Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
14 776.65 321.34 41.38  
1 SOUTH 24 PARAGANAS Namkhana Alipore Division GROUND WATER BASED AMRABATI PIPE WATER SUPPLY SCHEME UNDER ALIPORE DIVISION, BLOCK-NAMKHANA,DISTRICT - SOUTH 24 PARGANAS , SM/14156 New Construction of boundary wall along with Land Development and Plinth Protection and Approach Road for Pump House at Head Work Site of Amarabati W/S scheme, Block : Namkhana under JJM of Kakdwip Sub-Division under Alipore Division, P.H.E. Dte. (SM/14156) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_1, Kakdwip Sub Division ORD/000411/2024-2025 3061/AD 25/07/2024 45 SARADA CONSTRUCTION 30.44 0.00 0 0
2 SOUTH 24 PARAGANAS Namkhana Alipore Division GROUND WATER BASED AMRABATI PIPE WATER SUPPLY SCHEME UNDER ALIPORE DIVISION, BLOCK-NAMKHANA,DISTRICT - SOUTH 24 PARGANAS , SM/14156 New Construction, placing and fixing of FHTC platform at every individual beneficiary, pump connection etc. for Amarabati W/S Scheme, Block - Namkhana for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (SM/14156) (2nd Call) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_1, Kakdwip Sub Division ORD/000501/2024-2025 3604/AD 06/09/2024 75 SARADA CONSTRUCTION 80.76 0.00 0 0
3 SOUTH 24 PARAGANAS Namkhana Alipore Division GROUND WATER BASED AMRABATI PIPE WATER SUPPLY SCHEME UNDER ALIPORE DIVISION, BLOCK-NAMKHANA,DISTRICT - SOUTH 24 PARGANAS , SM/14156 New Allied works for pile and pile cap portion regarding the construction of 300 cum. capacity 20 mtr. staging height R.C.C. Over Head Reservoir as per departmental design, drawing & specification including R.C.C. Bored pile & pile cap upto pedestal at Amarabati W/S Scheme, Namkhana Block, Dist. - South 24 Parganas, under Kakdwip Sub-Division of Alipore Division P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_1, Kakdwip Sub Division ORD/000588/2023-2024 2345/AD 18/08/2023 45 SARADA CONSTRUCTION 42.65 19.57 45.89 98
4 SOUTH 24 PARAGANAS Namkhana Alipore Division GROUND WATER BASED AMRABATI PIPE WATER SUPPLY SCHEME UNDER ALIPORE DIVISION, BLOCK-NAMKHANA,DISTRICT - SOUTH 24 PARGANAS , SM/14156 New Preparation of design (Pile and Pile Cap) drawing for foundation of different capacity OHR of Amarabati PWSS under JJM at Namkhana Block under Kakdwip Sub-Division of Alipore Division P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/000938/2023-2024 278(I)/KSD 13/07/2023 4 GEOTECHNICAL ENGINEERS CONSORTIUM 0.49 0.24 48.98 100
5 SOUTH 24 PARAGANAS Namkhana Alipore Division GROUND WATER BASED AMRABATI PIPE WATER SUPPLY SCHEME UNDER ALIPORE DIVISION, BLOCK-NAMKHANA,DISTRICT - SOUTH 24 PARGANAS , SM/14156 New Conducting route survey, design distribution network and preparation & submission of DPR for each of different new water supply scheme / each Augmentation water supply scheme (Amrabati PWSS) including Functional Household Tap Connection (FHTC) for implementation of JJM at Namkhana Block under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/001784/2022-2023 3693/AD 02/08/2022 45 M/S R.DUTTA & CO. 9.01 9.01 100 95
6 SOUTH 24 PARAGANAS Namkhana Alipore Division GROUND WATER BASED AMRABATI PIPE WATER SUPPLY SCHEME UNDER ALIPORE DIVISION, BLOCK-NAMKHANA,DISTRICT - SOUTH 24 PARGANAS , SM/14156 New Construction of 300 cum. Over Head Reservoir (OHR), (20 mtr. Staging Height) along Laying distribution system, Rising Main, Functional Household Tap Connection (FHTC) to all households including design & drawing of foundation after soil investagation including O & M of Laying distribution, Rising Main & FHTC for 1 year after completion of FHTC works for Amarabati Water Supply Scheme, Block - Namkhana for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (Part-A). [No. of FHTC = 100] Assistant Engineer, Kakdwip Sub Division Juniour Engineer_1, Kakdwip Sub Division ORD/002075/2022-2023 12945/AD 21/03/2023 300 SARADA CONSTRUCTION 169.37 40.27 23.78 28
7 SOUTH 24 PARAGANAS Namkhana Alipore Division GROUND WATER BASED AMRABATI PIPE WATER SUPPLY SCHEME UNDER ALIPORE DIVISION, BLOCK-NAMKHANA,DISTRICT - SOUTH 24 PARGANAS , SM/14156 New Laying distribution system, Functional Household Tap Connection (FHTC) to all households for Amarabati Water Supply Scheme, Block - Namkhana for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (Part-B) [No. of FHTC = 1200] Assistant Engineer, Kakdwip Sub Division Juniour Engineer_1, Kakdwip Sub Division ORD/002076/2022-2023 12946/AD 21/03/2023 90 SARADA CONSTRUCTION 151.76 145.68 95.99 77
8 SOUTH 24 PARAGANAS Namkhana Alipore Division GROUND WATER BASED AMRABATI PIPE WATER SUPPLY SCHEME UNDER ALIPORE DIVISION, BLOCK-NAMKHANA,DISTRICT - SOUTH 24 PARGANAS , SM/14156 New Laying distribution system, Functional Household Tap Connection (FHTC) to all households for Amarabati Water Supply Scheme, Block - Namkhana for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (Part-C) [No. of FHTC = 1200] Assistant Engineer, Kakdwip Sub Division Juniour Engineer_1, Kakdwip Sub Division ORD/002077/2022-2023 12947/AD 21/03/2023 90 SARADA CONSTRUCTION 169.36 106.47 62.87 24
9 SOUTH 24 PARAGANAS Namkhana Alipore Division GROUND WATER BASED AMRABATI PIPE WATER SUPPLY SCHEME UNDER ALIPORE DIVISION, BLOCK-NAMKHANA,DISTRICT - SOUTH 24 PARGANAS , SM/14156 New Making and fixing of permanent display board at headwork site of Dakshin Chandranagar, Haripur Zone - I & II, Amarabati PWSS under JJM at Namkhana Block under Kakdwip Sub-Division of Alipore Division P.H.E.D. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_1, Kakdwip Sub Division ORD/002131/2023-2024 937/KSD 19/12/2023 5 M/S B. ENTERPRISE 0.63 0.10 15.87 100
10 SOUTH 24 PARAGANAS Namkhana Alipore Division GROUND WATER BASED AMRABATI PIPE WATER SUPPLY SCHEME UNDER ALIPORE DIVISION, BLOCK-NAMKHANA,DISTRICT - SOUTH 24 PARGANAS , SM/14156 New Road restoration and other allied works for laying pipe line to providing Functional Household Tap Connection (FHTC) to all households for Aamarabati Water Supply Scheme, Block - Namkhana for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E.D. (Part-A) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_1, Kakdwip Sub Division ORD/002565/2023-2024 510/KSD 15/03/2024 5 SARADA CONSTRUCTION 3.63 0.00 0 90
11 SOUTH 24 PARAGANAS Namkhana Alipore Division GROUND WATER BASED AMRABATI PIPE WATER SUPPLY SCHEME UNDER ALIPORE DIVISION, BLOCK-NAMKHANA,DISTRICT - SOUTH 24 PARGANAS , SM/14156 New Material Requisition To Resource Division RTOR000484/2023-2024 4786/AD 19/12/2023 Resource Division 64.94 0.00 0 0
12 SOUTH 24 PARAGANAS Namkhana Alipore Division GROUND WATER BASED AMRABATI PIPE WATER SUPPLY SCHEME UNDER ALIPORE DIVISION, BLOCK-NAMKHANA,DISTRICT - SOUTH 24 PARGANAS , SM/14156 New Material Requisition To Resource Division RTOR000554/2023-2024 42/AD 03/01/2024 Resource Division 16.45 0.00 0 0
13 SOUTH 24 PARAGANAS Namkhana Alipore Division GROUND WATER BASED AMRABATI PIPE WATER SUPPLY SCHEME UNDER ALIPORE DIVISION, BLOCK-NAMKHANA,DISTRICT - SOUTH 24 PARGANAS , SM/14156 New Material Requisition To Resource Division RTOR000983/2023-2024 1776/AD 27/03/2024 Resource Division 4.90 0.00 0 0
14 SOUTH 24 PARAGANAS Namkhana S24 Pgns Mechanical GROUND WATER BASED AMRABATI PIPE WATER SUPPLY SCHEME UNDER ALIPORE DIVISION, BLOCK-NAMKHANA,DISTRICT - SOUTH 24 PARGANAS , SM/14156 New Supply, installation and commissioning of submersible pumping machinery along with allied accessories at P.H. 1,2&3, of Amrabati water supply scheme under South 24 Pgs. Mechanical Division, PHE Dte. [Block: Namkhana] Assistant Engineer -I Junior Engineer ORD/000805/2022-2023 268/SMD 31/01/2023 90 CINZANO 32.26 0.00 0 0
Total 776.64 321.35 41.38