Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 508.85 231.06 45.41  
1 JHARGRAM Jhargram Jhargram Division BARABARI AND ADJOINING MOUJAS PWSS , SM/12722 New Sinking of Tube Well , Pump House , 100 cum OHR, & 100 cum GLR, Rising main pipe line, Interconnection pipe line, Laying distribution pipe line, Installation of display Board, soil investigation & Accommodate FHTC (883 nos) under JJM with allied work including 02(Two) Years Operation & Maintenanace for BARABARI AND IT'S ADJOINING MOUJAS PWSS in JHARGRAM Block including supply of all labour & materials within Jhargram Sub-Division under Jhargram Division, PHE Dte. Assistant Engineer Headquarter Junior Engineer-II ORD/000038/2023-2024 851/JHD 08/06/2023 180 ASIS KUMAR SARANGI 408.94 222.40 54.38 70
2 JHARGRAM Jhargram Jhargram Division BARABARI AND ADJOINING MOUJAS PWSS , SM/12722 New Construction of boundary wall and Allied works At Chandri, Barabari, Gramohan 1st and 2nd Tubewell site of public water supply schemes in Jhargram block within Jhargram District under Jhargram Division P.H.E Dte. Assistant Engineer Headquarter Junior Engineer-II ORD/000098/2024-2025 1282/JHD 03/09/2024 30 ASIS KUMAR SARANGI 37.46 0.00 0 0
3 JHARGRAM Jhargram Jhargram Division BARABARI AND ADJOINING MOUJAS PWSS , SM/12722 New Material Requisition To Resource Division RTOR000077/2023-2024 1602/JHD 08/09/2023 Resource Division 28.74 0.00 0 0
4 JHARGRAM Jhargram Jhargram Mechanical Division BARABARI AND ADJOINING MOUJAS PWSS , SM/12722 New New service connection charges. BILL/00780/2023-2024 20/JMD 08/12/2023 WBSEDCL 9.92 0.00 0 0
5 JHARGRAM Jhargram Jhargram Mechanical Division BARABARI AND ADJOINING MOUJAS PWSS , SM/12722 New New Service connection charges. BILL/01361/2023-2024 24/JMD 04/03/2024 WBSEDCL 3.00 0.00 0 0
6 JHARGRAM Jhargram Jhargram Mechanical Division BARABARI AND ADJOINING MOUJAS PWSS , SM/12722 New Supply, delivery, installation, commissioning & trial run of electro-mechanical components at T/W no. I & II and making compound lighting arrangement at T/W no. I of Barabari & adjoining moujas piped water supply scheme in the district of Jhargram under Jhargram Mechanical Division, PHE. Dte. Assistant Engineer JE (M) ORD/000033/2023-2024 1231/JMD 26/05/2023 180 KAMAKHYA ENTERPRISE 20.79 8.66 41.65 65
Total 508.85 231.06 45.41