Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 188.69 75.22 39.86  
1 HOOGHLY Polba - Dadpur Hooghly Division BASTA PIPED W/S SCHEME UNDER POLBA DADPUR BLOCK , SM/16763 New Preparation of DPR for BASTA Piped Water Supply Scheme Under Chinsurah Sub-Division of Hooghly Division P.H.E Dte. [Block-POLBA DADPUR]. Assistant Engineer (Civil) ORD/000085/2024-2025 687/CH 09/08/2024 7 DULAL MAJUMDER 2.58 0.00 0 0
2 HOOGHLY Polba - Dadpur Hooghly Division BASTA PIPED W/S SCHEME UNDER POLBA DADPUR BLOCK , SM/16763 New BASTA Piped Water Supply Scheme with Sinking of tube-well, Laying Distrubtuion System, Rising Main, Providing FHTC, construction of switch-rooms & boundary walls at different TW site under Hooghly Division, PHE Dte. within POLBA-DADPUR Block, District:- Hooghly Assistant Engineer (Civil) Junior Engineer (Civill) ORD/000780/2022-2023 844/HUG 23/03/2023 90 TOTON MONDAL 142.86 69.23 48.46 60
3 HOOGHLY Polba - Dadpur Hooghly Division BASTA PIPED W/S SCHEME UNDER POLBA DADPUR BLOCK , SM/16763 New Material Requisition To Resource Division RTOR000115/2023-2024 1264/10/HUG 03/05/2023 Resource Division 9.67 0.00 0 0
4 HOOGHLY Polba - Dadpur Hooghly Division BASTA PIPED W/S SCHEME UNDER POLBA DADPUR BLOCK , SM/16763 New Material Requisition To Resource Division RTOR000229/2023-2024 1386/8/Hug 15/05/2023 Resource Division 3.33 0.00 0 0
5 HOOGHLY Polba - Dadpur Hooghly Division BASTA PIPED W/S SCHEME UNDER POLBA DADPUR BLOCK , SM/16763 New Material Requisition To Resource Division RTOR000502/2023-2024 3059/16/Hug 11/10/2023 Resource Division 3.33 0.00 0 0
6 HOOGHLY Polba - Dadpur Electrical BASTA PIPED W/S SCHEME UNDER POLBA DADPUR BLOCK , SM/16763 New Quotation Bill for New Service Connection at Basta W/S. Sch.TW-I BILL/04580/2023-2024 578 27/12/2023 WBSEDCL 3.06 0.00 0 0
7 HOOGHLY Polba - Dadpur Electrical BASTA PIPED W/S SCHEME UNDER POLBA DADPUR BLOCK , SM/16763 New Quotation Bill for New Service Connection at Basta W/S. Sch. TW-II BILL/05115/2023-2024 686 19/01/2024 WBSEDCL 3.61 0.00 0 0
8 HOOGHLY Polba - Dadpur Electrical BASTA PIPED W/S SCHEME UNDER POLBA DADPUR BLOCK , SM/16763 New Supply, delivery & installation of submersible pumping machinery and other electrical/ mechanical equipments etc. including allied works for Basta water supply scheme, T.W. No. I & II, Block: Polba Dadpur, District- Hooghly under Electrical Division, PHE Dte. Assistant Engineer 2 Junior Engineer4 ORD/001215/2023-2024 4541/ED 23/11/2023 90 SHIVAM ENTERPRISE 20.25 5.99 29.58 95
Total 188.70 75.22 39.86