Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
13 | 182 | 4.55 | 2.5 | ||||||||||||||
1 | HOWRAH | Howrah Division | Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 | Retrofitting | Surveying, Planning, Design, Delivery, Erection and Construction of Intake arrangement, WTP including inlet well , flash mixture Chemical House , Clariflocculator with sump , Rapid Gravity Filter with back washing system, sludge pond with sludge pumping system , CWR, OHR, Rising Main, Remodelling of Distribution System, Administrative Building, Sub-Station Building, Lab, Store ,Staff Quarters ,Boundary wall, Approach Road all complete including Mechanical/Electrical works both for raw water intake and treatment plant consisting of supply, installation, commissioning of pumping machineries, substation equipments etc inclusive of all kinds of accessories and ancillaries etc all complete along with 6 months trial run & 5(five) years operation and maintenance¿ for Surface Water Based Water Supply Scheme at Bally Jagacha Block, District ¿ Howrah | ORD/000002/2013-2014 | work Order-1697/HD | 06/11/2013 | GANNON DUNKERLEY & CO. LTD. | 25.83 | 0.00 | 0 | 0 | ||||
2 | HOWRAH | Howrah Division | Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 | Retrofitting | Work Order for Riverine effect over Construction of 400 m3 capacity and 20 mtr staging height RCC Over Head Reservoir including pile foundation & delivery inlet & outlet and overflow pipe connection and allied works as per departmental drawing (DRG No. ¿ PC-I/OHR/11/2012) at Chitnan water supply scheme under Uluberia Sub-Division, under Howrah Division PHE Dte | AE/Ulu | JE/USD | ORD/000395/2021-2022 | 160/HD | 25/01/2022 | 45 | S.N ENTERPRISE | 4.55 | 4.55 | 100 | 0 | |
3 | HOWRAH | Howrah Division | Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 | Retrofitting | Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block under Howrah Division, PHE Dte. (Part-B) [Beral Mouza] [Number of FHTC to be provided (Approx) : 387] | AE/Ulu | JE/USD | ORD/000396/2020-2021 | 45/HD | 05/01/2021 | 30 | MS ASOKE GHOSH AND BROTHERS | 22.44 | 0.00 | 0 | 0 | |
4 | HOWRAH | Howrah Division | Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 | Retrofitting | Retrofitting Chitnan Water Supply Scheme | VCH/000005/2021-2022 | null | 19/04/2021 | JAHANGIR ALAM | 23.87 | 0.00 | 0 | 0 | ||||
5 | HOWRAH | Howrah Division | Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 | Retrofitting | Retrofitting Chitnan Water Supply Scheme | VCH/000006/2021-2022 | W/120 | 20/07/2021 | ASHOKE GHOSH AND BROTHERS | 15.46 | 0.00 | 0 | 0 | ||||
6 | HOWRAH | Howrah Division | Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 | Retrofitting | Retrofitting Chitnan Water Supply scheme | VCH/000023/2021-2022 | W/170 | 09/08/2021 | PRASANTA SANA | 19.78 | 0.00 | 0 | 0 | ||||
7 | HOWRAH | Howrah Division | Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 | Retrofitting | Retrofitting Chitnan | VCH/000038/2021-2022 | W/171 | 09/08/2021 | BOSE AND CO. | 26.83 | 0.00 | 0 | 0 | ||||
8 | HOWRAH | Howrah Division | Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 | Retrofitting | Retrofitting Chitnan | VCH/000039/2021-2022 | null | 03/06/2021 | S.N ENTERPRISE | 26.88 | 0.00 | 0 | 0 | ||||
9 | HOWRAH | Howrah Division | Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 | Retrofitting | Work Order for Riverine effect over Construction of 400 m3 capacity and 20 mtr staging height RCC Over Head Reservoir including pile foundation & delivery inlet & outlet and overflow pipe connection and allied works as per departmental drawing (DRG No. ¿ PC-I/OHR/11/2012) at Chitnan water supply scheme under Uluberia Sub-Division, under Howrah Division PHE Dte | VCH/000348/2022-2023 | null | 20/07/2022 | S.N ENTERPRISE | 3.52 | 0.00 | 0 | 0 | ||||
10 | HOWRAH | Howrah Division | Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 | Retrofitting | Construction of Bounadry wall Chitnan Water supply scheme | VCH/000405/2022-2023 | BP-2022-23-71 | 14/06/2022 | M/S SARADA UDYOG | 2.14 | 0.00 | 0 | 0 | ||||
11 | HOWRAH | Howrah Division | Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 | Retrofitting | Construction of 28 nos stand post at in various place of Chitnan Water Supply scheme in Uluberia Sub-Division, under Howrah Division, P.H.E. Dte. (Part-II) | VCH/000802/2021-2022 | BP-2021-22-338 | 17/02/2022 | ANUP PAUL | 2.63 | 0.00 | 0 | 0 | ||||
12 | HOWRAH | Howrah Division | Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 | Retrofitting | Construction of 35 nos stand post at in various place of Chitnan Water Supply scheme in Uluberia Sub-Division, under Howrah Division, P.H.E. Dte. (Part-I) | VCH/000803/2021-2022 | BP-2021-22-339 | 17/02/2022 | ANUP PAUL | 3.28 | 0.00 | 0 | 0 | ||||
13 | HOWRAH | Howrah Division | Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 | Retrofitting | Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block under Howrah Division, PHE Dte. (Part-C) [Mirgram Mouza] [Number of FHTC to be provided (Approx) : 415] | VCH/001010/2021-2022 | BP-2021-22-472 | 30/03/2022 | PRASANTA SANA | 4.79 | 0.00 | 0 | 0 | ||||
Total | 181.98 | 4.55 | 2.5 |