Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Showing 1 to 13 of 13 entries
Sl No.District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrustedName of JE entrustedSystem Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
13 561.9131.4223.39 
Sl No.
District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted
Name of JE entrusted
System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
13
561.9
131.42
23.39
 
Total
561.90
131.42
23.39
 
1 SOUTH 24 PARGANAS Gosaba Alipore Division GROUND WATER BASED BATTALI PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, BLOCK : GOSABA, DISTRICT : SOUTH 24 PARGANAS , SM/13840 New Inter connection and rising main with supply of specials of Augmentation of Battali W/S Scheme, Block-Gosaba under Canning Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Canning sub division Junior Engineer, 3 CSD ORD/000125/2023-2024 571/AD 15/05/2023 870 ARFIN CONSTRUCTION 11.53 0.00 0 80
2 SOUTH 24 PARGANAS Gosaba Alipore Division GROUND WATER BASED BATTALI PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, BLOCK : GOSABA, DISTRICT : SOUTH 24 PARGANAS , SM/13840 New Sinking of 02 (two) nos. 250mm x 150mm dia. 360 mtr. deep Tubewell by Direct Rotary Rig Method using P.V.C pipe and pre-packed Resin Bonded Gravel Filter of Battali W/S Scheme, Block - Gosaba under Canning Sub Division of Alipore Division, PHE Dte. (3rd Call) Assistant Engineer, Canning sub division Junior Engineer, 3 CSD ORD/000214/2023-2024 954/AD 06/06/2023 65 SALMAN CONSTRUCTION 43.94 32.70 74.42 100
3 SOUTH 24 PARGANAS Gosaba Alipore Division GROUND WATER BASED BATTALI PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, BLOCK : GOSABA, DISTRICT : SOUTH 24 PARGANAS , SM/13840 New Construction of OHR (150 Cum), Laying of Distribution System, Providing Functional Household Tap Connection etc. of Ground Water based Augmentation Piped Water Supply Scheme for the BATTALI, Block-Gosaba under Canning Sub-Division of Alipore Division, PHE Dte. [No. of FHTC= 1300] Assistant Engineer, Canning sub division Junior Engineer, 3 CSD ORD/000544/2023-2024 2210/AD 10/08/2023 300 FIDERE MARINE SERVICES PVT. LTD. 358.79 94.40 26.31 28
4 SOUTH 24 PARGANAS Gosaba Alipore Division GROUND WATER BASED BATTALI PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, BLOCK : GOSABA, DISTRICT : SOUTH 24 PARGANAS , SM/13840 New Construction of boundary wall at Head Work Site for Ground water Based at Battali Piped Water Supply Scheme Block - Gosaba under Canning Sub-Division of Alipore Division, PHE Dte. Assistant Engineer, Canning sub division Junior Engineer, 3 CSD ORD/000739/2024-2025 4396/AD 05/11/2024 45 FIDERE MARINE SERVICES PVT. LTD. 33.70 0.00 0 0
5 SOUTH 24 PARGANAS Gosaba Alipore Division GROUND WATER BASED BATTALI PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, BLOCK : GOSABA, DISTRICT : SOUTH 24 PARGANAS , SM/13840 New Construction of boundary wall at Pump House No-2 for Ground water Based at Battali Piped Water Supply Scheme Block - Gosaba under Canning Sub-Division of Alipore Division, PHE Dte. Assistant Engineer, Canning sub division Junior Engineer, 3 CSD ORD/000740/2024-2025 4397/AD 05/11/2024 30 SUBHO CONSTRUCTION 14.36 0.00 0 0
6 SOUTH 24 PARGANAS Gosaba Alipore Division GROUND WATER BASED BATTALI PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, BLOCK : GOSABA, DISTRICT : SOUTH 24 PARGANAS , SM/13840 New Construction of switch room cum chlorine room (5.4m x 3.6m) including Sanitary arrangement as per departmental drawing at the site of Battali W/S Scheme , Block - Gosaba under Canning Sub-Division of Alipore Division, PHE Dte. [Pump House-I] Assistant Engineer, Canning sub division Junior Engineer, 3 CSD ORD/001401/2022-2023 10926/AD 06/02/2023 634 ARBINA ENTERPRISE 8.88 0.00 0 100
7 SOUTH 24 PARGANAS Gosaba Alipore Division GROUND WATER BASED BATTALI PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, BLOCK : GOSABA, DISTRICT : SOUTH 24 PARGANAS , SM/13840 New Construction of switch room cum chlorine room (4.88m x 3.66m) including Sanitary arrangement as per departmental drawing at the site of Augmentation of Battali W/S Scheme , Block - Gosaba under Canning Sub-Division of Alipore Division, PHE Dte. [Pump House-II] Assistant Engineer, Canning sub division Junior Engineer, 3 CSD ORD/001402/2022-2023 10927/AD 06/02/2023 45 ARBINA ENTERPRISE 8.57 0.00 0 0
8 SOUTH 24 PARGANAS Gosaba Alipore Division GROUND WATER BASED BATTALI PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, BLOCK : GOSABA, DISTRICT : SOUTH 24 PARGANAS , SM/13840 New Conducting route survey, design distribution network and preparation & submission of DPR for Battali New Water Supply Scheme including Functional Household Tap Connection (FHTC) for implementation of JJM at Gosaba Block under Canning Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Canning sub division ORD/001881/2022-2023 7523/AD 28/11/2022 45 M/S R.DUTTA & CO. 4.32 4.32 100 99
9 SOUTH 24 PARGANAS Gosaba Alipore Division GROUND WATER BASED BATTALI PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, BLOCK : GOSABA, DISTRICT : SOUTH 24 PARGANAS , SM/13840 New Material Requisition To Resource Division RTOR000048/2023-2024 255/AD 24/04/2023 0 Resource Division 39.04 0.00 0 0
10 SOUTH 24 PARGANAS Gosaba Alipore Division GROUND WATER BASED BATTALI PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, BLOCK : GOSABA, DISTRICT : SOUTH 24 PARGANAS , SM/13840 New Material Requisition To Resource Division RTOR000409/2023-2024 363/AD 19/01/2024 0 Resource Division 8.01 0.00 0 0
11 SOUTH 24 PARGANAS Gosaba S24 Pgns Mechanical GROUND WATER BASED BATTALI PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, BLOCK : GOSABA, DISTRICT : SOUTH 24 PARGANAS , SM/13840 New Quotation for new service( power) connection at Battali PH-2 Water supply scheme under Gosaba block. Reference ID:-107071569, Application No :-1008591038 BILL/00502/2025-2026 42151 01/08/2025 0 WBSEDCL 4.77 0.00 0 0
12 SOUTH 24 PARGANAS Gosaba S24 Pgns Mechanical GROUND WATER BASED BATTALI PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, BLOCK : GOSABA, DISTRICT : SOUTH 24 PARGANAS , SM/13840 New Quotation for new service( power) connection at Batali PH-1 Water supply scheme under Gosaba block. Reference ID:-106748166, Application No :-1008091231 BILL/01841/2024-2025 BP-2024-25-469 18/11/2024 0 WBSEDCL 6.72 0.00 0 0
13 SOUTH 24 PARGANAS Gosaba S24 Pgns Mechanical GROUND WATER BASED BATTALI PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, BLOCK : GOSABA, DISTRICT : SOUTH 24 PARGANAS , SM/13840 New Supply, installation and commissioning of submersible pumping machinery along with allied accessories at P.H. 1&2, of Battali water supply scheme under South 24 Pgs. Mechanical Division, PHE Dte. [Block: Gosaba] Assistant Engineer Junior Engineer ORD/000548/2022-2023 411/SMD 16/02/2023 90 P.K. ENGINEERING 19.27 0.00 0 0
Total 561.90131.4223.39 
Showing 1 to 13 of 13 entries