Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 784.83 173.85 22.15  
1 ALIPURDUAR Falakata Alipurduar Division UMACHARANPUR PIPED WATER SUPPLY SCHEME , SM/16114 New Laying of rising main DI (K7), interconnection work with HDPE pipe , Construction of sluice valve chamber for Umacharanpur PWSS under Birpara Sub- Division ,Alipurduar Division PHE Dte. under North Bengal Circle-I PHE DTE. Birpara A.E RWS Falakata Block ORD/000210/2024-2025 2061/ALD 12/07/2024 300 TAPASH KUMAR BHOWMICK 101.24 46.59 46.02 90
2 ALIPURDUAR Falakata Alipurduar Division UMACHARANPUR PIPED WATER SUPPLY SCHEME , SM/16114 New Construction of tubewells (2 nos.) by Reverse rotary method of drilling at HW site and 2nd TW site, Soil investigation at OHR site, constructions of 500 Cum OHR at HW, construction of pump house and boundary wall at H/W and 2nd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for Uma Charanpur PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. Birpara A.E RWS Falakata Block ORD/000251/2023-2024 1873/ALD 07/09/2023 270 TAPASH KUMAR BHOWMICK 608.41 121.28 19.93 37
3 ALIPURDUAR Falakata Alipurduar Division UMACHARANPUR PIPED WATER SUPPLY SCHEME , SM/16114 New Supply of CI Sluice Valve and Special & CI Jeffy Coupling for Umachndrapur Water Supply Scheme under Alipurduar Division P.H.E. Dte. Alipurduar Sadar Sub Division Birpara Sub Division ORD/000465/2023-2024 608/ALD 29/02/2024 30 MANSAROVAR CASTING 11.95 5.98 50.04 85
4 ALIPURDUAR Falakata Alipurduar Division UMACHARANPUR PIPED WATER SUPPLY SCHEME , SM/16114 New Material Requisition To Resource Division RTOR000065/2023-2024 2775/ALD 18/12/2023 Resource Division 18.81 0.00 0 0
5 ALIPURDUAR Falakata Northern Mechanical Division II UMACHARANPUR PIPED WATER SUPPLY SCHEME , SM/16114 New New Service Connection Charges for UMACHARANPUR PWSS P/H NO-I,10 mile BILL/00050/2024-2025 BP-10/24-25 08/04/2024 WBSEDCL 12.04 0.00 0 null
6 ALIPURDUAR Falakata Northern Mechanical Division II UMACHARANPUR PIPED WATER SUPPLY SCHEME , SM/16114 New New Service Connection for Umacharanpur PH NO-II PWSS BILL/00987/2024-2025 BP-276/24-25 22/08/2024 WBSEDCL 10.48 0.00 0 null
7 ALIPURDUAR Falakata Northern Mechanical Division II UMACHARANPUR PIPED WATER SUPPLY SCHEME , SM/16114 New Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Umacharanpur Water Supply Scheme TW No.-I and II under NMD-II,PHE.Dte,Apd. Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 1, Northern Mechanical Division-II,PHE ORD/000895/2023-2024 2476/NMD-II 11/08/2023 30 CINZANO 21.90 0.00 0 0
Total 784.81 173.84 22.15