Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
5 | 37.95 | 17.12 | 45.11 | ||||||||||||||
1 | ALIPURDUAR | Alipurduar Division | REJUVENATION OF MUNSHIPARA WATER SUPPLY SCHEME , SM/09894 | Augmentation | Construction of Pump House ,Boundary Wall , Tube well Boring ( Reverse Rotary Method) and Rising Main for Additional T/W of MUNSHIPARA Piped Water Supply Scheme Under Alipurduar Division PHE DTE | Alipurduar Sadar Sub Division | Birpara Sub Division | ORD/000326/2021-2022 | 2227/ALD | 14/01/2022 | 90 | TAPASH DAS | 21.92 | 8.93 | 40.74 | 25 | |
2 | ALIPURDUAR | Northern Mechanical Division II | REJUVENATION OF MUNSHIPARA WATER SUPPLY SCHEME , SM/09894 | Augmentation | ADDITIONAL QUOTATION CHARGES FOR MUNSHIPARA PWSS . | BILL/00209/2024-2025 | BP-42/24-25 | 29/04/2024 | WBSEDCL | 0.36 | 0.00 | 0 | null | ||||
3 | ALIPURDUAR | Northern Mechanical Division II | REJUVENATION OF MUNSHIPARA WATER SUPPLY SCHEME , SM/09894 | Augmentation | QUOTATION FOR NSC AT MUNSHIPARA PH NO-III | BILL/01750/2023-2024 | BP-2023-24-359 | 27/09/2023 | WBSEDCL | 1.00 | 0.00 | 0 | 0 | ||||
4 | ALIPURDUAR | Northern Mechanical Division II | REJUVENATION OF MUNSHIPARA WATER SUPPLY SCHEME , SM/09894 | Augmentation | Additional quotation for Munshipara p/h-III | BILL/02150/2023-2024 | BP-2023-24-479 | 12/12/2023 | WBSEDCL | 3.86 | 0.00 | 0 | 0 | ||||
5 | ALIPURDUAR | Northern Mechanical Division II | REJUVENATION OF MUNSHIPARA WATER SUPPLY SCHEME , SM/09894 | Augmentation | Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Rejuvenation of Munshipara water supply scheme, TW no III under Northern Mechanical Division-II, PHE Dte.Alipurduar | Assistant Engineer,Alipurduar Mechanical Sub-Division,P | Junior Engineer 2,Alipurduar Mechanical sub-division,PH | ORD/000687/2023-2024 | 2173/NMD-II | 27/07/2023 | 30 | M/S KUNDU CONSTRUCTION | 10.81 | 8.19 | 75.76 | 50 | |
Total | 37.95 | 17.12 | 45.1 |