Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
13 525.37 136.69 26.02  
1 SOUTH 24 PARAGANAS Alipore Division AUGMENTATION FOR GROUND WATER BASED KHAS RAMKARCHAR, PIPED WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , SM/18871 Augmentation Construction, Placing and fixing of FHTC Platform at every individual beneficiary, pump connection etc. at Khas Ramkarchar W/S Scheme, Block - Sagar for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (SM/18871) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_4, Kakdwip Sub Division ORD/000181/2024-2025 2540/AD 18/06/2024 60 DEBARATI ENTERPRISE 48.53 0.00 0 0
2 SOUTH 24 PARAGANAS Alipore Division AUGMENTATION FOR GROUND WATER BASED KHAS RAMKARCHAR, PIPED WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , SM/18871 Augmentation Continuation order for the work of Laying distribution system, Rising Main, Functional Household Tap Connection (FHTC) to all households along with construction of 01 no. Pump House including O & M of distribution system, rising main, FHTC for 1 year after completion of FHTC works for Khas Ramkarchar Water Supply Scheme, Block - Sagar for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. [No. of FHTC = 100] Assistant Engineer, Kakdwip Sub Division Juniour Engineer_4, Kakdwip Sub Division ORD/000410/2024-2025 3205/AD 01/08/2024 45 DEBARATI ENTERPRISE 47.65 0.00 0 0
3 SOUTH 24 PARAGANAS Alipore Division AUGMENTATION FOR GROUND WATER BASED KHAS RAMKARCHAR, PIPED WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , SM/18871 Augmentation Laying distribution system, Rising Main, Functional Household Tap Connection (FHTC) to all households along with construction of 01 no. Pump House including O & M of distribution system, rising main, FHTC for 1 year after completion of FHTC works for Khas Ramkarchar Water Supply Scheme, Block - Sagar for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. [No. of FHTC = 100] Assistant Engineer, Kakdwip Sub Division Juniour Engineer_4, Kakdwip Sub Division ORD/001165/2023-2024 3744/AD 03/11/2023 90 DEBARATI ENTERPRISE 213.65 86.60 40.53 90
4 SOUTH 24 PARAGANAS Alipore Division AUGMENTATION FOR GROUND WATER BASED KHAS RAMKARCHAR, PIPED WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , SM/18871 Augmentation Conducting route survey, design distribution network and preparation & submission of DPR for each of different new water supply scheme / each Augmentation (KHAS RAMKARCHAR (Phase - B)) water supply scheme including Functional Household Tap Connection (FHTC) for implementation of JJM at Sagar Block under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/001360/2023-2024 3257/AD 05/10/2023 45 VOYAGER 5.58 3.57 63.98 100
5 SOUTH 24 PARAGANAS Alipore Division AUGMENTATION FOR GROUND WATER BASED KHAS RAMKARCHAR, PIPED WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , SM/18871 Augmentation Laying distribution system for providing FHTC to all households for Augmentation of Khas Ramkarchar (Zone- I & II) Water Supply Scheme, Block - Sagar for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E.D. (Zone-I) (Part-A) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_4, Kakdwip Sub Division ORD/001838/2023-2024 126/AD 05/01/2024 45 M/S. GIRI ENTERPRISE 23.17 11.55 49.85 60
6 SOUTH 24 PARAGANAS Alipore Division AUGMENTATION FOR GROUND WATER BASED KHAS RAMKARCHAR, PIPED WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , SM/18871 Augmentation Laying distribution system for providing FHTC to all households for Augmentation of Khas Ramkarchar (Zone- I & II) Water Supply Scheme, Block - Sagar for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E.D. (Zone-I) (Part-B) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_4, Kakdwip Sub Division ORD/001839/2023-2024 127/AD 05/01/2024 45 M/S. TRIPATHI & CO. 21.40 10.57 49.39 60
7 SOUTH 24 PARAGANAS Alipore Division AUGMENTATION FOR GROUND WATER BASED KHAS RAMKARCHAR, PIPED WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , SM/18871 Augmentation Construction of 300 cum. Capacity 20mtr. staging height RCC Over Head Reservoir at as per departmental design, drawing & specification etc.at Khas Ramkarer char W/s Scheme in 24 pgs (south) under Kakdwip Sub Division of Alipore Division PHE Dte. Assistant Engineer, Kakdwip Sub Division ORD/001896/2018-2019 4984/AD 04/03/2019 2190 M/S. S.S. ENTERPRISE 96.99 24.30 25.05 80
8 SOUTH 24 PARAGANAS Alipore Division AUGMENTATION FOR GROUND WATER BASED KHAS RAMKARCHAR, PIPED WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , SM/18871 Augmentation Making and fixing of permanent display board at headwork site of Krishnanagar, Khansaheber Abad, Naraharipur, Khas Ramkarchar PWSS under JJM at Sagar Block under Kakdwip Sub-Division of Alipore Division P.H.E.D. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_5, Kakdwip Sub Division ORD/002171/2023-2024 953/KSD 19/12/2023 5 ANANTA KUMAR GIRI 0.81 0.10 12.35 100
9 SOUTH 24 PARAGANAS Alipore Division AUGMENTATION FOR GROUND WATER BASED KHAS RAMKARCHAR, PIPED WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , SM/18871 Augmentation Material Requisition To Resource Division RTOR000516/2023-2024 4834/AD 20/12/2023 Resource Division 41.76 0.00 0 0
10 SOUTH 24 PARAGANAS Alipore Division AUGMENTATION FOR GROUND WATER BASED KHAS RAMKARCHAR, PIPED WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , SM/18871 Augmentation Material Requisition To Resource Division RTOR000528/2023-2024 15/AD 02/01/2024 Resource Division 0.59 0.00 0 0
11 SOUTH 24 PARAGANAS Alipore Division AUGMENTATION FOR GROUND WATER BASED KHAS RAMKARCHAR, PIPED WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , SM/18871 Augmentation Material Requisition To Resource Division RTOR000692/2023-2024 462/AD 24/01/2024 Resource Division 9.25 0.00 0 0
12 SOUTH 24 PARAGANAS S24 Pgns Mechanical AUGMENTATION FOR GROUND WATER BASED KHAS RAMKARCHAR, PIPED WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , SM/18871 Augmentation Payment for New Service connection Khas Ramkarchar PH-3 W/ S Scheme Application No:- 1008023779 Reference ID: 106715294 BILL/01515/2024-2025 null 02/09/2024 WBSEDCL 4.26 0.00 0 null
13 SOUTH 24 PARAGANAS S24 Pgns Mechanical AUGMENTATION FOR GROUND WATER BASED KHAS RAMKARCHAR, PIPED WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , SM/18871 Augmentation Supply, installation and commissioning of submersible pumping machinery along with allied accessories at P.H. 1 of Augmentation of Khasramkarchar ( Phase-B) water supply scheme under South 24 Pgs. Mechanical Division, PHE Dte. [Block: Sagar] Assistant Engineer -I Junior Engineer ORD/000164/2024-2025 2335/SMD 24/07/2024 90 PS & ASSOCIATES 11.73 0.00 0 0
Total 525.39 136.68 26.02