Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
2 3.15 0 0  
1 ALIPURDUAR Alipurduar - II Northern Mechanical Division II Parokata water supply scheme , SM/01378 New Operation and Guarding of Pumping machinery at Pump House No. II , Under MADHYA PAROKATA W/S Scheme, in the dist. Of Alipurduar. ORD/000359/2021-2022 726/NMD-II 08/07/2021 365 M/S CHANDRANATH MUKHERJEE 2.97 0.00 0 0
2 ALIPURDUAR Alipurduar - II Northern Mechanical Division II Parokata water supply scheme , SM/01378 New Internal wiring & Earthing arrangement & allied works at P/H No.I of Madhya Parokata W/S Scheme at under AMSD , PHE Dte. In the dist. of Alipurduar ORD/000806/2020-2021 400/AMSD 07/08/2020 10 TALUKDAR ENTERPRISE 0.18 0.00 0 0
Total 3.15 0.00 0