, BLOCK : KALIMPONG - II, DISTRICT:KALIMPONG New Junior Engineer-4 20/05/2022 588 752.80 752.80 0.00 29/09/2022 2 733.03 376.40 51.35 40
114 KALIMPONG SM/12630 PROPOSED GRAVITY BASED & PUMPING BASED PIPED WATER SUPPLY SCHEME FOR KASHONE KHASMAHAL (PART) UNDER KASHONE G.P, BLOCK : KALIMPONG - II, DISTRICT:KALIMPONG New Junior Engineer-4,Junior Engineer-I 20/05/2022 530 939.41 939.41 0.00 28/11/2022 2 888.80 0.00 0 90
115 KALIMPONG SM/13602 MANOPONG FOREST (PART) PIPED WATER SUPPLY SCHEME New Junior Engineer-4,Junior Engineer-III 20/05/2022 445 335.49 335.49 0.00 20/01/2023 5 327.61 2.66 0.81 69
116 KALIMPONG SM/13603 LOLAY KHASMAHAL PIPED WATER SUPPLYSCHEME, BLOCK : KALIMPONG - II, DISTRICT :KALIMPONG New Junior Engineer-2,Junior Engineer-II 20/05/2022 664 341.66 341.66 0.00 01/02/2023 4 333.80 0.55 0.16 83
117 KALIMPONG SM/13604 DETAILED PROJECT REPORT FORPROPOSED GRAVETY BASED & PUMPING BASEDPIPED WATER SUPPLY SCHEME FOR BONGKHASMAHAL, BLOCK : KALIMPONG - I, DISTRICT: Kalimpong New Junior Engineer III 20/05/2022 1,015 564.20 564.20 0.00 14/12/2022 6 567.85 5.66 1 60
118 KALIMPONG SM/13605 GRAVETY BASED PIPED WATER SUPPLY SCHEME FOR SAKIYONG KHASMAHAL (PART), BLOCK : KALIMPONG - II, DISTRICT : Kalimpong New Junior Engineer-2,Junior Engineer-II 20/05/2022 991 419.43 419.43 0.00 04/05/2023 7 403.54 2.39 0.59 80
119 KALIMPONG SM/13606 DETAILED PROJECT REPORT FOR PROPOSED GRAVITY BASED WATER SUPPLY SCHEME FOR PUDDUNG KHAS MAHAL PWSS,BLOCK : KALIMPONG - I, DISTRICT : KALIMPONG New Junior Engineer-4 20/05/2022 692 427.72 427.72 0.00 24/07/2023 1 345.67 0.00 0 60
120 KALIMPONG SM/13607 SURUK PIPED WATER SUPPLY SCHEME New Junior Engineer-4,Junior Engineer-I 05/07/2022 338 643.20 643.20 0.00 09/02/2023 3 640.68 0.00 0 75
121 KALIMPONG SM/13608 GODAK BUSTY PIPED WATER SUPPLY SCHEME. New 05/07/2022 136 356.95 356.95 0.00 24/07/2023 1 350.72 0.00 0 50
122 KALIMPONG SM/13609 PAREN FOREST PIPED WATER SUPPLY SCHEME New 05/07/2022 46 133.18 133.18 0.00 17/07/2023 5 97.64 1.97 2.02 10
123 KALIMPONG SM/13610 AMBEOK TEA GARDEN PIPED WATER SUPPLY SCHEME New Junior Engineer-4,Junior Engineer-I 15/07/2022 309 260.67 260.67 0.00 20/01/2023 2 257.62 0.00 0 85
124 KALIMPONG SM/13611 SAMABIYONG TEA GARDEN PIPED WATER SUPPLY SCHEME. New Junior Engineer-4,Junior Engineer-I 15/07/2022 383 648.24 648.24 0.00 09/02/2023 3 645.11 4.25 0.66 90
125 KALIMPONG SM/13612 KUMAI FOREST PIPED WATER SUPPLY SCHEME. New 15/07/2022 245 290.97 290.97 0.00 05/06/2023 4 282.46 1.09 0.39 10
126 KALIMPONG SM/13613 SAMSING MIDDLE & UPPER PIPED WATER SUPPLY SCHEME. New 15/07/2022 303 351.35 351.35 0.00 26/05/2023 3 351.21 0.00 0 5
127 KALIMPONG SM/13615 PROPOSED GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR LAVA FOREST UNDER LAVA GITBEONG G.P, BLOCK : KALIMPONG - II, DISTRICT:KALIMPONG New Junior Engineer III 22/08/2022 35 101.26 101.26 0.00 01/02/2023 2 93.71 0.00 0 50
128 KALIMPONG SM/13616 PROPOSED PUMPING BASED PIPED WATER SUPPLY SCHEME FOR MARIA KHASMAHAL (PART) (UPPER RABEK) UNDER KAGAY G.P, BLOCK : KALIMPONG - II, DISTRICT:KALIMPONG New Junior Engineer III 22/08/2022 123 268.04 268.04 0.00 20/01/2023 4 271.84 0.92 0.34 15
129 KALIMPONG SM/13617 PROPOSED PUMPING BASED PIPED WATER SUPPLY SCHEME FOR GIT DUBLING KHASMAHAL (PART) (POCHAK HABITATION) UNDER GITDABLING G.P, BLOCK : KALIMPONG - II, DISTRICT:KALIMPONG New Junior Engineer-4,Junior Engineer-I 22/08/2022 240 442.25 442.25 0.00 14/12/2022 3 421.75 82.25 19.5 85
130 KALIMPONG SM/13621 PROPOSED PUMPING BASED PIPED WATER SUPPLY SCHEME FOR TURZUM FOREST UNDER TEESTA G.P, BLOCK : KALIMPONG - I, DISTRICT:KALIMPONG New Junior Engineer-2,Junior Engineer-II 22/08/2022 124 236.28 236.28 0.00 23/12/2022 6 254.88 0.00 0 90
131 KALIMPONG SM/13622 BINDU PIPED WATER SUPPLY SCHEME New Junior Engineer-4,Junior Engineer-I 22/08/2022 174 130.17 130.17 0.00 20/01/2023 2 123.46 0.00 0 75
132 KALIMPONG SM/13953 SAKAM FOREST & DARJILING HILLDOARS TEA GARDEN PWSS New Junior Engineer-4 22/08/2022 663 882.37 882.37 0.00 09/02/2023 3 882.57 0.00 0 60
133 KALIMPONG SM/13954 UPPER FAGU PIPED WATER SUPPLY SCHEME. New 22/08/2022 924 819.76 819.76 0.00 18/07/2023 4 808.19 0.00 0 5
134 KALIMPONG SM/14170 PANKHASARI KHASMAHAL PWSS New Junior Engineer III 22/08/2022 666 1,201.07 1,201.07 0.00 06/02/2023 2 1,197.70 0.00 0 50
135 KALIMPONG SM/14171 TODAY TANGTA KHASMAHAL PWSS New Junior Engineer III,Junior Engineer IV 22/08/2022 970 1,635.15 1,635.15 0.00 01/02/2023 8 1,601.74 0.00 0 5
136 KALIMPONG SM/14172 GORUBATHAN-I PWSS New Junior Engineer-4 22/08/2022 1,818 1,146.86 1,146.86 0.00 18/07/2023 2 1,132.56 0.00 0 20
137 KALIMPONG SM/14191 SANTUK KHASMAHAL PIPED WATER SUPPLYSCHEME, BLOCK : KALIMPONG - II, DISTRICT :KALIMPONG New Junior Engineer-3,Junior Engineer-I 20/05/2022 915 693.21 693.21 0.00 09/02/2023 4 678.65 0.00 0 60
138 KALIMPONG SM/14192 DETAILED PROJECT REPORT FOR PROPOSED GRAVETY BASED & PUMPING BASED PIPED WATER SUPPLY SCHEME FOR PEMLINGKHASMAHAL, BLOCK : KALIMPONG - I, DISTRICT : Kalimpong New Junior Engineer-4,Junior Engineer-I 20/05/2022 690 839.64 839.64 0.00 03/03/2023 6 798.06 0.00 0 85
139 KALIMPONG SM/14193 DETAILED PROJECT REPORT FOR PROPOSED GRAVETY BASED & PUMPING BASED PIPED WATER SUPPLY SCHEME FOR YANGMAKHUM KHAS MAHAL (Part) PWSS,BLOCK : KALIMPONG - I, DISTRICT : Kalimpong New Junior Engineer-3 20/05/2022 724 701.20 701.20 0.00 26/05/2023 2 649.45 0.00 0 10
140 KALIMPONG SM/14194 DETAILED PROJECT REPORT FOR PROPOSED GRAVITY BASED & PUMPING BASED WATER SUPPLY SCHEME FOR BHALUKHOP KHAS MAHAL PWSS, BLOCK : KALIMPONG - I, District : Kalimpong New Junior Engineer-2 20/05/2022 1,264 747.62 747.62 0.00 12/07/2023 3 739.94 0.00 0 50
141 KALIMPONG SM/15042 GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR LAVA FOREST (PART) UNDER LAVA GITBEONG G.P, BLOCK : KALIMPONG - II, DISTRICT:KALIMPONG New Junior Engineer IV 30/09/2022 161 213.24 213.24 0.00 09/02/2023 3 196.09 0.00 0 50
142 KALIMPONG SM/15463 GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR PANKHASARI KHASMAHAL (PART) UNDER GORUBATHAN II G.P, BLOCK : GORUBATHAN, DISTRICT:KALIMPONG New Junior Engineer III 30/09/2022 165 226.88 226.88 0.00 28/02/2023 3 48.72 0.00 0 10
143 KALIMPONG SM/15554 KUMAI FOREST (PART) & KUMAI TEA GARDEN PWSS New Junior Engineer-4,Junior Engineer-I 26/09/2022 278 248.56 248.56 0.00 03/03/2023 2 196.17 0.00 0 65
144 KALIMPONG SM/15640 PROPOSED GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR TISTA BAZAR DIF (PART) UNDER TEESTA G.P, BLOCK : KALIMPONG - I, DISTRICT:KALIMPONG New Junior Engineer-2,Junior Engineer-II 09/09/2022 685 497.43 497.43 0.00 28/02/2023 5 487.78 0.00 0 96
145 KALIMPONG SM/15641 PROPOSED GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR KALIMPONG DANSONG FOREST UNDER TEESTA G.P, BLOCK : KALIMPONG - I, DISTRICT:KALIMPONG New Junior Engineer-2,Junior Engineer-II 09/09/2022 275 214.02 214.02 0.00 28/02/2023 4 206.66 0.00 0 100
146 KALIMPONG SM/15642 PROPOSED PUMPING BASED PIPED WATER SUPPLY SCHEME FOR RAMBI BAZAR D I F UNDER TEESTA G.P, BLOCK : KALIMPONG - I, DISTRICT:KALIMPONG New Junior Engineer-2,Junior Engineer-II 09/09/2022 314 211.63 211.63 0.00 28/02/2023 4 208.04 96.35 46.31 99
147 KALIMPONG SM/15643 PROPOSED GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR LADAM KHASMAHAL (PART) UNDER KAGAY G.P, BLOCK:KALIMPONG - II, DISTRICT:KALIMPONG New Junior Engineer-2,Junior Engineer-II 09/09/2022 169 300.21 300.21 0.00 28/02/2023 2 284.60 0.00 0 85
148 KALIMPONG SM/15644 PROPOSED GRAVITY BASED & PUMPING BASED PIPED WATER SUPPLY SCHEME FOR GITDUBLING KHASMAHAL (PART) UNDER GITDUBLING G.P, BLOCK : KALIMPONG-II DISTRICT:KALIMPONG New Junior Engineer-4,Junior Engineer-I 09/09/2022 538 650.72 650.72 0.00 10/05/2023 3 629.87 0.00 0 57
149 KALIMPONG SM/15645 PROPOSED GRAVITY BASED & PUMPING BASED PIPED WATER SUPPLY SCHEME FOR GITBEONG KHASMAHAL UNDER LAVA GITBEONG G.P, BLOCK : KALIMPONG-II DISTRICT:KALIMPONG New Junior Engineer-4,Junior Engineer-I 09/09/2022 651 973.41 973.41 0.00 10/05/2023 2 943.34 0.00 0 68
150 KALIMPONG SM/15646 DETAIL PROJECT REPORT OF PALLA KHASMAHAL PIPED WATER SUPPLY SCHEME (PWSS) UNDER LOLAY G.P, BLOCK:-KALIMPONG-II, P.S:-KALIMPONG, DISTRICT:KALIMPONG New Junior Engineer-2,Junior Engineer-II 09/09/2022 171 226.84 226.84 0.00 28/02/2023 4 228.92 0.00 0 96
151 KALIMPONG SM/15937 KUMAI KHASMAHAL & KUMAI TEA GARDEN PWSS New Junior Engineer-4,Junior Engineer-I 09/09/2022 782 657.46 657.46 0.00 03/03/2023 2 642.32 0.00 0 75
152 KALIMPONG SM/16230 KALIMPONG KHASMAHAL (PART) PIPED WATER SUPPLY SCHEME UNDER TASHIDING G.P, BLOCK-KALIMPONG-I, DISTRICT:-KALIMPONG New Junior Engineer-4,Junior Engineer-I 28/12/2022 1,068 921.36 921.36 0.00 29/05/2023 3 919.45 0.00 0 70
153 KALIMPONG SM/16231 KALIMPONG KHASMAHAL (PART) PIPED WATER SUPPLY SCHEME UNDER KALIMPONG G.P, BLOCK:-KALIMPONG-I, DISTRICT:-KALIMPONG New Junior Engineer-I 28/12/2022 1,175 944.04 944.04 0.00 26/05/2023 2 855.25 0.00 0 50
154 KALIMPONG SM/16232 PROPOSED GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR YANG MAKUM KHASMAHAL (PART) UNDER YANGMAKUM G.P, BLOCK : KALIMPONG - I, DISTRICT:KALIMPONG New 28/12/2022 206 380.82 380.82 0.00 05/06/2023 2 378.20 0.00 0 0
155 KALIMPONG SM/16233 GRAVITY BASED AND PUMPING BASED PIPED WATER SUPPLY SCHEME FOR PAIYONG KHASMAHAL (PART) UNDER PAIYONG G.P, BLOCK : KALIMPONG - II, DISTRICT:KALIMPONG New Junior Engineer-2 28/12/2022 700 963.91 963.91 0.00 12/07/2023 2 882.06 0.00 0 75
156 KALIMPONG SM/16234 GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR MANGWA FOREST (PART) UNDER TEESTA G.P, BLOCK : KALIMPONG - I, DISTRICT:KALIMPONG New 28/12/2022 47 55.28 55.28 0.00 12/07/2023 4 55.59 2.27 4.08 10
157 KALIMPONG SM/16235 GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR KAGEY KHASMAHAL (PART) UNDER KAGEY G.P, BLOCK : KALIMPONG II, DISTRICT:KALIMPONG New 28/12/2022 199 233.82 233.82 0.00 12/07/2023 2 209.91 0.00 0 50
158 KALIMPONG SM/16511 LINGSAY KHASMAHAL PIPED WATER SUPPLY SCHEME UNDER BLOCK: KALIMPONG-II, DISTRICT:-KALIMPONG New Junior Engineer-4 28/12/2022 1,013 964.71 964.71 0.00 05/06/2023 2 932.62 0.00 0 70
159 KALIMPONG SM/16512 GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR YOKPRINTAM KHASMAHAL (PART) UNDER SAMTHAR G.P, BLOCK : KALIMPONG - I, DISTRICT:KALIMPONG New Junior Engineer III,Junior Engineer-3 28/12/2022 136 160.61 160.61 0.00 28/04/2023 6 159.97 0.00 0 60
160 KALIMPONG SM/16513 GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR RANGPOO FOREST UNDER SANGASEY G.P, BLOCK : KALIMPONG II, DISTRICT:KALIMPONG New Junior Engineer-2,Junior Engineer-II 28/12/2022 369 304.00 304.00 0.00 28/04/2023 5 263.12 0.00 0 100
161 KALIMPONG SM/16514 PROPOSED GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR LINGSAYKHA KHASMAHAL UNDER LINGSEKHA G.P, BLOCK : KALIMPONG - II, DISTRICT:KALIMPONG New Junior Engineer-3 28/12/2022 538 896.34 896.34 0.00 05/06/2023 2 879.30 0.00 0 20
162 KALIMPONG SM/16649 GRAVITY BASED BASED PIPED WATER SUPPLY SCHEME FOR DALAPCHAN KHASMAHAL (PART) UNDER DALAPCHAND G.P, BLOCK : KALIMPONG - II, DISTRICT:KALIMPONG New Junior Engineer-3 28/12/2022 351 437.66 437.66 0.00 28/04/2023 5 382.40 0.00 0 50
163 KALIMPONG SM/16854 PAGRAN BONG KHASMAHAL PWSS New Junior Engineer-2 28/12/2022 187 473.77 473.77 0.00 12/07/2023 4 391.06 0.00 0 90
164 KALIMPONG SM/18247 PROPOSED GRAVITY BASED & PUMPING BASED PIPED WATER SUPPLY SCHEME FOR DUNGRA KHASMAHAL (PART) UNDER DUNGRA G.P, BLOCK : KALIMPONG - I, DISTRICT:KALIMPONG New 28/12/2022 946 1,350.54 1,350.54 0.00 18/07/2023 2 1,232.78 0.00 0 0
165 KALIMPONG SM/18255 PATEN GODAK KHASMAHAL PWSS New 15/07/2022 874 1,128.06 1,128.06 0.00 17/07/2023 4 1,123.22 0.00 0 5
166 KALIMPONG SM/18322 GRAVITY BASED WATER SUPPLY SCHEME FOR ICHA KHASMAHAL PWSS, BLOCK: -KALIMPONG-I, DISTRICT: KALIMPONG New 20/05/2022 1,196 1,040.03 1,040.03 0.00 18/07/2023 4 928.00 0.00 0 10
167 KALIMPONG SM/18415 NIM KHASMAHAL & PHASINTING KHASMAL PWSS New Junior Engineer-2 05/07/2022 475 1,069.70 1,069.70 0.00 17/08/2023 2 957.24 0.00 0 80
168 KALIMPONG SM/18442 Augmentation of source cum creation of spring water storage of 80 ML water by improvement of and upgradation of Open Ground Reservoir /Lake at 3.2 Km from Algarah and other allied works to cover the uncovered areas of Kalimpong Block-I & Kalimpong Block-I Augmentation 28/12/2022 3,573 3,858.84 3,858.84 0.00 06/12/2023 3 3,837.59 0.00 0 50
169 KALIMPONG SM/18443 Providing piped water Supply Scheme for Fourteen 14 Nos of villages (part) under Kalimpong Block-I & Kalimpong Block-II in the district of Kalimpong under Neorakhola water Supply & Maintenance Division PHE Dte. New 28/12/2022 3,512 3,488.92 3,488.92 0.00 28/02/2023 22 2,929.12 0.00 0 50
170 KALIMPONG SM/18589 WATER SUPPLY SCHEME FOR LOLAY KHASMAHAL PWSS IN KALIMPONG II BLOCK UNDER KALIMPONG DISTRICT. New Junior Engineer-4 28/12/2022 1,130 1,104.14 1,104.14 0.00 07/08/2023 1 1,057.74 0.00 0 75
171 KALIMPONG SM/18823 RANGO FOREST PWSS New 15/07/2022 1,892 1,664.29 1,664.29 0.00 21/09/2023 2 1,661.53 0.00 0 50
172 KALIMPONG SM/19112 DALINGKOT FOREST & DALINGMA KHASMAHAL PWSS New 15/07/2022 784 1,414.95 1,414.95 0.00 03/01/2024 3 1,408.44 0.00 0 100
173 KALIMPONG SM/19176 PROJECT REPORT FOR WATER SUPPLY SCHEME FOR SANGSER KHASMAHAL PWSS IN KALIMPONG II BLOCK UNDER KALIMPONG DISTRICT. New 22/08/2022 1,749 2,560.38 2,560.38 0.00 20/02/2024 11 2,452.06 0.00 0 10
Total 67,062 72,816.30 72,816.30 0.00 # 525 67,751.79 8,692.92 # #