Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
2 58.07 43.73 75.31  
1 PASCHIM MEDINIPUR Midnapore Division Retrofitting to accommodate FHTC under JJM in Sabang PWSS, Block - Sabang, District - Paschim Medinipur. , SM/09087 Retrofitting Extension of Pipeline at Mouza Gourbar Muslim Para within Sabang Augmentation Water Supply Scheme (Zone-I) at Sabang Block for FHTC Work under Kharagpur Sub-Division within Midnapore Division, P.H.E. Dte. AE Kharagpur Sub-division ORD/000063/2022-2023 490/AE/KSD 01/08/2022 30 PALASH KUMAR DAS 4.70 4.28 91.06 0
2 PASCHIM MEDINIPUR Midnapore Division Retrofitting to accommodate FHTC under JJM in Sabang PWSS, Block - Sabang, District - Paschim Medinipur. , SM/09087 Retrofitting Retrofitting to accommodate FHTC under JJM in Sabang (Zone-I) PWSS under Sabang Block in Paschim Medinipur District. AE Kharagpur Sub-division,Assistant Engineer (HQ) JE RWS Kharagpur Sub-Division( Sabang),JE3 Kharagpur Sub-division ORD/000493/2021-2022 2186/MD 17/12/2021 45 MASUM ALI KHAN 53.37 39.45 73.92 0
Total 58.07 43.73 75.31