Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
12 21,793.65 164.1 0.75  
1 JHARGRAM Gopiballavpur - I,Gopiballavpur - II Central Drilling GOHAL BURA AND ADJOINING MOUJAS PWSS , SM/17585 New Construction of Big Diameter Tube-Well by Deploying of Suitable Capacity Drilling Rig (Direct Rotary, Reverse Rotary, Odex Method) at Different Districts for Different Water Supply Schemes Including Procurement & Installation Pumping Machinery with All Allied Accessories at the Above Constructed Tube-Wells Under JJM Program throughout the State of West Bengal. (2ed call of NIET 25 of 2022-23) Assistant Engineer,Driller In Charge Junior Engineer ORD/000001/2023-2024 1415/CDD 21/09/2023 300 JHARGRAM SPV PRIVATE LIMITED 21,339.76 0.00 0 11
2 JHARGRAM Gopiballavpur - I,Gopiballavpur - II Jhargram Division GOHAL BURA AND ADJOINING MOUJAS PWSS , SM/17585 New Construction of Laying distribution pipe line under JJM with allied work for GOHAL BURA AND ITS ADJOINING MOUJAS PWSS in GOPIBALLAVPUR-I Block including supply of all labour and materials within Jhargram Sub-Division under Jhargram Division, PHE Dte. (Part-B) Assistant Engineer Junior Engineer-III ORD/000039/2023-2024 865/JHD 08/06/2023 90 ASIS KUMAR SARANGI 30.88 26.04 84.33 85
3 JHARGRAM Gopiballavpur - I,Gopiballavpur - II Jhargram Division GOHAL BURA AND ADJOINING MOUJAS PWSS , SM/17585 New Construction of Laying distribution pipe line under JJM with allied work for GOHAL BURA AND IT'S ADJOINING MOUJAS PWSS in GOPIBALLAVPUR-I Block including supply of all labour & materials within Jhargram Sub-Division under Jhargram Division, PHE Dte. (Part-C) Assistant Engineer Junior Engineer-III ORD/000046/2023-2024 866/JHD 08/06/2023 90 ASIS KUMAR SARANGI 66.32 47.09 71 75
4 JHARGRAM Gopiballavpur - I,Gopiballavpur - II Jhargram Division GOHAL BURA AND ADJOINING MOUJAS PWSS , SM/17585 New Construction of Laying distribution pipe line under JJM with allied work for GOHAL BURA AND IT'S ADJOINING MOUJAS PWSS in GOPIBALLAVPUR-I Block including supply of all labour & materials within Jhargram Sub-Division under Jhargram Division, PHE Dte. (Part-D) Assistant Engineer Junior Engineer-III ORD/000049/2023-2024 867/JHD 08/06/2023 90 ASIS KUMAR SARANGI 61.58 49.33 80.11 75
5 JHARGRAM Gopiballavpur - I,Gopiballavpur - II Jhargram Division GOHAL BURA AND ADJOINING MOUJAS PWSS , SM/17585 New Construction of Laying distribution pipe line under JJM with allied work for GOHAL BURA AND IT'S ADJOINING MOUJAS PWSS in GOPIBALLAVPUR-I Block including supply of all labour & materials within Jhargram Sub-Division under Jhargram Division, PHE Dte. 2nd Call (Ref eNIT_24 of 2022-23 , SL No.-2 ) Assistant Engineer Junior Engineer-III ORD/000159/2023-2024 1400/JHD 18/08/2023 90 SRIMANTA KUMAR DE 45.02 22.04 48.96 96
6 JHARGRAM Gopiballavpur - I,Gopiballavpur - II Jhargram Division GOHAL BURA AND ADJOINING MOUJAS PWSS , SM/17585 New Accommodate FHTC ( 1558 nos) under JJM with allied work for GOHAL BURA AND IT'S ADJOINING MOUJAS PWSS in GOPIBALLAVPUR-I Block including supply of all labour & materials within Jhargram Sub-Division under Jhargram Division, PHE Dte. Assistant Engineer Junior Engineer-III ORD/000161/2023-2024 1401/JHD 18/08/2023 90 M/S. D.K.H.CONSTRUCTION 64.91 8.65 13.33 60
7 JHARGRAM Gopiballavpur - I,Gopiballavpur - II Jhargram Division GOHAL BURA AND ADJOINING MOUJAS PWSS , SM/17585 New Sinking of Tube Well , Pump House , 200 cum OHR, Rising main pipe line, Interconnection pipe line, Laying distribution pipe line, Installation of display Board, soil investigation under JJM with allied work for GOHAL BURA AND IT'S ADJOINING MOUJAS PWSS in GOPIBALLAVPUR-I Block including supply of all labour & materials within Jhargram Sub-Division under Jhargram Division, PHE Dte. 3rd Call (Ref 1st Call eNIT_24 of 2022-23 , SL No.-1, 2nd Call eNIT_07 of 2023-24 , SL No.-3 ) Assistant Engineer Junior Engineer-III ORD/000421/2023-2024 86/JHD 17/01/2024 210 ANUSKA ENTERPRISE 131.40 10.95 8.33 15
8 JHARGRAM Gopiballavpur - I,Gopiballavpur - II Jhargram Division GOHAL BURA AND ADJOINING MOUJAS PWSS , SM/17585 New Material Requisition To Resource Division RTOR000076/2023-2024 1599/JHD 08/09/2023 Resource Division 40.95 0.00 0 0
9 JHARGRAM Gopiballavpur - I,Gopiballavpur - II Jhargram Mechanical Division GOHAL BURA AND ADJOINING MOUJAS PWSS , SM/17585 New ADDITIONAL Quotation for new service connection at GOHALBURA T/W-II water supply scheme. BILL/00174/2024-2025 101/JMD 08/05/2024 WBSEDCL 3.32 0.00 0 null
10 JHARGRAM Gopiballavpur - I,Gopiballavpur - II Jhargram Mechanical Division GOHAL BURA AND ADJOINING MOUJAS PWSS , SM/17585 New Supply of diesel and lubricants for KLR/DR/DTH-500 unit during PWSS works under JJM ( scheme code SM/17585 ) BILL/01025/2024-2025 null 12/09/2024 SURAJ SERVICE STATION 0.80 0.00 0 null
11 JHARGRAM Gopiballavpur - I,Gopiballavpur - II Jhargram Mechanical Division GOHAL BURA AND ADJOINING MOUJAS PWSS , SM/17585 New New Service connection charges. BILL/01328/2023-2024 95/JMD 22/02/2024 WBSEDCL 2.86 0.00 0 0
12 JHARGRAM Gopiballavpur - I,Gopiballavpur - II Jhargram Mechanical Division GOHAL BURA AND ADJOINING MOUJAS PWSS , SM/17585 New New Service connection charges. BILL/01329/2023-2024 96/JMD 22/02/2024 WBSEDCL 5.85 0.00 0 0
Total 21,793.65 164.10 0.75