Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
15 | 5,433.63 | 22.65 | 0.42 | ||||||||||||||
1 | PURULIA | Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I | Purulia Division | PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR PHASE III , SM/18653 | New | Laying of DI pipe along with interconnection arrangement at OHR site & Construction of Boundary wall & pathway & Sinking of Tubewell at Baghmundi (Zone-VII) under Purulia W/S Scheme (southern sector) of Purulia Division, PHE Dte. | Assistant Engineer | Junior Engineer-2 | ORD/000133/2024-2025 | 903/PD | 07/05/2024 | 60 | CHATTERJEE CONSTRUCTION | 95.89 | 0.00 | 0 | 0 |
2 | PURULIA | Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I | Purulia Division | PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR PHASE III , SM/18653 | New | Laying of DI pipe along with interconnection arrangement at OHR site & Construction of Boundary wall & pathway & Sinking of Tubewell at Baghmundi (Zone-VIII) under Purulia W/S Scheme (southern sector) of Purulia Division, PHE Dte. | ORD/000134/2024-2025 | 904/PD | 07/05/2024 | 60 | M/S SB CONSTRUCTION | 95.99 | 0.00 | 0 | 0 | ||
3 | PURULIA | Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I | Purulia Division | PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR PHASE III , SM/18653 | New | Laying of DI pipe along with interconnection arrangement at OHR site & Construction of Boundary wall & pathway & Sinking of Tubewell at Purulia-I (Zone-V) under Purulia W/S Scheme (southern sector) of Purulia Division, PHE Dte. | Assistant Engineer | Junior Engineer-1 | ORD/000148/2024-2025 | 919/PD | 07/05/2024 | 60 | M/S SB CONSTRUCTION | 61.00 | 0.00 | 0 | 50 |
4 | PURULIA | Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I | Purulia Division | PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR PHASE III , SM/18653 | New | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 250 CUM and staging height 20 mtr as per approved drawing ( No:PC-I/OHR/3/2012) including Laying Distribution pipe line and providing FHTC including other allied work & Operation & Maintenance of Distribution, pipe line (Dt/HDPE),including Sluce Valve & FHTC for the period of thirty six (36) month at zone-Ix of Bandwan Block under Purulia Piped Water Supply Scheme (Southern Sector) under Purulia Divn. PHE Dte. (Sl No.6) | Assistant Engineer | Junior Engineer-3 | ORD/000271/2023-2024 | 1099/PD | 14/08/2023 | 270 | JAL PRAVAHIKA PVT. LTD. | 492.94 | 22.65 | 4.59 | 40 |
5 | PURULIA | Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I | Purulia Division | PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR PHASE III , SM/18653 | New | Construction and commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe lines and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe lines (DI/HDPE), including Sluice Valves & FHTCs for the period of thirty six (36) month at Zone- V & VI of Bandwan Block under Purulia Piped Water Supply Scheme (Southern Sector) under Purulia Divn. PHE Dte.(SL-4) | Assistant Engineer | ORD/000272/2023-2024 | 1110/PD | 16/08/2023 | 270 | ANUP KUMAR SAHA | 647.66 | 0.00 | 0 | 0 | |
6 | PURULIA | Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I | Purulia Division | PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR PHASE III , SM/18653 | New | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 100 CUM and staging height 20 mtr as per approved drawing (No:PCI/OHR/3/2012) including Laying Distribution Pipe line and providing FHTC including other allied works & Operation & Maintenance of Distribution, Pipe line (DI/HDPE), including Sluice Valve & FHTC for the period of thirty six (36) month at Zone- XIII of Bandwan Block under Purulia Piped Water Supply Scheme (Southern Sector) under Purulia Divn. PHE Dte. (2nd Call)(SL-4) | Assistant Engineer | ORD/000274/2023-2024 | 1092/PD | 14/08/2023 | 270 | SAMAN KUMAR MAHATO | 184.53 | 0.00 | 0 | 0 | |
7 | PURULIA | Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I | Purulia Division | PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR PHASE III , SM/18653 | New | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 150 CUM and staging height 20 mtr as per approved drawing ( No:PC-I/OHR/3/2012) including Laying Distribution Pipe line and providing FHTC including other allied works & Operation & Maintenance of Distribution, Pipe line (DI/HDPE), including Sluice Valve & FHTC for the period of thirty six (36) month at Zone- XV of Bandwan Block under Purulia Piped Water Supply Scheme (Southern Sector ) under Purulia Divn. PHE Dte.(SL-11) | Assistant Engineer | ORD/000276/2023-2024 | 1108/PD | 16/08/2023 | 270 | MS D.PALIT AND CO. | 400.45 | 0.00 | 0 | 0 | |
8 | PURULIA | Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I | Purulia Division | PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR PHASE III , SM/18653 | New | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 150 CUM and staging height 20 mtr as per approved drawing ( No:PC-I/OHR/3/2012) including Laying Distribution Pipe line and providing FHTC including other allied works & Operation & Maintenance of Distribution, Pipe line (DI/HDPE), including Sluice Valve & FHTC for the period of thirty six (36) month at Zone- XVI of Bandwan Block under Purulia Piped Water Supply Scheme (Southern Sector ) under Purulia Divn. PHE Dte.(SL-12) | Assistant Engineer | ORD/000277/2023-2024 | 1104/PD | 14/08/2023 | 270 | ANUP KUMAR SAHA | 449.89 | 0.00 | 0 | 0 | |
9 | PURULIA | Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I | Purulia Division | PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR PHASE III , SM/18653 | New | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 350 CUM and staging height 20 mtr as per approved drawing ( No:PC-I/OHR/3/2012) including Laying Distribution Pipe line and providing FHTC including other allied works & Operation & Maintenance of Distribution, Pipe line (DI/HDPE), including Sluice Valve & FHTC for the period of thirty six(36) month at Zone- II of Bandwan Block under Purulia Piped Water Supply Scheme (Southern Sector ) under Purulia Divn. PHE Dte.(SL-2) | Assistant Engineer | ORD/000279/2023-2024 | 1095/PD | 14/08/2023 | 270 | MS D.PALIT AND CO. | 478.83 | 0.00 | 0 | 0 | |
10 | PURULIA | Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I | Purulia Division | PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR PHASE III , SM/18653 | New | Construction and commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe lines and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe lines (DI/HDPE), including Sluice Valves & FHTCs for the period of thirty six (36) month at Zone- III & IV of Bandwan Block under Purulia Piped Water Supply Scheme (Southern Sector) under Purulia Divn. PHE Dte.(SL-3) | Assistant Engineer | ORD/000280/2023-2024 | 1102/PD | 14/08/2023 | 270 | ANUP KUMAR SAHA | 671.47 | 0.00 | 0 | 0 | |
11 | PURULIA | Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I | Purulia Division | PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR PHASE III , SM/18653 | New | Construction of Boundary wall & Sinking of T/well at Purulia-II,Zone-II under Purulia W/S Scheme under Purulia Sadar Sub-Division under Purulia Division, PHE Dte. | ORD/000442/2024-2025 | 1504/PD | 27/08/2024 | 45 | RANJIB GHATAK | 21.02 | 0.00 | 0 | 0 | ||
12 | PURULIA | Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I | Purulia Division | PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR PHASE III , SM/18653 | New | Left out laying of Distribution Pipe Line for distribution System at Chatambari Mouza under command area of Jhalda Rural W/S Scheme Under Purulia W/S Scheme (Southern Sector) of Purulia Sadar Sub-Division under Purulia Division, PHE Dte. | Assistant Engineer | Junior Engineer-1 | ORD/000445/2024-2025 | 1507/PD | 27/08/2024 | 45 | BHAGABAN DAS KUMAR | 2.73 | 0.00 | 0 | 0 |
13 | PURULIA | Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I | Purulia Division | PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR PHASE III , SM/18653 | New | Construction and Commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 100 CUM and staging height 20 mtr as per approved drawing (No: PC-I/OHR/3/2012) including Laying Distribution Pipe Lines and providing FHTCs including other allied works & Operation & Maintenance of Distributions , Pipe Line (DI/HDPE), including Sluice Valves & FHTCs for the period of thirty six month (36) at Zone-I of Bandwan Block under Purulia Piped Water Supply Scheme (Southern Sector) under Purulia Divn. PHE Dte. (2nd Call) (SL-8) | Assistant Engineer | ORD/000905/2023-2024 | 1574/PD | 30/10/2023 | 270 | BOSE CONSTRUCTION | 181.34 | 0.00 | 0 | 0 | |
14 | PURULIA | Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I | Purulia Division | PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR PHASE III , SM/18653 | New | Construction and Commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe Lines and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe lines (DI/HDPE), including Sluice Valves & FHTCs for the period of thirty six month (36) at Zone-II & III of Manbazar-II Block under Purulia Piped Water Supply Scheme (Southern Sector) under Purulia Divn. PHE Dte. (SL No.2) | Assistant Engineer | Junior Engineer-2 | ORD/000909/2023-2024 | 1584/PD | 30/10/2023 | 270 | DEBAKI RANJAN SARKAR | 667.42 | 0.00 | 0 | 0 |
15 | PURULIA | Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I | Purulia Division | PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR PHASE III , SM/18653 | New | Construction and Commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe Lines and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe lines (DI/HDPE), including Sluice Valves & FHTCs for the period of thirty six month (36) at Zone-V & VI of Manbazar-II Block under Purulia Piped Water Supply Scheme (Southern Sector) under Purulia Divn. PHE Dte. (2nd Call) (SL No.10) | Assistant Engineer | Junior Engineer-1 | ORD/000914/2023-2024 | 1579/PD | 30/10/2023 | 270 | ANUP KUMAR SAHA | 982.47 | 0.00 | 0 | 20 |
Total | 5,433.63 | 22.65 | 0.42 |