Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
4 | 24.35 | 0 | 0 | ||||||||||||||
1 | SOUTH 24 PARAGANAS | Alipore Division | Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households in Dakshin Ramkrishnapur, Zone-II including Operation & Maintenance of scheme for 1 (one) year, Block - Kulpi under Diamond Harbour Sub-Divi , SM/09974 | Retrofitting | Material Requisition To Resource Division | RTOR000101/2022-2023 | 7497/AD | 26/11/2022 | Resource Division | 3.31 | 0.00 | 0 | 0 | ||||
2 | SOUTH 24 PARAGANAS | Alipore Division | Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households in Dakshin Ramkrishnapur, Zone-II including Operation & Maintenance of scheme for 1 (one) year, Block - Kulpi under Diamond Harbour Sub-Divi , SM/09974 | Retrofitting | Material Requisition To Resource Division | RTOR000123/2022-2023 | 12049/AD | 27/02/2023 | Resource Division | 3.51 | 0.00 | 0 | 0 | ||||
3 | SOUTH 24 PARAGANAS | Alipore Division | Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households in Dakshin Ramkrishnapur, Zone-II including Operation & Maintenance of scheme for 1 (one) year, Block - Kulpi under Diamond Harbour Sub-Divi , SM/09974 | Retrofitting | Material Requisition To Resource Division | RTOR000864/2023-2024 | 771/AD | 03/02/2024 | Resource Division | 16.91 | 0.00 | 0 | 0 | ||||
4 | SOUTH 24 PARAGANAS | Alipore Division | Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households in Dakshin Ramkrishnapur, Zone-II including Operation & Maintenance of scheme for 1 (one) year, Block - Kulpi under Diamond Harbour Sub-Divi , SM/09974 | Retrofitting | Material Requisition To Resource Division | RTOR000932/2023-2024 | 1274/AD | 02/03/2024 | Resource Division | 0.62 | 0.00 | 0 | 0 | ||||
Total | 24.35 | 0.00 | 0 |