Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
10 | 338.88 | 63.09 | 18.62 | ||||||||||||||
1 | ALIPURDUAR | Kumargram | Alipurduar Division | CHUOTA DALDALI PIPED WATER SUPPLY SCHEME. , SM/13242 | New | Providing balance FHTC for Chhoto Daldali PWSS under Alipurduar Division, PHE Dte. | Alipurduar Sadar Sub Division | Alipurduar Sub Division | ORD/000208/2023-2024 | 1562/ALD | 23/08/2023 | 30 | DAS CONSTRUCTION | 3.35 | 0.00 | 0 | 0 |
2 | ALIPURDUAR | Kumargram | Alipurduar Division | CHUOTA DALDALI PIPED WATER SUPPLY SCHEME. , SM/13242 | New | Constructions of pump house & Tube well Boring by ODEX-165 Method of drilling at HW site & 2nd site , laying of distribution system with UPVC pipeline , Constructions of 200 Cum OHR as per Departmental Design & drawing , providing FHTC and others allied works for Chuota Daldali PWSS Under Alipurduar Division PHE DTE. | Alipurduar Sadar Sub Division | Alipurduar Sub Division | ORD/000508/2022-2023 | 3393/ALD | 16/03/2023 | 180 | DAS CONSTRUCTION | 278.20 | 63.09 | 22.68 | 30 |
3 | ALIPURDUAR | Kumargram | Alipurduar Division | CHUOTA DALDALI PIPED WATER SUPPLY SCHEME. , SM/13242 | New | Material Requisition To Resource Division | RTOR000017/2024-2025 | 3951/ALD | 26/11/2024 | Resource Division | 6.17 | 0.00 | 0 | 0 | |||
4 | ALIPURDUAR | Kumargram | Alipurduar Division | CHUOTA DALDALI PIPED WATER SUPPLY SCHEME. , SM/13242 | New | Material Requisition To Resource Division | RTOR000031/2023-2024 | 1276/ALD | 11/08/2023 | Resource Division | 11.58 | 0.00 | 0 | 0 | |||
5 | ALIPURDUAR | Kumargram | Alipurduar Division | CHUOTA DALDALI PIPED WATER SUPPLY SCHEME. , SM/13242 | New | Material Requisition To Resource Division | RTOR000101/2023-2024 | 125/ALD | 10/01/2024 | Resource Division | 6.17 | 0.00 | 0 | 0 | |||
6 | ALIPURDUAR | Kumargram | Northern Mechanical Division II | CHUOTA DALDALI PIPED WATER SUPPLY SCHEME. , SM/13242 | New | QUOTATION FOR NEW SERVICE CONNECTION AT CHOTO DALDALI PWSS PH NO-II | BILL/00043/2023-2024 | BP-2023-24-44 | 12/05/2023 | WBSEDCL | 1.21 | 0.00 | 0 | 0 | |||
7 | ALIPURDUAR | Kumargram | Northern Mechanical Division II | CHUOTA DALDALI PIPED WATER SUPPLY SCHEME. , SM/13242 | New | QUOTATION FOR NEW SERVICE CONNECTION AT CHOTO DALDALI PWSS PH NO-I | BILL/00044/2023-2024 | BP-2023-24-43 | 12/05/2023 | WBSEDCL | 1.21 | 0.00 | 0 | 0 | |||
8 | ALIPURDUAR | Kumargram | Northern Mechanical Division II | CHUOTA DALDALI PIPED WATER SUPPLY SCHEME. , SM/13242 | New | Additional Quotation for CHOTO DALDALI PH NO-2 | BILL/00865/2024-2025 | BP-266/24-25 | 09/08/2024 | WBSEDCL | 5.79 | 0.00 | 0 | null | |||
9 | ALIPURDUAR | Kumargram | Northern Mechanical Division II | CHUOTA DALDALI PIPED WATER SUPPLY SCHEME. , SM/13242 | New | Additional Quotation for CHOTO DALDALI PH NO-1 | BILL/00866/2024-2025 | BP-265/24-25 | 09/08/2024 | WBSEDCL | 3.48 | 0.00 | 0 | null | |||
10 | ALIPURDUAR | Kumargram | Northern Mechanical Division II | CHUOTA DALDALI PIPED WATER SUPPLY SCHEME. , SM/13242 | New | Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for CHOTO DALDALI water supply scheme, TW no I and II under Northern Mechanical Division-II, PHE Dte.Alipurduar. | Assistant Engineer,Alipurduar Mechanical Sub-Division,P | Junior Engineer 1, Cooch-Behar Mechanical Sub-Division, | ORD/000843/2023-2024 | 2424/NMD-II | 10/08/2023 | 30 | M/S SAJAHAN CHOWDHURY | 21.72 | 0.00 | 0 | 0 |
Total | 338.86 | 63.09 | 18.62 |