Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
7 | 2,263.19 | 9.16 | 0.4 | ||||||||||||||
1 | HOWRAH | Panchla | Howrah Division | GABBERIA-MALLIK BAGAN PIPED WATER SUPPLY SCHEME. , SM/13749 | New | Work Order for Additional laying distribution Pipeline work of Gabberia Mallickbagan PWSS at Panchla Block,of Howrah Sadar Sub Division under Howrah Division , PHE Dte. | AE/SADAR | je_how_rws_jagat | ORD/000069/2023-2024 | 1930/HD | 10/05/2023 | 60 | ADITYA HAZRA | 52.70 | 0.00 | 0 | 0 |
2 | HOWRAH | Panchla | Howrah Division | GABBERIA-MALLIK BAGAN PIPED WATER SUPPLY SCHEME. , SM/13749 | New | Work Order for Preparation of DPR with Route Survey for new piped water supply scheme of Gabberia PWSS (Mouza-Gabberia(CT) & Mallik Bagan (CT) of Panchla Block under Howrah Division PHE Dte. | AE/SADAR | JE Sadar | ORD/000079/2022-2023 | 1022/HD | 05/05/2022 | 15 | GEOTECHNICAL ENGINEERS CONSORTIUM | 3.04 | 3.04 | 100 | 0 |
3 | HOWRAH | Panchla | Howrah Division | GABBERIA-MALLIK BAGAN PIPED WATER SUPPLY SCHEME. , SM/13749 | New | Different Piped Water Supply Scheme with sinking of Tube-well, LDS, Rising Main, FHTC, and Construction of different capacity RCC OHR with 20.0 mtr. with Staging height including soil investigation & construction of switch rooms & boundary walls with gates and land development, drain and internal pathway at different TW site under Panchla Block, District:-Howrah [NEW SCHEME][Name of Schemes:-1)Paschim Panchla PWSS 2) Panchla PWSS 3) Gabberia-Mallik Bagan PWSS]. | AE/SADAR | je_how_rws_jagat | ORD/000148/2023-2024 | 2866/HD | 08/08/2023 | 365 | SAMIRON GHOSH | 1,986.19 | 6.12 | 0.31 | 17 |
4 | HOWRAH | Panchla | Howrah Division | GABBERIA-MALLIK BAGAN PIPED WATER SUPPLY SCHEME. , SM/13749 | New | Material Requisition To Resource Division | RTOR000081/2023-2024 | 135/HD | 10/01/2024 | Resource Division | 21.47 | 0.00 | 0 | 0 | |||
5 | HOWRAH | Panchla | Howrah Division | GABBERIA-MALLIK BAGAN PIPED WATER SUPPLY SCHEME. , SM/13749 | New | Material Requisition To Resource Division | RTOR000083/2022-2023 | 446/HD | 06/02/2023 | Resource Division | 59.98 | 0.00 | 0 | 0 | |||
6 | HOWRAH | Panchla | Electrical | GABBERIA-MALLIK BAGAN PIPED WATER SUPPLY SCHEME. , SM/13749 | New | Adhoc payment to WBSEDCL against service connnection | BILL/01127/2023-2024 | null | 28/06/2023 | WBSEDCL | 109.23 | 0.00 | 0 | 0 | |||
7 | HOWRAH | Panchla | Electrical | GABBERIA-MALLIK BAGAN PIPED WATER SUPPLY SCHEME. , SM/13749 | New | Supply, delivery & installation of submersible pumping machinery and other electrical/ mechanical equipments etc. including allied works for Gabberia Mallik Bagan water supply scheme, T.W. No.- I, II & III, Block: Panchla, District- Howrah under Electrical Division, PHE Dte. | Assistant Engineer Howrah mechanical Sub Division | Junior Engineer5 | ORD/000152/2022-2023 | 3538/ED | 30/12/2022 | 90 | INDIA ENTERPRISE | 30.58 | 0.00 | 0 | 0 |
Total | 2,263.20 | 9.16 | 0.4 |