Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 566.56 252.8 44.62  
1 ALIPURDUAR Falakata Alipurduar Division DHANIRAMPUR PIPED WATER SUPPLY SCHEME , SM/15208 New Laying of rising main, delivery main, bypass arrangement, Laying of HDPE Pipeline for left out household connection and other allied works at Dhanirampur PWSS (both H/W and 2nd site) of Birpara Sub-Division under Alipurduar Division, P.H.E. Dte. (SM/15208) Birpara A.E RWS Falakata Block ORD/000511/2023-2024 829/ALD 14/03/2024 45 DILIP MAHATO 58.70 0.00 0 0
2 ALIPURDUAR Falakata Alipurduar Division DHANIRAMPUR PIPED WATER SUPPLY SCHEME , SM/15208 New Supply of DIDF pipes and DI specials and CI Jeffy Coupling for Dhanirampur Water Supply Scheme (SM/15208) of Falakata Block under Alipurduar Division P.H.E. Dte. Alipurduar Sadar Sub Division Birpara Sub Division ORD/000519/2023-2024 838/ALD 14/03/2024 30 BARMAN ENTERPRISE 9.78 4.89 50 90
3 ALIPURDUAR Falakata Alipurduar Division DHANIRAMPUR PIPED WATER SUPPLY SCHEME , SM/15208 New Construction of tubewells (2 nos.) by Reverse rotary method of drilling at HW site and 2nd TW site , Soil investigation at OHR site, constructions of 250 Cum OHR at HW , construction of pump house and boundary wall at H/W and 2nd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for DHANIRAMPUR PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. Birpara A.E RWS Falakata Block ORD/000575/2022-2023 3636/ALD 31/03/2023 180 DILIP MAHATO 457.51 247.91 54.19 80
4 ALIPURDUAR Falakata Alipurduar Division DHANIRAMPUR PIPED WATER SUPPLY SCHEME , SM/15208 New Material Requisition To Resource Division RTOR000095/2023-2024 119/ALD 10/01/2024 Resource Division 9.56 0.00 0 0
5 ALIPURDUAR Falakata Northern Mechanical Division II DHANIRAMPUR PIPED WATER SUPPLY SCHEME , SM/15208 New NEW SERVICE CONNECTION CHARGES FOR DHANIRAMPURPH NO-I BILL/03014/2023-2024 BP-2023-24-691 14/03/2024 WBSEDCL 4.08 0.00 0 null
6 ALIPURDUAR Falakata Northern Mechanical Division II DHANIRAMPUR PIPED WATER SUPPLY SCHEME , SM/15208 New NEW SERVICE CONNECTION CHARGE DHANIRAMPUR PH NO-II BILL/03016/2023-2024 BP-2023-24-693 14/03/2024 WBSEDCL 5.85 0.00 0 null
7 ALIPURDUAR Falakata Northern Mechanical Division II DHANIRAMPUR PIPED WATER SUPPLY SCHEME , SM/15208 New Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Dhanirampur Water Supply Scheme TW No.-I and II under NMD-II,PHE.Dte,Apd. Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 1, Northern Mechanical Division-II,PHE ORD/000899/2023-2024 2473/NMD-II 11/08/2023 30 SARKAR ELECTRIC 21.08 0.00 0 0
Total 566.55 252.80 44.62