Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
13 775.92 263.09 33.91  
1 PURULIA Purulia Division Augmentation of Raghunathpur Pipe Water Supply Scheme for Zone 1A/1& Zone -1A/II , SM/14669 Augmentation Route Survey & Drawing Preparation for uncovered areas under Raghunathpur-II Block under Purulia Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000001/2023-2024 527/PD 10/04/2023 15 TIYAS CONSULTANCY AND INFRASTRUCTURE PRIVATE LIMITED 4.95 4.94 99.8 100
2 PURULIA Purulia Division Augmentation of Raghunathpur Pipe Water Supply Scheme for Zone 1A/1& Zone -1A/II , SM/14669 Augmentation Construction of Guard Room at WTP Campus under Raghunathpur Pipe Water Supply Scheme within Raghunathpur Sub-Division under Purulia Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000056/2023-2024 664/PD 17/05/2023 100 BISWAJIT MAJI 6.34 5.22 82.33 100
3 PURULIA Purulia Division Augmentation of Raghunathpur Pipe Water Supply Scheme for Zone 1A/1& Zone -1A/II , SM/14669 Augmentation Construction of Boundary wall, RCC Pillar, gate, Barbed wire at Ketlapur Mouza, JL No.-82, Plot No.-2790 under Para Block at OHR site under Raghunathpur W/S Scheme (German Project) of Raghunathpur Sub-Division under Purulia Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/000080/2023-2024 767/PD 08/06/2023 60 PARTHA SARATHI SAHABABU 10.96 4.35 39.69 100
4 PURULIA Purulia Division Augmentation of Raghunathpur Pipe Water Supply Scheme for Zone 1A/1& Zone -1A/II , SM/14669 Augmentation Construction of RCC clear water reservoir (CWR) of capacity 500 Cum with other allied works at Boosting Station under Raghunathpur W/S Scheme (German Project) of Raghunathpur Sub-Division under Purulia Division, PHE Dte. Assistant Engineer Junior Engineer ORD/001043/2022-2023 275/PD 27/02/2023 90 BOSE CONSTRUCTION 56.66 22.78 40.2 70
5 PURULIA Purulia Division Augmentation of Raghunathpur Pipe Water Supply Scheme for Zone 1A/1& Zone -1A/II , SM/14669 Augmentation Laying of distribution pipe line ( 90 mm,75mm & 63 mm dia HDPE pipe ) towards Garhpanchkot Prakriti Kendra under Raghunathpur W/S Scheme of Raghunathpur Sub-Divn, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001140/2022-2023 418/PD 21/03/2023 45 CHANDAN CHATTERJEE 10.97 0.00 0 0
6 PURULIA Purulia Division Augmentation of Raghunathpur Pipe Water Supply Scheme for Zone 1A/1& Zone -1A/II , SM/14669 Augmentation Laying Distribution pipe line including providing Functional Household Tap Connection (FHTC), and other allied works of Raghunathpur Water Supply Scheme (Zone-I A/I) of Raghunathpur Sub-Division under Purulia Division, PHE Dte. Assistant Engineer Junior Engineer ORD/001197/2022-2023 471/PD 28/03/2023 60 ASHOK KUMAR CHATTERJEE 261.64 101.35 38.74 35
7 PURULIA Purulia Division Augmentation of Raghunathpur Pipe Water Supply Scheme for Zone 1A/1& Zone -1A/II , SM/14669 Augmentation Laying Distribution pipe line including providing Functional Household Tap Connection (FHTC), Construction of 250 Cum OHR and other allied works of Raghunathpur Water Supply Scheme (Zone-I A/II) of Raghunathpur Sub-Division under Purulia Division, PHE Dte. Assistant Engineer Junior Engineer ORD/001198/2022-2023 472/PD 28/03/2023 270 ASHOK KUMAR CHATTERJEE 360.46 102.63 28.47 30
8 PURULIA Purulia Division Augmentation of Raghunathpur Pipe Water Supply Scheme for Zone 1A/1& Zone -1A/II , SM/14669 Augmentation Continuation work order for the work of Daily Maintenance for Beautification of existing gardens and all vacant places within the residential compound at Lakshmanpur WTP of Raghunathpur water supply Project within Raghunathpur Sub-Division under Purulia Division, P.H.E.Dte. ( w.e.f. 01.04.2023 to 31.03.2024) Assistant Engineer Junior Engineer ORD/001326/2022-2023 0137/RNP 30/03/2023 366 ASHOKE KUMAR CHATTERJEE 4.86 0.00 0 0
9 PURULIA Purulia Division Augmentation of Raghunathpur Pipe Water Supply Scheme for Zone 1A/1& Zone -1A/II , SM/14669 Augmentation Supply & delivery of spreading and levelling Filter media at Rapid Gravity sand filter beds after removal of existing not functioning filter media at Laxmanpur WTP under Purulia Division,P.H.E.Dte. Assistant Engineer Junior Engineer ORD/003455/2023-2024 317/PD 01/03/2024 60 ANUP KUMAR SAHA CIVIL CONTRACTORS PRIVATE LIMITED 15.86 12.03 75.85 100
10 PURULIA Purulia Division Augmentation of Raghunathpur Pipe Water Supply Scheme for Zone 1A/1& Zone -1A/II , SM/14669 Augmentation Sinking of 1(One) Nos. 200 mm dia DTH rigbored tubewell with other allied works at Boosting Pump Station (Seleta Mouza) of Raghunathpur W/S Scheme (German Project) of Raghunathpur Sub-Division under Purulia Division, PHE Dte. Assistant Engineer Junior Engineer ORD/003989/2023-2024 518/PD 16/03/2024 45 SUBRATA SINGHADEO 3.87 2.37 61.24 100
11 PURULIA Purulia Division Augmentation of Raghunathpur Pipe Water Supply Scheme for Zone 1A/1& Zone -1A/II , SM/14669 Augmentation Material Requisition To Resource Division RTOR000029/2022-2023 75/PD 17/01/2023 Resource Division 14.94 0.00 0 0
12 PURULIA Purulia Mechanical Augmentation of Raghunathpur Pipe Water Supply Scheme for Zone 1A/1& Zone -1A/II , SM/14669 Augmentation For new connection at Gobag near uposasthya kendra under augmentation of Raghunathpur zone 1A/1 & zone 1A/II BILL/00777/2023-2024 BP-23-24-277 01/02/2024 WBSEDCL PURULIA 2.81 0.00 0 0
13 PURULIA Purulia Mechanical Augmentation of Raghunathpur Pipe Water Supply Scheme for Zone 1A/1& Zone -1A/II , SM/14669 Augmentation Supply delivery installation of 1kg/hr gaseous chlorination system for Augmentation of Rathunathpur Pipe Water Supply scheme for Zone 1A/II under PMD PHE Dte. District Purulia. ASSISTANT ENGINEER(H.Q) JUNIOR ENGINEER ORD/000124/2023-2024 860/PMD 20/07/2023 30 CREATIVE WATER AND PROCESS TECHNOLOGIES PVT LTD. 21.60 7.42 34.35 75
Total 775.92 263.09 33.91