Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
3 58.17 0 0  
1 SOUTH 24 PARAGANAS Alipore Division AUGMENTATION OF PHULMALANCHA PIPED WATER SUPPLY SCHEME BLOCK BASANTI UNDER CANNING SUB DIVISION OF ALIPORE DIVISION PHE DTE. , SM/15225 Augmentation Material Requisition To Resource Division RTOR000030/2023-2024 378/AD 02/05/2023 Resource Division 35.29 0.00 0 0
2 SOUTH 24 PARAGANAS S24 Pgns Mechanical AUGMENTATION OF PHULMALANCHA PIPED WATER SUPPLY SCHEME BLOCK BASANTI UNDER CANNING SUB DIVISION OF ALIPORE DIVISION PHE DTE. , SM/15225 Augmentation Supply, installation and commissioning of submersible pumping machinery along with allied accessories at P.H. 1 for Augmentation of Phulmalancha water supply scheme under South 24 Pgs. Mechanical Division, PHE Dte. [Block: Basanti] Assistant Engineer Junior Engineer ORD/000013/2023-2024 948/SMD 04/04/2023 90 B. P. CONSTRUCTION 11.70 0.00 0 0
3 SOUTH 24 PARAGANAS S24 Pgns Mechanical AUGMENTATION OF PHULMALANCHA PIPED WATER SUPPLY SCHEME BLOCK BASANTI UNDER CANNING SUB DIVISION OF ALIPORE DIVISION PHE DTE. , SM/15225 Augmentation Supply, installation and commissioning of submersible pumping machinery along with allied accessories at P.H. 1, for Augmentation of Phulmalancha water supply scheme under South 24 Pgs. Mechanical Division, PHE Dte. [Block: Basanti] Assistant Engineer Junior Engineer ORD/000494/2022-2023 296/SMD 03/02/2023 90 SRI KRISHNA NIRMAN 11.18 0.00 0 0
Total 58.18 0.00 0