Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
2 32,202.85 0 0  
1 PURULIA Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I Purulia Division PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR (PHASE I) , SM/18333 New Design, Surveying,Engineering, Supplying and Construction, Erection, Installation, Testing,Commissioning, of Fixed type Intake Jetty with Pump house, Construction of Sub-station; Raw Water Raising Main Bank Protection, 40 MLD (Minimum) capacity Water Treatment Plant (WTP) based on conventional technologies + 20% overloading; Clear Water Pumping Mains, Booster Stations (11 numbers) at Arsha, Baghmundi, Balarampur, Bandwan, Manbazar I (part), Manbazar II & Purulia I (Part) Blocks including pumping machineries on EPC/ Turnkey basis in a single package including 3 (three) months Trial Run and Operation & Maintenance for 3 years for Surface Based W/S scheme for Southern Sector under Purulia Distric. Assistant Engineer Junior Engineer,Junior Engineer-1,Junior Engineer-3 ORD/001820/2023-2024 53/PD 09/01/2024 810 WPIL LIMITED 32,180.00 0.00 0 0
2 PURULIA Arsha,Bagmundi,Balarampur,Bundwan,Manbazar - I,Manbazar - II,Purulia - I Purulia Division PURULIA WATER SUPPLY PROJECT SOUTHERN SECTOR (PHASE I) , SM/18333 New Construction of Boundary wall & Sinking of T/well at Jhalda-II,Zone-VII under Purulia W/S Scheme under Purulia Sadar Sub Division under Purulia Division, PHE Dte. Assistant Engineer Junior Engineer-2 ORD/003465/2023-2024 334/PD 01/03/2024 60 VIVEKANANDA CONSTRUCTION 22.85 0.00 0 0
Total 32,202.85 0.00 0