Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
42 314.36 151.85 48.3  
1 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Additional work for retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to additional households (1500 nos.) in excess of IMIS in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Supply Scheme including one year Operation & Maintenance of scheme, Block - Canning-I South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Canning sub division Junior Engineer, 4 CSD ORD/000337/2023-2024 1939/AD 02/08/2023 90 KIRON CONSTRUCTION 126.68 0.00 0 0
2 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - I) Assistant Engineer, Canning sub division ORD/000611/2020-2021 850/CSD 12/10/2020 45 DIPA CHHETRI 4.74 4.74 100 0
3 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - IV) Assistant Engineer, Canning sub division ORD/000614/2020-2021 853/CSD 12/10/2020 45 SUKANTA HALDER 4.74 4.72 99.58 0
4 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Gola Bari of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - I) Assistant Engineer, Canning sub division ORD/000616/2020-2021 855/CSD 12/10/2020 45 MODERN CONSTRUCTION 4.74 4.73 99.79 0
5 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Gola Bari of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - II) Assistant Engineer, Canning sub division ORD/000617/2020-2021 860/CSD 12/10/2020 45 C.S. CONSTRUCTION 4.73 4.63 97.89 95
6 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Gola Bari of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - III) Assistant Engineer, Canning sub division ORD/000618/2020-2021 861/CSD 12/10/2020 45 SARKAR CONSTRUCTION 4.75 4.72 99.37 0
7 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Gola Bari of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - IV) Assistant Engineer, Canning sub division ORD/000619/2020-2021 862/CSD 12/10/2020 45 ARFIN CONSTRUCTION 4.75 4.68 98.53 100
8 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Gola Bari of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - V) Assistant Engineer, Canning sub division ORD/000620/2020-2021 863/CSD 12/10/2020 45 KUNDU CONSTRUCTION CO. 4.74 4.72 99.58 0
9 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Modhu Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - I) Assistant Engineer, Canning sub division ORD/000621/2020-2021 864/CSD 12/10/2020 45 GANGA TUBEWELL AND HARDWARE 4.74 4.72 99.58 100
10 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Modhu Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - II) Assistant Engineer, Canning sub division ORD/000622/2020-2021 865/CSD 12/10/2020 45 M/S. M.K. NASKAR & CONSTRUCTION 4.73 4.72 99.79 100
11 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Modhu Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - III) Assistant Engineer, Canning sub division ORD/000623/2020-2021 866/CSD 12/10/2020 45 M/S. MANABESH ROY 4.74 4.74 100 0
12 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Modhu Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - IV) Assistant Engineer, Canning sub division ORD/000624/2020-2021 867/CSD 12/10/2020 45 ASHIS ENTERPRISE 4.72 4.71 99.79 100
13 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Modhu Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - V) Assistant Engineer, Canning sub division ORD/000625/2020-2021 868/CSD 12/10/2020 45 DEY ENTERPRISE (III) 4.74 4.74 100 100
14 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Kripa Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - I) Assistant Engineer, Canning sub division ORD/000630/2020-2021 869/CSD 12/10/2020 45 SAHANA ENTERPRISE 4.74 4.74 100 100
15 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Laying pipe line for FHTC work at Budhkhali W/S Scheme, Block - Canning-I under Canning Sub-Division of Alipore Division, PHE Dte. Assistant Engineer, Canning sub division ORD/000996/2021-2022 991/CSD 26/10/2021 30 MODERN CONSTRUCTION 3.74 3.72 99.47 100
16 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase ¿ XI) Assistant Engineer, Canning sub division ORD/001455/2020-2021 1003/CSD 13/11/2020 45 MONCON INDIA 4.70 4.70 100 100
17 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Gola Bari of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase ¿ IX) Assistant Engineer, Canning sub division ORD/001456/2020-2021 1005/CSD 13/11/2020 45 MODERN CONSTRUCTION 4.74 0.00 0 100
18 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Modhu Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase ¿ X) Assistant Engineer, Canning sub division ORD/001457/2020-2021 1006/CSD 13/11/2020 45 SOURAV NASKAR 4.79 4.78 99.79 100
19 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - VI) Assistant Engineer, Canning sub division ORD/001466/2020-2021 1018/CSD 23/11/2020 45 SUKANTA HALDER 4.71 0.00 0 100
20 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Extension of pipeline for FHTC work of Budhkhali Piped Water Supply Scheme Block-Canning-I under Canning Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Canning sub division ORD/001468/2021-2022 1490/CSD 09/02/2022 20 MITRA ASSOCIATE 4.60 4.59 99.78 100
21 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Repairing & relaying of damaged pipeline for FHTC work of Budhkhali Piped Water Supply Scheme Block-Canning-I under Canning Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Canning sub division ORD/001469/2021-2022 1491/CSD 09/02/2022 20 ASHIS ENTERPRISE 4.56 4.56 100 100
22 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - VII) Assistant Engineer, Canning sub division ORD/001470/2020-2021 1019/CSD 23/11/2020 45 A.S.A.CONSTRUCTION AND CONSULTANT 4.77 4.76 99.79 100
23 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - VIII) Assistant Engineer, Canning sub division ORD/001471/2020-2021 1020/CSD 23/11/2020 45 RAKTIM ENTERPRISE 4.69 4.68 99.79 100
24 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - IX) Assistant Engineer, Canning sub division ORD/001472/2020-2021 1021/CSD 23/11/2020 45 M/S TAMAL CHAKRABORTY 4.72 0.00 0 0
25 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - X) Assistant Engineer, Canning sub division ORD/001473/2020-2021 1022/CSD 23/11/2020 45 M/S. PROMILA CONSTRUCTION 4.62 0.00 0 0
26 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Gola Bari of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - VI) Assistant Engineer, Canning sub division ORD/001474/2020-2021 1023/CSD 23/11/2020 45 R.G. ENTERPRISE (I) 4.78 0.00 0 0
27 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Gola Bari of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - VII) Assistant Engineer, Canning sub division ORD/001475/2020-2021 1029/CSD 24/11/2020 45 BANERJEE ENTERPRISE 4.73 0.00 0 0
28 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Gola Bari of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - VIII) Assistant Engineer, Canning sub division ORD/001476/2020-2021 1030/CSD 24/11/2020 45 MODERN CONSTRUCTION 4.70 0.00 0 100
29 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Modhu Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - VI) Assistant Engineer, Canning sub division ORD/001477/2020-2021 1031/CSD 24/11/2020 45 GANGA TUBEWELL AND HARDWARE 4.79 4.66 97.29 100
30 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Modhu Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - VII) Assistant Engineer, Canning sub division ORD/001478/2020-2021 1032/CSD 24/11/2020 45 ASHIS ENTERPRISE 4.72 4.21 89.19 100
31 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Modhu Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - VIII) Assistant Engineer, Canning sub division ORD/001479/2020-2021 1033/CSD 24/11/2020 45 GANGA TUBEWELL AND HARDWARE 4.69 4.67 99.57 100
32 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Modhu Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - IX) Assistant Engineer, Canning sub division ORD/001480/2020-2021 1034/CSD 24/11/2020 45 S.C. ENTERPRISE (I) 4.66 4.58 98.28 100
33 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase ¿ XII) Assistant Engineer, Canning sub division ORD/001506/2020-2021 1004/CSD 13/11/2020 45 M/S KRISHNA MONDAL 4.75 4.74 99.79 100
34 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase ¿ XIV) Assistant Engineer, Canning sub division ORD/001556/2020-2021 1211/CSD 15/12/2020 45 M/S M3 SOLUTION 4.70 4.69 99.79 100
35 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase ¿ XV) Assistant Engineer, Canning sub division ORD/001557/2020-2021 1212/CSD 15/12/2020 45 M/S. MANABESH ROY 4.65 4.64 99.78 100
36 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase ¿ XVI) Assistant Engineer, Canning sub division ORD/001558/2020-2021 1214/CSD 15/12/2020 45 D.R.CONSTRUCTION 4.60 4.54 98.7 100
37 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - XVII) Assistant Engineer, Canning sub division ORD/001747/2020-2021 1450/CSD 27/01/2021 45 KIRON CONSTRUCTION 4.61 4.17 90.46 100
38 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - XVIII) Assistant Engineer, Canning sub division ORD/001748/2020-2021 1451/CSD 27/01/2021 45 KIRON CONSTRUCTION 4.69 4.34 92.54 100
39 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - XIX) Assistant Engineer, Canning sub division ORD/001751/2020-2021 1452/CSD 27/01/2021 45 KIRON CONSTRUCTION 4.57 3.88 84.9 100
40 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase - XX) Assistant Engineer, Canning sub division ORD/001754/2020-2021 1453/CSD 27/01/2021 45 KIRON CONSTRUCTION 4.65 4.50 96.77 100
41 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Laying of pipeline for providing house connection from H/O Rajkumar Sardar to H/O Bhagyadhar Sardar of Pakhirali habitation under Budhkhali W/S Scheme, Block-Canning-I under Canning Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Canning sub division ORD/002028/2020-2021 1517/CSD 10/02/2021 30 MONCON INDIA 0.43 0.42 97.67 0
42 SOUTH 24 PARAGANAS Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 18 (eighteen) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Budhkhali Water Suppl , SM/07641 Retrofitting Providing Functional Household Tap Connection (FHTC) to the households at Budh Khali of Budh Khali Water Supply Scheme, Block - Canning-I, South 24 Pgs. District under Canning Sub-Division of Alipore Division, P.H.E.Dte. (Phase ¿ XIII) Assistant Engineer, Canning sub division ORD/002039/2020-2021 1210/CSD 15/12/2020 45 M/S ARIYAN ENTERPRISE 4.72 4.71 99.79 100
Total 314.34 151.85 48.31