H2- Exception Report on Scheme

Update Data
Rs. in Lakh
Sl. No. Division District Block Scheme Name Scheme Category Sub Division Name of AE entrusted Name of JE entrusted Date of Sanction Date of Commencement Target Date of Completion Date Of Updation Work Order Issued FHTCs Sanctioned Cost Payment Physical Progress (in %) Financial Progress (in %)
11 33 4,303 2,836.09 410.12   14
1 Kurseong Division DARJEELING Kurseong Providing Functional Household Tap Connection under Jal Jeevan Mission and Jal Swapno Programme for Piped Water Supply Scheme (9 Nos.) under GTA. [Volume No-III],SM/10262 Retrofitting Neorakhola W/S Mnt. Division Assistant Engineer Sub-Assistant Engineer 08/02/2021 08/05/2021 30/04/2022 12 817 159.17 75.90 0 48
2 Kurseong Division DARJEELING Jorebunglow Sukiapokhri Providing Functional Household Tap Connection under Jal Jeevan Mission and Jal Swapno Programme for Piped Water Supply Scheme (5 Nos.) under GTA. [Volume No-II],SM/10263 Retrofitting 08/02/2021 08/05/2021 30/04/2022 6 312 39.28 19.82 0 50
3 Kurseong Division DARJEELING Kurseong Providing Functional Household Tap Connection under Jal Jeevan Mission and Jal Swapno Programme for Piped Water Supply Scheme (5 Nos.). [Volume No-I],SM/10264 Retrofitting 08/02/2021 08/05/2021 30/04/2022 6 1,124 108.57 72.81 0 67
4 Kurseong Division DARJEELING Kurseong PWS Scheme for Gayabari Tea Garden with FHTC under JJM/JSP.,SM/15650 New Kurseong Division Assistant Engineer5 Junior Engineer1,Sub-Assistant Engineer 17/02/2023 28/02/2023 17/08/2024 28/05/2024 2 229 210.61 0.00 46 0
5 Kurseong Division DARJEELING Kurseong PWS Scheme for Selim Hill Tea Garden,SM/15652 New Kurseong Division Assistant Engineer5 Junior Engineer1,Sub-Assistant Engineer 17/02/2023 09/03/2023 17/08/2024 30/11/2023 2 384 967.91 192.42 48 20
6 Kurseong Division DARJEELING Kurseong PWS scheme for St. Mary's & Goethals ,SM/15661 New Kurseong Division Assistant Engineer 4,Assistant Engineer4 Junior Engineer4,Sub-Assistant Engineer 17/02/2023 01/03/2023 17/08/2024 16/10/2023 3 675 338.76 0.00 9 0
7 Kurseong Division DARJEELING Mirik RANGMOHAN PIPED WATER SUPPLY SCHEME,SM/15880 New Kurseong Division Assistant Engineer 2,Assistant Engineer2 Junior Engineer5,Sub-Assistant Engineer 20/02/2023 03/08/2023 20/08/2024 11/01/2024 2 172 327.70 49.17 47 15
8 Kurseong Division DARJEELING Kurseong AUGMENTATION OF SIMULBARI TEA GARDEN AREA PIPED WATER SUPPLY SCHEME,SM/18878 Augmentation 05/10/2023 05/04/2024 06/10/2023 0 161 199.02 0.00 0 0
9 Kurseong Division DARJEELING Kurseong AUGMENTATION OF PAIRIKUMARI PIPED WATER SUPPLY SCHEME,SM/18879 Augmentation 05/10/2023 05/04/2024 06/10/2023 0 80 93.17 0.00 0 0
10 Kurseong Division DARJEELING Kurseong AUGMENTATION OF GARIDHORA (M.BARI) TEA GARDEN AREA PIPED WATER SUPPLY SCHEME,SM/18880 Augmentation 05/10/2023 05/04/2024 06/10/2023 0 190 197.84 0.00 0 0
11 Kurseong Division DARJEELING Naxalbari Augmentation of Nipania Piped Water Supply Scheme.,SM/18881 Augmentation 05/10/2023 05/04/2024 06/10/2023 0 159 194.06 0.00 0 0
Total 33 4,303 2,836.09 410.12   14