Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
2 101.94 71.25 69.89  
1 HOOGHLY Hooghly Division Retrofitting works for providing functional household tap connection within the left out mouza of Baruipara water supply scheme , SM/18110 Retrofitting Providing Functional Household Tap Connection (FHTC) under JJM within left out Mouzas of BARUIPARA PWSS under CHANDANNAGAR Sub-Division of Hooghly Division P.H.E Dte. Assistant Engineer (Civil) ORD/000344/2023-2024 2433/HUG 11/08/2023 90 MALLIKA ENTERPRISE 95.97 65.29 68.03 50
2 HOOGHLY Hooghly Division Retrofitting works for providing functional household tap connection within the left out mouza of Baruipara water supply scheme , SM/18110 Retrofitting Laying of rising main for Interconnection of Laying Distribution System & 7 th Tubewell Including Protection Work of BARUIPARA Water Supply Scheme under Chandannagar Sub-Division of Hooghly Division, PHE Dte. Assistant Engineer (Civil) ORD/000388/2022-2023 2141/HUG 26/09/2022 20 AMBIAN INFRASTRUTTURE 5.97 5.96 99.83 0
Total 101.93 71.26 69.9