Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
10 1,379.33 182.83 13.25  
1 SOUTH 24 PARAGANAS Patharpratima Alipore Division Dakshin Durgapur Piped Water Supply Scheme. , SM/16758 New Sinking of 02 Nos. 250mm x 150mm dia. 360 mtr. deep Tubewell by D.R. Rig method using UPVC Pipe & Pre-packed Resin Bonded Gravel Filter at 1st and 2nd Tubewell Site of Dakshin Durgapur Water Supply Scheme, Block - Pathar Pratima under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/000024/2022-2023 13065/AD 24/03/2023 60 AQUATECH ENGINEERS 36.60 0.00 0 0
2 SOUTH 24 PARAGANAS Patharpratima Alipore Division Dakshin Durgapur Piped Water Supply Scheme. , SM/16758 New Construction, placing and fixing of FHTC platform at every individual beneficiary, pump connections, pile & pile cap for OHR etc at Ramnagarabad and Dakshin Durgapur PWSS, Block - Patharpratima for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E.D. (SM/16759 and 16758) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/000329/2024-2025 2732/AD 25/06/2024 90 M/S B. ENTERPRISE 318.12 0.00 0 0
3 SOUTH 24 PARAGANAS Patharpratima Alipore Division Dakshin Durgapur Piped Water Supply Scheme. , SM/16758 New Construction of 200 cum. (1 no.) and 300 cum. (1 no.) Over Head Reservoir (OHR), (20 mtr. Staging Height) along with Laying distribution system, Rising Main, Functional Household Tap Connection (FHTC) to all households including design & drawing of pile foundation & pile cap after soil investigation including O & M of distribution system, rising main, FHTC for 1 year after completion of FHTC works for Dakshin Durgapur and Ramnagar Abad Water Supply Scheme, Block - Pathar Pratima for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. [No. of FHTC = 450] Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/000765/2023-2024 2911/AD 20/09/2023 300 M/S B. ENTERPRISE 547.29 35.40 6.47 25
4 SOUTH 24 PARAGANAS Patharpratima Alipore Division Dakshin Durgapur Piped Water Supply Scheme. , SM/16758 New Laying distribution system, Rising Main, Functional Household Tap Connection (FHTC) to all households including design & drawing of pile foundation & pile cap after soil investigation including O & M of distribution system, rising main, FHTC for 1 year after completion of FHTC works for Dakshin Durgapur and Ramnagar Abad Water Supply Scheme, Block - Pathar Pratima for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (Part-B) [No. of FHTC = 1192] Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/001214/2023-2024 3818/AD 07/11/2023 90 M/S B. ENTERPRISE 377.97 147.43 39.01 30
5 SOUTH 24 PARAGANAS Patharpratima Alipore Division Dakshin Durgapur Piped Water Supply Scheme. , SM/16758 New Making and fixing of permanent display board at headwork site of Digambarpur, Indranarayanpur, Dakshin Durgapur, Ramnagar Abad, Gurudaspur PWSS under JJM at Pathar Pratima Block under Kakdwip Sub-Division of Alipore Division P.H.E.D. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/002102/2023-2024 926/KSD 19/12/2023 5 BIMALENDU GIRI 0.79 0.00 0 100
6 SOUTH 24 PARAGANAS Patharpratima Alipore Division Dakshin Durgapur Piped Water Supply Scheme. , SM/16758 New Construction of boundary wall along with Land Development and Plinth Protection and Approach Road for Pump House at Head Work Site of Dakshin Durgapur W/S scheme, Block : Pathar Pratima under JJM of Kakdwip Sub-Division under Alipore Division, P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/002159/2023-2024 804/AD 05/02/2024 60 M/S. SIKHA ENTERPRISE 27.47 0.00 0 0
7 SOUTH 24 PARAGANAS Patharpratima Alipore Division Dakshin Durgapur Piped Water Supply Scheme. , SM/16758 New Construction of boundary wall along with Land Development, Plinth Protection and Approach Road for Pump House at 2nd Tubewell Site of Dakshin Durgapur W/S scheme, Block : Pathar Pratima under JJM of Kakdwip Sub-Division under Alipore Division, P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/002160/2023-2024 805/AD 05/02/2024 30 SANKAR HALDER 9.55 0.00 0 0
8 SOUTH 24 PARAGANAS Patharpratima Alipore Division Dakshin Durgapur Piped Water Supply Scheme. , SM/16758 New Preparation of design (Pile and Pile Cap) drawing for foundation of different capacity OHR of Dakshin Durgapur PWSS under JJM at Pathar Pratima Block under Kakdwip Sub-Division of Alipore Division P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/002623/2023-2024 880/KSD 15/12/2023 10 CONSTEEL CONSULTANCY & SERVICES 0.48 0.00 0 100
9 SOUTH 24 PARAGANAS Patharpratima Alipore Division Dakshin Durgapur Piped Water Supply Scheme. , SM/16758 New Material Requisition To Resource Division RTOR000481/2023-2024 4756/AD 19/12/2023 Resource Division 46.54 0.00 0 0
10 SOUTH 24 PARAGANAS Patharpratima Alipore Division Dakshin Durgapur Piped Water Supply Scheme. , SM/16758 New Material Requisition To Resource Division RTOR000560/2023-2024 48/AD 03/01/2024 Resource Division 14.52 0.00 0 0
Total 1,379.31 182.83 13.26