Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9 1,506.03 111.27 7.39  
1 ALIPURDUAR Madarihat Alipurduar Division JAYBIRPARA TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/10177 New Carrying of different dia AC pipes from Alipurduar Stackyard and withdrawing CI pipes at Alipurduar Sadar Sub-Division under Alipurduar Division, PHE Dte. HQ-A.E RWS Kalchini Block ORD/000094/2022-2023 458/ALD 13/05/2022 30 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 0.99 0.00 0 58.14
2 ALIPURDUAR Madarihat Alipurduar Division JAYBIRPARA TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/10177 New Laying of Distribution Line (HDPE and DI) for retrofitting of FHTC for BIRPARA WSS under Alipurduar Division, PHE Dte. Alipurduar RWS RWS Alipurduar - I Block ORD/000360/2020-2021 1754/ALD 19/02/2021 45 BILTU DAS 47.98 0.00 0 61
3 ALIPURDUAR Madarihat Alipurduar Division JAYBIRPARA TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/10177 New Construction of OHR 200cum for Jay Birpara TG Water Supply Scheme under Alipurduar Division, PHE Dte. Alipurduar RWS RWS Alipurduar - I Block ORD/000422/2021-2022 2601/ALD 17/02/2022 180 SUBHAS CHANDRA ROY 55.36 46.90 84.72 80
4 ALIPURDUAR Madarihat Alipurduar Division JAYBIRPARA TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/10177 New Construction of Pump House, Boundary Wall, Tube well Boring by ODEX-165 Method of drilling including providing FHTC and Rising main for JAY BIRPARA TG AREA PWSS under Alipurduar Division PHE DTE. Birpara A.E Alipurduar Sub Division ORD/000487/2021-2022 2911/ALD 08/03/2022 120 ALOK ENTERPRISE 156.25 64.37 41.2 50
5 ALIPURDUAR Madarihat Alipurduar Division JAYBIRPARA TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/10177 New Supply of different materials for Alipurduar Divisional Stack Yard under Alipurduar Division, PHE Dte. HQ-A.E RWS Kalchini Block ORD/000495/2021-2022 939/ALD 08/09/2021 30 EXECUTIVE ENGINEER, RESOURCE DIVISION 1,200.00 0.00 0 0
6 ALIPURDUAR Madarihat Alipurduar Division JAYBIRPARA TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/10177 New Material Requisition To Resource Division RTOR000028/2023-2024 1273/ALD 11/08/2023 Resource Division 20.82 0.00 0 0
7 ALIPURDUAR Madarihat Northern Mechanical Division II JAYBIRPARA TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/10177 New QUOTATION FOR NEW SERVICE CONNECTION AT JAYBIRPARA TG TW NO-II BILL/00070/2023-2024 BP-2023-24-65 13/05/2023 WBSEDCL 1.46 0.00 0 0
8 ALIPURDUAR Madarihat Northern Mechanical Division II JAYBIRPARA TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/10177 New QUOTATION FOR NEW SERVICE CONNECTION AT JAYBIRPARA TG TW NO-I BILL/00071/2023-2024 BP-2023-24-64 13/05/2023 WBSEDCL 1.46 0.00 0 0
9 ALIPURDUAR Madarihat Northern Mechanical Division II JAYBIRPARA TEA GARDEN AREA PIPED WATER SUPPLY SCHEME , SM/10177 New Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for JAY BIRPARA TG water supply scheme, TW no I and II under Northern Mechanical Division-II, PHE Dte.Alipurduar Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 1, Cooch-Behar Mechanical Sub-Division, ORD/000825/2023-2024 2398/NMD-II 09/08/2023 30 GEETA CONSTRUCTION 21.71 0.00 0 0
Total 1,506.04 111.26 7.39