Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
3 76.45 20.91 27.35  
1 ALIPURDUAR Alipurduar Division REJUVENATION OF 'BAKLA WATER SUPPLY SCHEME' , SM/09890 Augmentation Construction of Pump House ,Boundary Wall , Tube well Boring ( Reverse Rotary Method)and Rising Main for Additional T/W of BAKLA Piped Water Supply Scheme Under Alipurduar Division PHE DTE Alipurduar Sadar Sub Division RWS Alipurduar - II Block ORD/000314/2021-2022 2190/ALD 11/01/2022 90 SHYAMAL ROY 21.81 10.18 46.68 100
2 ALIPURDUAR Alipurduar Division REJUVENATION OF 'BAKLA WATER SUPPLY SCHEME' , SM/09890 Augmentation Extension of pipeline (UPVC) and providing FHTC at surrounding area of Bakla PWSS Under Alipurduar Division, PHE DTE. Alipurduar Sadar Sub Division RWS Alipurduar - II Block ORD/000444/2021-2022 2753/ALD 24/02/2022 60 BENGAL YOUTH UN EMPLOYED ENGINEERS CO OPERATIVE SOCIETY LIMITED 43.78 0.00 0 42.75
3 ALIPURDUAR Northern Mechanical Division II REJUVENATION OF 'BAKLA WATER SUPPLY SCHEME' , SM/09890 Augmentation Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for REJUVINATION OF BAKLA water supply scheme, TW no III under Jal Jeevan Mission under NMD-II, PHE Dte.APD Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 2,Alipurduar Mechanical sub-division,PH ORD/000822/2022-2023 478/NMD-II 02/03/2023 30 M/S A.D. ENTERPRISE 10.86 10.73 98.8 80
Total 76.46 20.92 27.36