Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 778.34 221.32 28.43  
1 SOUTH 24 PARAGANAS Jaynagar - I S24 Pgns Mechanical Ground water based piped water supply scheme for Purba Gabberia (Zone-I) PWSS, Under South 24-Pgns W/S Division-I, Block: Jaynagar-I District South 24-Pgns. , SM/11277 New Payment of electricity bill for new service connection under SMD, PHE Dte. BILL/05023/2023-2024 BP-2023-24-570 12/03/2024 WBSEDCL 8.55 0.00 0 0
2 SOUTH 24 PARAGANAS Jaynagar - I S24 Pgns Mechanical Ground water based piped water supply scheme for Purba Gabberia (Zone-I) PWSS, Under South 24-Pgns W/S Division-I, Block: Jaynagar-I District South 24-Pgns. , SM/11277 New Supply, installation and commissioning of submersible pumping machinery along with allied accessories at P.H. 1&2, Zone-I of Purba Gabberia water supply scheme under South 24 Pgs. Mechanical Division, PHE Dte. [Block: Jaynagar-I] Assistant Engineer Junior Engineer ORD/000557/2022-2023 546/SMD 21/02/2023 90 DEBJYOTI BASU 19.37 0.00 0 0
3 SOUTH 24 PARAGANAS Jaynagar - I South 24 Pgs W/S Division I Ground water based piped water supply scheme for Purba Gabberia (Zone-I) PWSS, Under South 24-Pgns W/S Division-I, Block: Jaynagar-I District South 24-Pgns. , SM/11277 New Additional work for sinking of 02 (two) nos. Rig bored 300 mm x 200 mm dia. & 300 mtr. deep Tube well to achieve 66 mtr. housing pipe by Rotary Method for Purba Gabberia Zone-I PWSS of Joynagar-I Block for Augmentation of Surface Water Based W/S Scheme in the Arsenic Affected Areas of South 24 Pgs district under South 24-Parganas W/S Division- I, P.H.E. Dte. [TSM/010747] AE BSD ORD/000018/2023-2024 41/SWD-I 06/04/2023 15 K P CONSTRUCTION 4.41 4.23 95.92 100
4 SOUTH 24 PARAGANAS Jaynagar - I South 24 Pgs W/S Division I Ground water based piped water supply scheme for Purba Gabberia (Zone-I) PWSS, Under South 24-Pgns W/S Division-I, Block: Jaynagar-I District South 24-Pgns. , SM/11277 New Construction of 02 (Two) nos. chlorination room at PURBA GABBERIA (Zone-I) of Joynagar-I Block for disinfection of ground water from big dia tube well due to improvement of water supply in the water Scarcity area/non command area under Surface Water Based Water Supply Scheme in the Arsenic affected areas of South 24-Pgns district. [TSM/010754] AE BSD ORD/000156/2022-2023 1409/SWD-I 22/09/2022 60 NIRMAN 11.01 0.00 0 100
5 SOUTH 24 PARAGANAS Jaynagar - I South 24 Pgs W/S Division I Ground water based piped water supply scheme for Purba Gabberia (Zone-I) PWSS, Under South 24-Pgns W/S Division-I, Block: Jaynagar-I District South 24-Pgns. , SM/11277 New Sinking of 02 (two) nos. Rig bored 300mm x 200mm dia. & 300 mtr. deep Tubewell by Rotary method for PURBA GABBERIA (Zone-I) PWSS of Joynagar-I Block under South-24 Pns W/S- Divn-I, PHE Dte., within South 24 Parganas District. [TSM/010747] AE BSD ORD/000243/2022-2023 1686/SWD-I 01/11/2022 30 K P CONSTRUCTION 42.29 35.45 83.83 90
6 SOUTH 24 PARAGANAS Jaynagar - I South 24 Pgs W/S Division I Ground water based piped water supply scheme for Purba Gabberia (Zone-I) PWSS, Under South 24-Pgns W/S Division-I, Block: Jaynagar-I District South 24-Pgns. , SM/11277 New Construction of 300 m3 capacity 20 M. staging height R.C.C. Over Head Water Reservoir as per departmental design, drawing & specification including R.C.C. Bored Pile & Pile Cap after soil investigation alongwith Providing 100% FHTC & Laying distribution system from Big dia deep Tube Well at PURBO GABBERIA (Zone-I) Mouza of JOYNAGAR-I Block due to improvement of water supply in the water Scarcity area/non command area under Surface Water Based Water Supply Scheme in the Arsenic affected areas of South 24-Pgns district. (No. of FHTC = 1909) AE BSD JE RWS,JE-2 ORD/000274/2022-2023 1808/SWD-I 09/11/2022 300 PASCON 449.74 178.92 39.78 65
7 SOUTH 24 PARAGANAS Jaynagar - I South 24 Pgs W/S Division I Ground water based piped water supply scheme for Purba Gabberia (Zone-I) PWSS, Under South 24-Pgns W/S Division-I, Block: Jaynagar-I District South 24-Pgns. , SM/11277 New Preparation and submission of Detailed Project Report of PURBA GABBERIA(I) Ground Water Based Piped Water Supply Scheme in JOYNAGAR-I Block under Surface Water Based Water Supply Scheme in the Arsenic affected areas of South 24-Pgns. district. AE BSD ORD/000364/2021-2022 1929/SWD-I 27/01/2022 30 MS R. DUTTA AND CO 2.76 2.72 98.55 100
8 SOUTH 24 PARAGANAS Jaynagar - I South 24 Pgs W/S Division I Ground water based piped water supply scheme for Purba Gabberia (Zone-I) PWSS, Under South 24-Pgns W/S Division-I, Block: Jaynagar-I District South 24-Pgns. , SM/11277 New Material Requisition To Resource Division RTOR000069/2023-2024 291/SWD-I 24/04/2023 Resource Division 240.21 0.00 0 0
Total 778.33 221.31 28.43