Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 310.15 203.69 65.67  
1 ALIPURDUAR Madarihat Alipurduar Division HOASINBAD TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/11696 New Construction of 200 cum OHR as per Departmental Design and drawing in headwork site, Tube well Boring by ODEX-165 method of drilling 2nos. respectively at Headwork site and 2nd Tubewell site, Rising Main and distribution line (Part-1) for HOASINBAD TG AREA PWSS under Birpara Sub-Division, Alipurduar Division, PHE Dte Birpara A.E Alipurduar Sub Division ORD/000281/2022-2023 1635/ALD 19/09/2022 180 SASANKA ROY 96.32 66.35 68.88 78
2 ALIPURDUAR Madarihat Alipurduar Division HOASINBAD TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/11696 New Construction of 2nos. Pump house, 2nos. Boundary wall at headwork site and 2nd Tubewell site including providing FHTC for HOASINBAD TG AREA PWSS under Birpara Sub-Division, Alipurduar Division, PHE Dte. Birpara A.E Alipurduar Sub Division ORD/000282/2022-2023 1636/ALD 19/09/2022 120 RATAN DUTTA 37.70 30.66 81.33 81
3 ALIPURDUAR Madarihat Alipurduar Division HOASINBAD TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/11696 New Laying of distribution system (Part-2) and providing FHTC for HOASINBAD TG AREA PWSS under Alipurduar Division, PHE Dte. Birpara A.E Alipurduar Sub Division ORD/000283/2022-2023 1637/ALD 19/09/2022 60 SASANKA ROY 81.64 75.12 92.01 92
4 ALIPURDUAR Madarihat Alipurduar Division HOASINBAD TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/11696 New Soil investigation works at head works site for HOASINBAD TG AREA PWSS under Birpara Sub-Division, Alipurduar Division, PHE Dte. Birpara A.E Alipurduar Sub Division ORD/000309/2022-2023 2133/ALD 10/11/2022 30 MOYTEC 0.70 0.64 91.43 0
5 ALIPURDUAR Madarihat Alipurduar Division HOASINBAD TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/11696 New Laying of DI and HDPE pipeline, trenchless pipe laying by HDD process, providing FHTC and others for Hossainabad PWSS under Alipurduar Division, PHE Dte. Birpara A.E Alipurduar Sub Division ORD/000472/2023-2024 690/ALD 07/03/2024 90 SASANKA ROY 62.82 17.12 27.25 80
6 ALIPURDUAR Madarihat Northern Mechanical Division II HOASINBAD TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/11696 New QUOTATION FOR NEW SERVICE CONNECTION AT HOASINABAD TG TW NO-II BILL/00062/2023-2024 BP-2023-24-57 13/05/2023 WBSEDCL 1.60 0.00 0 0
7 ALIPURDUAR Madarihat Northern Mechanical Division II HOASINBAD TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/11696 New QUOTATION FOR NEW SERVICE CONNECTION AT HOASINABAD TG TW NO-I BILL/00063/2023-2024 BP-2023-24-56 13/05/2023 WBSEDCL 1.60 0.00 0 0
8 ALIPURDUAR Madarihat Northern Mechanical Division II HOASINBAD TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/11696 New Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Hosainbad TG water supply scheme, TW no. I and II under Northern Mechanical Division-II, PHE Dte.APD Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 1, Cooch-Behar Mechanical Sub-Division, ORD/000826/2022-2023 485/NMD-II 02/03/2023 30 MITRA ENTERPRISE 27.77 13.80 49.69 99
Total 310.14 203.68 65.67