Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
20 258.84 22.77 8.8  
1 ALIPURDUAR Alipurduar Division REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Extension of pipeline from Santali TG connection line to upper line of Madhu TG area (booster line) under Hasimara TG PWSS at Kalchini Block under Alipurduar Division, PHE Dte. HQ-A.E RWS Kalchini Block ORD/000024/2022-2023 19/ALD 01/04/2022 60 AASHIRBAD ENTERPRISE 12.61 0.00 0 49
2 ALIPURDUAR Alipurduar Division REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Extension of pipeline from Malangi TW to Bharnobari TG area (booster line) under Hasimara PWSS at Kalchini Block under Alipurduar Division, PHE Dte. HQ-A.E RWS Kalchini Block ORD/000025/2022-2023 20/ALD 01/04/2022 60 AASHIRBAD ENTERPRISE 14.64 0.00 0 49.5
3 ALIPURDUAR Alipurduar Division REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Construction of valve chamber, dismantling concrete road and other misc works at Malangi TG area within Hasimara W/S/S under Alipurduar Division, PHE Dte. HQ-A.E RWS Kalchini Block ORD/000077/2022-2023 442/ALD 13/05/2022 30 MADHAB SAHA 4.90 0.00 0 49
4 ALIPURDUAR Alipurduar Division REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Construction of HP Culvert for drainage purpose with 900 mm dia humepipe and construction of screening and inspection chamber at Hasimara PWSS HWS under Alipurduar Division PHE Dte.,Part-B Alipurduar Sadar Sub Division,HQ-A.E Birpara Sub Division ORD/000215/2022-2023 1105/ALD 29/07/2022 30 ALATYA CONSTRUCTION & CO. 3.60 0.00 0 0
5 ALIPURDUAR Alipurduar Division REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Construction of HP Culvert for drainage purpose with 900 mm dia humepipe and construction of screening and inspection chamber at Hasimara PWSS HWS under Alipurduar Division PHE Dte., Part-C Alipurduar Sadar Sub Division,HQ-A.E Birpara Sub Division ORD/000216/2022-2023 1106/ALD 29/07/2022 30 ALATYA CONSTRUCTION & CO. 4.08 0.00 0 0
6 ALIPURDUAR Alipurduar Division REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Laying of DI pipe and connection with Tubewell, Construction of Pathway, Fencing work and other works at Malangi TG Pump House under Alipurduar Division, PHE Dte. HQ-A.E ORD/000220/2022-2023 1110/ALD 29/07/2022 30 MAHENDRA CHHETRI 4.99 0.00 0 0
7 ALIPURDUAR Alipurduar Division REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Construction of Pump House ,Boundary Wall , Tube well Boring ( ODEX-165 Method of drilling) and Rising Main for Additional T/W of HASIMARA Piped Water Supply Scheme Under Alipurduar Division PHE DTE. HQ-A.E RWS Kalchini Block ORD/000294/2021-2022 1992/ALD 27/12/2021 90 MAHENDRA CHHETRI 42.03 0.00 0 49
8 ALIPURDUAR Alipurduar Division REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Laying of HDPE pipeline for Malangi Tea Garden Area within Hasimara Water Supply Scheme under Alipurduar Division, PHE Dte. HQ-A.E RWS Kalchini Block ORD/000375/2021-2022 2375/ALD 31/01/2022 60 MADHAB SAHA 74.82 0.00 0 94
9 ALIPURDUAR Alipurduar Division REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Material Requisition To Resource Division RTOR000012/2022-2023 717/ALD 13/06/2022 Resource Division 49.83 0.00 0 0
10 ALIPURDUAR Alipurduar Division REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Material Requisition To Resource Division RTOR000083/2023-2024 107/ALD 10/01/2024 Resource Division 12.32 0.00 0 0
11 ALIPURDUAR Northern Mechanical Division II REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Hasimara Water Supply Scheme TW No.-III under NMD-II,PHE Dte Alipurduar. Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 1, Cooch-Behar Mechanical Sub-Division, ORD/000006/2022-2023 534/NMD-II 20/04/2022 30 M/S RATAN KUMAR DASGUPTA & CO. 8.46 7.95 93.97 100
12 ALIPURDUAR Northern Mechanical Division II REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Hasimara Water Supply Scheme TW No.-IV under NMD-II PHE Dte Alipurduar. Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 1, Cooch-Behar Mechanical Sub-Division, ORD/000013/2022-2023 595/NMD-II 05/05/2022 30 M/S B ENTERPRISE 8.49 8.49 100 100
13 ALIPURDUAR Northern Mechanical Division II REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Supply, delivery & installation of Electro Mechanical Compopnents at HASIMARA W/S Scheme, P/H No. I(Handedover), under NMD-II, PHE, Dte. in the dist of Alipurduar. ORD/000360/2022-2023 243/AMSD 29/07/2022 15 S.K ELECTRICALS 1.06 0.00 0 0
14 ALIPURDUAR Northern Mechanical Division II REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation "Hiring of Motor Cab for site visit of the Assistant Engineer , Alipurduar Mechanical Sub- Division, P.H.E. Dte. under Northern Mechanical Division -II, P.H.E. Dte." ORD/000695/2023-2024 202/AMSD 28/07/2023 360 DILIP MAHATO 4.16 0.00 0 0
15 ALIPURDUAR Northern Mechanical Division II REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Supply, delivery & installation of 30 KVA, Servo Motor operated Copper wound line voltage stabilizer of HASIMARA Water Supply Scheme TW No.- IV under NMD-II, PHE. Dte. Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 2,Alipurduar Mechanical sub-division,PH ORD/000882/2021-2022 400/NMD-II 22/03/2022 30 M/S A.D. ENTERPRISE 3.17 3.17 100 0
16 ALIPURDUAR Northern Mechanical Division II REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Supply, delivery & installation of 30 KVA, Servo Motor operated Copper wound line voltage stabilizer of Hasimara Water Supply scheme T/W No.III NMD-II, PHE. Dte, Alipurduar. ORD/000917/2021-2022 408/NMD-II 22/03/2022 30 MAA TARA ENTERPRISE 3.16 3.16 100 0
17 ALIPURDUAR Northern Mechanical Division II REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Quotation for new service connection at Hasimara W/SS Tw No-IV Application No- 4002954692 VCH/000685/2022-2023 null 02/08/2022 WBSEDCL 1.63 0.00 0 0
18 ALIPURDUAR Northern Mechanical Division II REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Quotation for new service connection at Hasimara W/SS Tw No-III Application No- 4002954503 VCH/000686/2022-2023 null 02/08/2022 WBSEDCL 1.63 0.00 0 0
19 ALIPURDUAR Northern Mechanical Division II REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Quotation for new connection service connection at HASIMARA W/SS T/W no. IV ,Application no.4002954692 VCH/001278/2022-2023 BP-39/22-23 08/08/2022 WBSEDCL 1.63 0.00 0 0
20 ALIPURDUAR Northern Mechanical Division II REJUVENATION OF HASIMARA WATER SUPPLY SCHEME , SM/09887 Augmentation Quotation for new service connection for HASIMARA W/SS T/W no. III , Application no. 4002954503 VCH/001279/2022-2023 BP-40/22-23 08/08/2022 WBSEDCL 1.63 0.00 0 0
Total 258.85 22.77 8.8