Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
11 643.34 362.71 56.38  
1 ALIPURDUAR Alipurduar - II Alipurduar Division CHALNIPAK PIPED WATER SUPPLY SCHEME. , SM/15534 New Providing balance FHTC for CHALNIPAK PWSS under Alipurduar Division, PHE Dte. Alipurduar Sadar Sub Division RWS Madarihat - Birpara Block ORD/000214/2023-2024 1568/ALD 23/08/2023 45 SOUVIK ROY PALADHI 9.97 0.00 0 0
2 ALIPURDUAR Alipurduar - II Alipurduar Division CHALNIPAK PIPED WATER SUPPLY SCHEME. , SM/15534 New Laying of new UPVC/DI pipeline for interconnection in the distribution system and bridge/ culvert crossing , Land developement works , Constructions of surface drain , pathway and others allied works in connection with the Chalnipak PWSS Alipurduar Sadar Sub-Division, under Alipurduar Division PHE DTE. .(SM/15534) HQ-A.E JUNIOR ENGINEER ORD/000223/2024-2025 2276/ALD 05/08/2024 60 SOUVIK ROY PALADHI 77.22 0.00 0 0
3 ALIPURDUAR Alipurduar - II Alipurduar Division CHALNIPAK PIPED WATER SUPPLY SCHEME. , SM/15534 New Supply of CIDF & CISS Pipes and specials for Chalnipak WSS Under Alipurduar Division P.H.E Dte. Alipurduar Sadar Sub Division JUNIOR ENGINEER ORD/000238/2023-2024 1607/ALD 25/08/2023 30 SOUVIK ROY PALADHI 7.89 0.00 0 0
4 ALIPURDUAR Alipurduar - II Alipurduar Division CHALNIPAK PIPED WATER SUPPLY SCHEME. , SM/15534 New Constructions of pump house and Sinking of 250 mm x 200 mm X 150 mtr Big dia Tubewel at HW site , 2nd site and 3 rd Site Laying of distribution system with UPVC pipeline , Constructions of 200 Cum OHR as per Departmental Design and drawing , including the Soil investigation works providing FHTC and others allied works for Chalnipak PWSS Under Alipurduar Division PHE DTE. Alipurduar Sadar Sub Division JUNIOR ENGINEER ORD/000472/2022-2023 3156/ALD 22/02/2023 180 SOUVIK ROY PALADHI 481.77 362.71 75.29 50
5 ALIPURDUAR Alipurduar - II Alipurduar Division CHALNIPAK PIPED WATER SUPPLY SCHEME. , SM/15534 New Material Requisition To Resource Division RTOR000018/2023-2024 224/ALD 03/05/2023 Resource Division 13.14 0.00 0 0
6 ALIPURDUAR Alipurduar - II Alipurduar Division CHALNIPAK PIPED WATER SUPPLY SCHEME. , SM/15534 New Material Requisition To Resource Division RTOR000051/2023-2024 2399/ALD 08/11/2023 Resource Division 10.15 0.00 0 0
7 ALIPURDUAR Alipurduar - II Northern Mechanical Division II CHALNIPAK PIPED WATER SUPPLY SCHEME. , SM/15534 New NEW SERVICE CONNECTIO CHARGE FOR CHALNIPAK W/S/S P/H NO.2 BILL/00596/2023-2024 BP-2023-24-177 15/06/2023 WBSEDCL 1.41 0.00 0 0
8 ALIPURDUAR Alipurduar - II Northern Mechanical Division II CHALNIPAK PIPED WATER SUPPLY SCHEME. , SM/15534 New QUOTATION FOR NEW SERVICE CONNECTION AT CHALNIPAK PWSS P/H NO-III BILL/01446/2023-2024 BP-2023-24-286 21/08/2023 WBSEDCL 5.44 0.00 0 0
9 ALIPURDUAR Alipurduar - II Northern Mechanical Division II CHALNIPAK PIPED WATER SUPPLY SCHEME. , SM/15534 New QUOTATION FOR NEW SERVICE CONNECTION AT CHALNIPAK PWSS P/H NO. I BILL/01447/2023-2024 BP-2023-24-291 21/08/2023 WBSEDCL 8.12 0.00 0 0
10 ALIPURDUAR Alipurduar - II Northern Mechanical Division II CHALNIPAK PIPED WATER SUPPLY SCHEME. , SM/15534 New ADDITIONAL QUOTATION FOR CHALNIRPAK PH NO-III BILL/02960/2023-2024 BP-06/24-25 08/04/2024 WBSEDCL 0.38 0.00 0 null
11 ALIPURDUAR Alipurduar - II Northern Mechanical Division II CHALNIPAK PIPED WATER SUPPLY SCHEME. , SM/15534 New Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Chalnipak water supply scheme, TW no I,II and III under Jal Jeevan Mission under NMD-II, PHE Dte.APD Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 2,Alipurduar Mechanical sub-division,PH ORD/000741/2023-2024 2287/NMD-II 31/07/2023 30 QUAZI NOZRUL ISLAM 27.85 0.00 0 0
Total 643.34 362.71 56.38