Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 638.19 116.04 18.18  
1 BANKURA Patrasayer Bankura Division Dhagaria Piped Water Supply Scheme , SM/15023 New SUPPLY, DELIVERY, CONSTRUCTION, COMMISSIONING AND COMPLETION OF ALL CIVIL WORKS INCLUDING ALL ALLIED, RELATED AND ENABLING WORKS FOR DHAGARIA PIPED WATER SUPPLY SCHEME, BLOCK- PATRASAYER, DIST- BANKURA UNDER JJM INCLUDING TRIAL RUN FOR 3 MONTHS AND O&M FOR A PERIOD OF 3 YEARS UNDER BANKURA DIVISION,PHE Dte. Assistant Engineer Junior Engineer ORD/000347/2023-2024 1971/BQA 18/07/2023 531 BAJRANG ROAD CONSTRUCTION PRIVATE LIMITED 534.20 88.32 16.53 28
2 BANKURA Patrasayer Bankura Division Dhagaria Piped Water Supply Scheme , SM/15023 New Material Requisition To Resource Division RTOR000010/2024-2025 2011/BQA 26/07/2024 Resource Division 11.40 0.00 0 0
3 BANKURA Patrasayer Bankura Division Dhagaria Piped Water Supply Scheme , SM/15023 New Material Requisition To Resource Division RTOR000034/2023-2024 1120/BQA 12/05/2023 Resource Division 26.98 0.00 0 0
4 BANKURA Patrasayer Bankura Mechanical Dhagaria Piped Water Supply Scheme , SM/15023 New Dhagaria Piped Water Supply Scheme BILL/01670/2023-2024 BP-2023-24-182 22/03/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 18.51 0.00 0 0
5 BANKURA Patrasayer Bankura Mechanical Dhagaria Piped Water Supply Scheme , SM/15023 New Acceptance cum Formal work order for the work of Providing, installation of Pumping machineries with other electro-mechanical accessories for newly sunk TW No-I, TW No-II of Dhagaria Piped water supply scheme under Bankura Mechanical Division, PHE Dte. Block : Patrashayar , Dist: Bankura. Assistant Engineer Junior Engineer ORD/000108/2023-2024 769/BMD 24/04/2023 180 M/S SWAPAN BANERJEE 47.10 27.72 58.85 58
Total 638.20 116.03 18.18