Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 286.53 90.18 31.47  
1 ALIPURDUAR Kalchini Alipurduar Division NIMTIJHORA TEA GARDEN PIPED WATER SUPPLY SCHEME , SM/14215 New Providing FHTC from existing distribution system as per specification for Nimtijhora TG PWSS under Alipurduar Division, PHE Dte. HQ-A.E RWS Kalchini Block ORD/000264/2023-2024 1882/ALD 07/09/2023 30 M/S A. B. ENTERPRISE 7.09 0.00 0 0
2 ALIPURDUAR Kalchini Alipurduar Division NIMTIJHORA TEA GARDEN PIPED WATER SUPPLY SCHEME , SM/14215 New Laying of CIDI pipes & HDPE (PN-10) pipeline and other allied works for Nimtijhora Tea Garden PWSS under Alipurduar Division, PHE Dte. HQ-A.E RWS Kalchini Block ORD/000396/2023-2024 207/ALD 16/01/2024 90 SAMIRON PODDER 44.44 1.61 3.62 7
3 ALIPURDUAR Kalchini Alipurduar Division NIMTIJHORA TEA GARDEN PIPED WATER SUPPLY SCHEME , SM/14215 New Tube well Boring by ODEX-165 Method of drilling at HW, FIRST TUBE WELL site including laying distribution system with new HDPE pipeline , Constructions of 100 Cum OHR as per Departmental Design & drawing , TWO nos. pump house & boundary wall, providing FHTC, Soil Investigation work and others allied works for NIMTIJHORA TEA GARDEN AREA PWSS Under Alipurduar Division PHE DTE HQ-A.E Alipurduar Sub Division ORD/000578/2022-2023 3639/ALD 31/03/2023 180 SAMIRON PODDER 207.36 88.57 42.71 90
4 ALIPURDUAR Kalchini Alipurduar Division NIMTIJHORA TEA GARDEN PIPED WATER SUPPLY SCHEME , SM/14215 New Material Requisition To Resource Division RTOR000071/2023-2024 2784/ALD 18/12/2023 Resource Division 6.17 0.00 0 0
5 ALIPURDUAR Kalchini Northern Mechanical Division II NIMTIJHORA TEA GARDEN PIPED WATER SUPPLY SCHEME , SM/14215 New New Service connection charge for Nimti Jhora tea garden PWSS P/H No-I. BILL/00561/2023-2024 BP-2023-24-190 22/06/2023 WBSEDCL 1.36 0.00 0 0
6 ALIPURDUAR Kalchini Northern Mechanical Division II NIMTIJHORA TEA GARDEN PIPED WATER SUPPLY SCHEME , SM/14215 New New Service connection charge for Nimti Jhora tea garden PWSS P/H No-II BILL/00562/2023-2024 BP-2023-24-189 22/06/2023 WBSEDCL 1.36 0.00 0 0
7 ALIPURDUAR Kalchini Northern Mechanical Division II NIMTIJHORA TEA GARDEN PIPED WATER SUPPLY SCHEME , SM/14215 New Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Nimtijhora TG water supply scheme, TW no I and II under Jal Jeevan Mission under NMD-II, PHE Dte.APD Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 1, Cooch-Behar Mechanical Sub-Division, ORD/000838/2023-2024 2413/NMD-II 10/08/2023 30 SUNLIT 18.75 0.00 0 90
Total 286.54 90.18 31.47