Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
3 | 141.11 | 21.1 | 14.95 | ||||||||||||||
1 | ALIPURDUAR | Alipurduar - I | Alipurduar Division | Parpatla Khawa Piped Water Supply Scheme , SM/18158 | New | Boring of Tube Well by reverse rotary method, Construction of Pump House, Boundary Wall, Laying Of Distribution System and providing FHTC for Parpatlakhawa PWSS under Alipurduar Division, PHE Dte. | Alipurduar RWS | JUNIOR ENGINEER,RWS Madarihat - Birpara Block | ORD/000017/2023-2024 | 235/ALD | 04/05/2023 | 240 | ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. | 113.69 | 21.10 | 18.56 | 16 |
2 | ALIPURDUAR | Alipurduar - I | Northern Mechanical Division II | Parpatla Khawa Piped Water Supply Scheme , SM/18158 | New | NEW SERVICE CONNECTION CHARGES FOR PAR PATLAKHAWA PWSS P/H NO-I | BILL/03128/2023-2024 | BP-235/24-25 | 29/07/2024 | WBSEDCL | 6.17 | 0.00 | 0 | null | |||
3 | ALIPURDUAR | Alipurduar - I | Northern Mechanical Division II | Parpatla Khawa Piped Water Supply Scheme , SM/18158 | New | Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for PARPATLA KHAWA water supply scheme, TW no I and II of under JJM under NMD-II, PHE Dte. APD. | Assistant Engineer,Alipurduar Mechanical Sub-Division,P | Junior Engineer 2,Alipurduar Mechanical sub-division,PH | ORD/000993/2023-2024 | 2625/NMD-II | 25/08/2023 | 30 | HARA PROSAD DAS | 21.25 | 0.00 | 0 | 0 |
Total | 141.12 | 21.10 | 14.95 |