Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 2,357.94 5.23 0.22  
1 HOOGHLY Arambag Hooghly Division GROUND WATER BASED SELALPUR PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY, HOOGHLY DISTRICT , SM/18596 New BALUNDI,SELALPUR, MADHABPUR, DAHARKUNDU ZONE-II Piped Water Supply Scheme with T.W, SWITCH ROOM , BOUNDARY WALL, RISING MAIN, LDS, FHTC & Construction of OHR with 20 mtr. staging height including Soil Investigation work at ARAMBAGH Block under ARAMBAGH Sub-Division Under Hooghly Division PHE Dte Assistant Engineer Junior Engineer (Civill) ORD/000556/2023-2024 3191/HUG 31/10/2023 360 S & P ENTERPRISE 2,296.42 0.00 0 30
2 HOOGHLY Arambag Hooghly Division GROUND WATER BASED SELALPUR PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY, HOOGHLY DISTRICT , SM/18596 New Material Requisition To Resource Division RTOR000398/2023-2024 3057/52/Hug 11/10/2023 Resource Division 17.64 0.00 0 0
3 HOOGHLY Arambag Electrical GROUND WATER BASED SELALPUR PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY, HOOGHLY DISTRICT , SM/18596 New Quotation of New Service Connection for Selalpur w/s Scheme,PH No-II Block-Arambag Dist-Hooghly under Electrical Division,PHE Dte.(SM/18596) Application No-5004135212, Reference Id-503626837 BILL/00415/2024-2025 99 06/05/2024 WBSEDCL 7.66 0.00 0 null
4 HOOGHLY Arambag Electrical GROUND WATER BASED SELALPUR PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY, HOOGHLY DISTRICT , SM/18596 New Quotation Bill for New Service Connection at Selalpur W/S. Sch. TW-I BILL/04166/2023-2024 400 09/11/2023 WBSEDCL 3.98 0.00 0 0
5 HOOGHLY Arambag Electrical GROUND WATER BASED SELALPUR PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY, HOOGHLY DISTRICT , SM/18596 New Supply, delivery & installation of submersible pumping machinery and other electrical / mechanical equipments etc. including allied works for SELALPUR PIPED W/S SCHEME, T.W. No. III, Block: Arambag, District - Hooghly under JJM Program under Electrical Division PHE Dte. Assistant Engineer Howrah mechanical Sub Division Junior Engineer4 ORD/000132/2024-2025 1157/ED 14/06/2024 90 M/S DILIP MITRA 10.74 0.00 0 0
6 HOOGHLY Arambag Electrical GROUND WATER BASED SELALPUR PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY, HOOGHLY DISTRICT , SM/18596 New Supply, delivery & installation of submersible pumping machinery and other electrical/ mechanical equipments etc. including allied works for Selalpur water supply scheme, T.W. No.- I & II, Block: Aambag, District- Hooghly under Electrical Division, PHE Dte. Assistant Engineer 2 Junior Engineer4 ORD/000915/2023-2024 3586/ED 28/08/2023 90 M/S DILIP MITRA 21.50 5.23 24.33 30
Total 2,357.93 5.23 0.22