Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
4 | 429.6 | 8.25 | 1.92 | ||||||||||||||
1 | BANKURA | Patrasayer | Bankura Division | Chandal Bandi Piped Water Supply Scheme , SM/13999 | New | SUPPLY, DELIVERY, CONSTRUCTION, COMMISSIONING AND COMPLETION OF ALL CIVIL WORKS INCLUDING ALL ALLIED, RELATED AND ENABLING WORKS FOR CHANDAL BANDI PIPED WATER SUPPLY SCHEME, BLOCK- PATRASAYER, DIST- BANKURA UNDER JJM INCLUDING TRIAL RUN FOR 3 MONTHS AND O&M FOR A PERIOD OF 3 YEARS UNDER BANKURA DIVISION,PHE Dte. | Assistant Engineer | Junior Engineer | ORD/000108/2023-2024 | 1190/BQA | 22/05/2023 | 511 | PRAVAT SARKAR | 360.29 | 0.00 | 0 | 78 |
2 | BANKURA | Patrasayer | Bankura Division | Chandal Bandi Piped Water Supply Scheme , SM/13999 | New | Material Requisition To Resource Division | RTOR000008/2024-2025 | 2011/BQA | 26/07/2024 | Resource Division | 8.16 | 0.00 | 0 | 0 | |||
3 | BANKURA | Patrasayer | Bankura Division | Chandal Bandi Piped Water Supply Scheme , SM/13999 | New | Material Requisition To Resource Division | RTOR000029/2023-2024 | 1120/BQA | 12/05/2023 | Resource Division | 25.37 | 0.00 | 0 | 0 | |||
4 | BANKURA | Patrasayer | Bankura Mechanical | Chandal Bandi Piped Water Supply Scheme , SM/13999 | New | Acceptance cum Formal work order for the work of Providing, installation of Pumping machineries with other electro-mechanical accessories for newly sunk TW No-I & T/W No-II of Chandal Bandi piped water supply scheme under Bankura Mechanical Division, PHE Dte Block : Patrashayar, Dist: Bankura. | Assistant Engineer | Junior Engineer | ORD/000160/2023-2024 | 872/BMD | 04/05/2023 | 180 | GOENKA ENTERPRISE | 35.78 | 8.25 | 23.06 | 46 |
Total | 429.60 | 8.25 | 1.92 |