Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
3 931.85 0 0  
1 PURBA MEDINIPUR Potashpur - I Tamluk Division TALCHITKINI AND IT'S ADJOINING MOUJAS PWSS , SM/12433 New Sinking of Tube well,Pump House ,Construction of 200 cum & 250 Cum OHR (Intze type with pile foundation), Rising main, Head work site, Laying distribution pipe line, Boundary Wall, Soil investigation & Accommodate FHTC (3146 nos) under JJM with allied work including 02(Two) Years Operation & Maintenance for Dhankar & Talchitkini its adjoining moujas PWSS in Patashpur-I Block within Contai Sub-Division under Tamluk Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000495/2023-2024 1671/TD 25/07/2023 180 HALDIA DEVELOPMENT CONSTRUCTION 895.07 0.00 0 20
2 PURBA MEDINIPUR Potashpur - I Tamluk Division TALCHITKINI AND IT'S ADJOINING MOUJAS PWSS , SM/12433 New Material Requisition To Resource Division RTOR000325/2022-2023 2991/TD 27/02/2023 Resource Division 14.06 0.00 0 0
3 PURBA MEDINIPUR Potashpur - I Midnapore Mechanical TALCHITKINI AND IT'S ADJOINING MOUJAS PWSS , SM/12433 New Providing and Installation of Submersible pumping machineries and other electromechanical equipments for Ground Water Based Piped Water Supply Scheme for TALCHITKINI and ADJOINING MOUJAS, Block - Potashpur I, District - Purba Medinipur under JJM Program under MMD PHE Dte. Sri Srinath Ranjan Ghosh, AE/Haldia Electrical Sub-Divi Sri Sukanta Mondal, JE/Haldia Electrical Sub-Division. ORD/001643/2022-2023 520/W/MMD 20/03/2023 180 BIJAN ENTERPRISE 22.72 0.00 0 0
Total 931.86 0.00 0