Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
1 22.93 11.92 51.98  
1 BANKURA Bankura Division Augmentation of Panchal Zone-I Water Supply Scheme , SM/17233 Augmentation Laying of distribution system, Creation of 'FHTC (Funtional House Hold Tap Connection)' for extra house hold and Repairing and Renovation of RCC Elevated Over Head Reservoir of 90 cum capacity with staging height 20 m and other allied works in connection with Jal Jeevan Mission (JJM) of Panchal Zone-I W/S Scheme within Sonamukhi Block under Bishnupur Sub-Division of Bankura Division, PHE Dte. Block Name:- Sonamukhi, Location of OHR :-Jamdoba No. of Mouzas Covered :- 3 nos., Name of Mouzas & JL No.:-Jamdoba (154), Ichharia (155), Bhabanipur (165) Total No. House Hold:-12 Assistant Engineer Junior Engineer ORD/000796/2022-2023 679/BQA 28/03/2023 90 SOUMITRA KUMAR DAS 22.93 11.92 51.98 40
Total 22.93 11.92 51.97