Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
12 1,023.58 436.16 42.61  
1 JHARGRAM Midnapore Division Retrofitting to accommodate FHTC under JJM in Nayagram Block (Part) PWSS. , SM/09384 Retrofitting Material Requisition To Resource Division RTOR000009/2022-2023 355 29/09/2022 Resource Division 0.22 0.00 0 0
2 JHARGRAM Jhargram Division Retrofitting to accommodate FHTC under JJM in Nayagram Block (Part) PWSS. , SM/09384 Retrofitting Laying Of Balance Distribution System of HDPE (Pe-100- Pn-6) And D.I. (K-7) Pipe For Zone - Viii-B & Xiii-A Of Sub- Surface Water Supply Scheme For Nayagram Block (Part) Under Jhargram Sub-Division P.H.E. Dte. Of Jhargram Division P.H.E.Dte. Assistant Engineer Junior Engineer-III ORD/000004/2024-2025 801/JHD 06/06/2024 30 SUBHRANIL DAS 25.56 0.00 0 0
3 JHARGRAM Jhargram Division Retrofitting to accommodate FHTC under JJM in Nayagram Block (Part) PWSS. , SM/09384 Retrofitting Retrofitting to Accommodate FHTC for Sub-Surface Water Based Piped Water Supply Scheme in Nayagram Block (Part) under JJM under Jhargram Division P.H.E. Dte. Assistant Engineer Junior Engineer-II ORD/000042/2022-2023 805/MD 28/04/2022 180 GOBINDA MAITY 659.49 338.14 51.27 100
4 JHARGRAM Jhargram Division Retrofitting to accommodate FHTC under JJM in Nayagram Block (Part) PWSS. , SM/09384 Retrofitting Continuation Order for the Work of "Retrofitting to Accommodate FHTC for Sub-Surface Water Based Piped Water Supply Scheme in Nayagram Block (Part) under JJM under Jhargram Division P.H.E. Dte. (For Zone VIII-B)" Junior Engineer-II ORD/000078/2022-2023 337/JHD 26/09/2022 60 GOBINDA MAITY 95.26 79.83 83.8 1
5 JHARGRAM Jhargram Division Retrofitting to accommodate FHTC under JJM in Nayagram Block (Part) PWSS. , SM/09384 Retrofitting Erection of scaffolding with necessary cross bracing and fixtures and removal after condition assesment for the OHR of Zone-IX of Nayagram (Part) W/S Scheme within Nayagram Dev. Block of Jhargram Division P.H.E Dte. Assistant Engineer Junior Engineer-II ORD/000085/2023-2024 663/JSD 21/07/2023 21 SUNIL DULE 2.29 2.29 100 100
6 JHARGRAM Jhargram Division Retrofitting to accommodate FHTC under JJM in Nayagram Block (Part) PWSS. , SM/09384 Retrofitting Construction of Neutralization Pit at Khanamuri, under Nayagram block (part) sub-surface base water supply scheme under Jhargram Division P.H.E.Dte. (Part-A) & Construction of Neutralization Pit at Barasukjora under Jhargram Division P.H.E.Dte. (Part-B) Junior Engineer-II ORD/000232/2022-2023 541/JSD 23/09/2022 30 MAHAVIR SAMPARK PVT. LTD. 0.29 0.00 0 100
7 JHARGRAM Jhargram Division Retrofitting to accommodate FHTC under JJM in Nayagram Block (Part) PWSS. , SM/09384 Retrofitting Hiring of 1 (one) no, Motor Cab (standard) Commercial with Catalytic Converter attachment with Bharat Stage as per prevalent applicable standard compliant new not older than 30 (thirty) months from the date of 1st registration on daily hire rate basis for 04 (Four) months only having contract carriage permit for plying within West Bengal from Regional Transport Authority for the use of the Assistant Engineer, Jhargram Sub-Division PHE Dte.(from 01.01.2023 to 30.04.2023) Assistant Engineer ORD/000241/2022-2023 761/JSD 30/12/2022 120 BIDYUT KUMAR SANTRA 0.67 1.34 200 99
8 JHARGRAM Jhargram Division Retrofitting to accommodate FHTC under JJM in Nayagram Block (Part) PWSS. , SM/09384 Retrofitting Functional Household Tap Connection data uploading charges of different pwss under Jhargram District in JJM_IMIS portal under Jal Jeevan Mission for January-2023 and February-2023 under Jhargram Division, PHE Dte. Assistant Engineer ORD/000253/2022-2023 29A/JRWS 28/12/2022 60 PROVAT KUMAR DE 0.93 0.00 0 100
9 JHARGRAM Jhargram Division Retrofitting to accommodate FHTC under JJM in Nayagram Block (Part) PWSS. , SM/09384 Retrofitting Lay Left Out Different Dia Pipe with Balace F.H.T.C (700 Nos), Of Nayagram (part) Sub-Surface based pipe water supply scheme under Nayagram Dev. Block under Gopiballavpur Sub-Division of Jhargram Division PHE Dte. the District of Jhargram. Assistant Engineer Junior Engineer-II ORD/000340/2023-2024 1871/JHD 01/11/2023 45 GOBINDA MAITY 101.65 12.84 12.63 36
10 JHARGRAM Jhargram Division Retrofitting to accommodate FHTC under JJM in Nayagram Block (Part) PWSS. , SM/09384 Retrofitting Supply delivery of DI Specials, for the work of Nayagram Block (Part) Sub Surface Based Water Supply Scheme under Gopiballavpur Sub Division of Jhargram Division, PHE Dte. Assistant Engineer The Junior Engineer-IV Jhargram Sub-Division ORD/000389/2023-2024 464/GPSD 12/12/2023 15 S.B.TRADERS 3.44 1.72 50 100
11 JHARGRAM Jhargram Division Retrofitting to accommodate FHTC under JJM in Nayagram Block (Part) PWSS. , SM/09384 Retrofitting Retrofitting to Accommodate FHTC for Sub-Surface Water Based Piped Water Supply Scheme in Nayagram Block (Part) under JJM under Jhargram Division P.H.E. Dte. VCH/000002/2022-2023 null 19/07/2022 GOBINDA MAITY 73.78 0.00 0 0
12 JHARGRAM Jhargram Division Retrofitting to accommodate FHTC under JJM in Nayagram Block (Part) PWSS. , SM/09384 Retrofitting Retrofitting to Accommodate FHTC for Sub-Surface Water Based Piped Water Supply Scheme in Nayagram Block (Part) under JJM under Jhargram Division P.H.E. Dte. VCH/000020/2022-2023 null 12/08/2022 GOBINDA MAITY 60.00 0.00 0 0
Total 1,023.59 436.15 42.61