Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 524.19 86.42 16.49  
1 BANKURA Vishnupur Bankura Division Jamuna Band Pipe Water Supply Scheme , SM/18037 New SUPPLY, DELIVERY, CONSTRUCTION, COMMISSIONING AND COMPLETION OF ALL CIVIL WORKS INCLUDING ALL ALLIED, RELATED AND ENABLING WORKS FOR JAMUNABANDH PIPED WATER SUPPLY SCHEME, BLOCK- BISHNUPUR, DIST- BANKURA UNDER JJM INCLUDING TRIAL RUN FOR 3 MONTHS AND O&M FOR A PERIOD OF 3 YEARS UNDER BANKURA DIVISION,PHE Dte. Assistant Engineer Junior Engineer ORD/000374/2023-2024 2036/BQA 24/07/2023 540 DEBAKI RANJAN SARKAR 457.16 76.35 16.7 20
2 BANKURA Vishnupur Bankura Division Jamuna Band Pipe Water Supply Scheme , SM/18037 New Preparation of Detailed Project Report for Proposed ground water based JAMUNA BAND pipe water supply scheme, under Bankura Division Block : Bishnupur, District : Bankura under Jal Jeevan Mission Program under Bishnupur Sub-Division of Bankura Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001210/2023-2024 484/BQA 09/02/2024 150 ROY CHOWDHURY ASSOCIATES 3.56 0.00 0 91
3 BANKURA Vishnupur Bankura Division Jamuna Band Pipe Water Supply Scheme , SM/18037 New Preparation of Detailed Project Report for Proposed ground water based Dwarika pipe water supply scheme, under Bankura Division Block : Bishnupur, District : Bankura under Jal Jeevan Mission Program under Bishnupur Sub-Division of Bankura Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001211/2023-2024 485/BQA 09/02/2024 150 ROY CHOWDHURY ASSOCIATES 3.09 0.00 0 90
4 BANKURA Vishnupur Bankura Division Jamuna Band Pipe Water Supply Scheme , SM/18037 New Material Requisition To Resource Division RTOR000016/2023-2024 1120/BQA 12/05/2023 Resource Division 15.80 0.00 0 0
5 BANKURA Vishnupur Bankura Mechanical Jamuna Band Pipe Water Supply Scheme , SM/18037 New Jamuna Band Pipe Water Supply Scheme BILL/00173/2023-2024 null 28/06/2023 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 2.00 0.00 0 0
6 BANKURA Vishnupur Bankura Mechanical Jamuna Band Pipe Water Supply Scheme , SM/18037 New Submission of Quotation for new service connection at Jamunabundh TW-I W/S scheme under BMD.PHE Dte. SM/18037 BILL/00497/2024-2025 null 08/07/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 5.68 0.00 0 null
7 BANKURA Vishnupur Bankura Mechanical Jamuna Band Pipe Water Supply Scheme , SM/18037 New Acceptance cum Formal work order for the work of Providing, installation of Pumping machineries with other electro-mechanical accessories for proposed ground water based Jamuna Bandh piped water supply scheme under Bankura Mechanical Division, PHE Dte. Block : Bishnupur Dist: Bankura Assistant Engineer Junior Engineer ORD/000442/2023-2024 1771/BMD 01/08/2023 60 M/S BIPUL BANERJEE 36.90 10.07 27.29 65
Total 524.20 86.42 16.49