Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
19 598.05 73.55 12.3  
1 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Preparation of design (Pile and Pile Cap) drawing for foundation of different capacity OHR of Harendragnagar PWSS under JJM at Kakdwip Block under Kakdwip Sub-Division of Alipore Division P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/000048/2023-2024 33/KSD 24/04/2023 4 GEOTECHNICAL ENGINEERS CONSORTIUM 0.49 0.49 100 100
2 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Allied works for pile and pile cap portion regarding the construction of 300 cum. capacity 20 mtr. staging height R.C.C. Over Head Reservoir as per departmental design, drawing and specification including R.C.C. Bored pile andile cap upto pedestal at Harendranagar, South 24 Parganas, Kakdwip Block under Kakdwip Sub-Division of Alipore Division P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division ORD/000277/2023-2024 1427/AD 13/07/2023 45 SUPRITI ENTERPRISE 32.00 0.00 0 0
3 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Laying distribution system, Functional Household Tap Connection (FHTC) to all households for Harendranagar Water Supply Scheme, Block - Kakdwip for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (Part-B) Junior Engineer 4, Raidghi Sub Division,Juniour Engineer_3, Kakdwip Sub Division ORD/000335/2022-2023 4065/AD 18/08/2022 30 M/S MODINA ENTERPRISE 19.21 13.68 71.21 40
4 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Laying distribution system, Functional Household Tap Connection (FHTC) to all households for Harendranagar Water Supply Scheme, Block - Kakdwip for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (Part-C) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/000336/2022-2023 4066/AD 18/08/2022 30 M/S. PARAMESWAR ENTERPRISE 12.68 0.00 0 0
5 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Laying distribution systemfor Providing Functional Household Tap Connection (FHTC) to all households for Harendranagar Water Supply Scheme, Block - Kakdwip for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (Part-D) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/000337/2022-2023 4067/AD 18/08/2022 21 M/S. MOYNA ENTERPRISE 7.49 3.74 49.93 100
6 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Sinking of 02 Nos. 250mm x 150mm dia. 360 mtr. deep Tubewell by D.R. Rig method using UPVC Pipe & Pre-packed Resin Bonded Gravel Filter at 1st and 2nd Tubewell Site of Harendranagar W/S Scheme, Block - Kakdwip for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Junior Engineer 4, Raidghi Sub Division ORD/000343/2022-2023 4070/AD 18/08/2022 45 AQUATECH ENGINEER 37.06 9.56 25.8 0
7 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Conducting route survey, design distribution network and preparation & submission of DPR for each of different new water supply scheme / each Augmentation water supply scheme (HARENDRANAGAR PWSS) including Functional Household Tap Connection (FHTC) for implementation of JJM at Kakdwip Block under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Junior Engineer 4, Raidghi Sub Division ORD/000501/2022-2023 2494/AD 27/06/2022 45 LEMNISCATE 4.71 4.71 100 100
8 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Construction of 300 cum. Over Head Reservoir (OHR), (20 mtr. Staging Height) along with 2 nos. Pump House, Laying distribution system, Rising Main, Functional Household Tap Connection (FHTC) to all households including design & drawing of pile foundation & pile cap after soil investagation including O & M of distribution system, rising main, FHTC for 1 year after completion of FHTC works for Harendranagar Water Supply Scheme, Block - Kakdwip for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (Part-A) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/000783/2022-2023 6537/AD 11/11/2022 300 SUPRITI ENTERPRISE 371.44 40.01 10.77 20
9 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Construction of boundary wall along with Land Development and Plinth Protection and Approach Road for Pump House at Head Work Site of Harendranagar W/S scheme, Block - Kakdwip under JJM of Kakdwip Sub-Division under Alipore Division, P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division ORD/000945/2023-2024 2978/AD 26/09/2023 45 C L B SYNDICATE 27.65 0.00 0 0
10 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Construction of boundary wall along with Land Development, Plinth Protection and Approach Road for Pump House at 2nd Tubewell Site of Harendranagar W/S scheme, Block - Kakdwip under JJM of Kakdwip Sub-Division under Alipore Division, P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/000947/2023-2024 2979/AD 26/09/2023 30 DEBIKA CONSTRUCTION 9.52 0.00 0 0
11 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Trial bore (1 no.) of 100mm dia depth up to 450 mtr for Sinking of 250mm x 150mm dia. deep Tubewell by D.R. Rig method at Head Work Site of Harendranagar W/S Scheme under JJM, Block - Kakdwip under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (2nd Call) Assistant Engineer, Kakdwip Sub Division Junior Engineer-1,Juniour Engineer_3, Kakdwip Sub Division ORD/001008/2023-2024 512/KSD 03/10/2023 7 S.K.GOLUI 2.72 1.36 50 100
12 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Hiring of Diesel Car / Luxury Taxi for official use of the Assistant Engineer, Kakdwip Sub Division, P.H.E. Dte. for the period from 01.08.2021 to 31.01.2022 Assistant Engineer, Kakdwip Sub Division ORD/001331/2021-2022 456/KSD 29/07/2021 180 PIKASU BOSE 2.40 0.00 0 100
13 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Hiring of Diesel Car / Luxury Taxi for official use of the Assistant Engineer, Kakdwip Sub Division, P.H.E. Dte. for the period from 01.02.2022 to 31.07.2022 Assistant Engineer, Kakdwip Sub Division ORD/001679/2021-2022 935/KSD 31/01/2022 180 PIKASU BOSE 2.40 0.00 0 100
14 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Making and fixing of permanent display board at headwork site of Harendranagar, Ramgopalpur, Uttar Kashiabad, Dakshin Kashiabad, Thangara, Nebutala PWSS under JJM at Kakdwip Block under Kakdwip Sub-Division of Alipore Division P.H.E.D. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_2, Kakdwip Sub Division ORD/002140/2023-2024 940/KSD 19/12/2023 5 M/S B. ENTERPRISE 0.94 0.00 0 100
15 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Material Requisition To Resource Division RTOR000118/2023-2024 654/AD 17/05/2023 Resource Division 7.62 0.00 0 0
16 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Material Requisition To Resource Division RTOR000440/2023-2024 4708/AD 18/12/2023 Resource Division 12.49 0.00 0 0
17 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Material Requisition To Resource Division RTOR000807/2023-2024 652/AD 30/01/2024 Resource Division 1.37 0.00 0 0
18 SOUTH 24 PARAGANAS Kakdwip Alipore Division GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Material Requisition To Resource Division RTOR000990/2023-2024 1783/AD 27/03/2024 Resource Division 27.00 0.00 0 0
19 SOUTH 24 PARAGANAS Kakdwip S24 Pgns Mechanical GROUND WATER BASED HARENDRANAGAR PIPED WATER SUPPLY SCHEME, UNDER ALIPORE DIVISION, PHE DTE., BLOCK : KAKDWIP, DISTRICT : SOUTH 24 PARGANAS , SM/11849 New Supply, installation and commissioning of submersible pumping machinery along with allied accessories at P.H. 1&2, Zone-I of Harendranagar water supply scheme under South 24 Pgs. Mechanical Division, PHE Dte. [Block: Kakdwip] Assistant Engineer -I Junior Engineer ORD/000430/2022-2023 3826/SMD 29/12/2022 90 RELIABLE CONSTRUCTION 18.86 0.00 0 0
Total 598.03 73.55 12.3