Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 354.34 84.55 23.86  
1 HOOGHLY Haripal Hooghly Division GROUND WATER BASED RAJABALLABHBATI PIPED W/S SCHEME , SM/16136 New RAJABALLABHBATI Piped Water Supply Scheme with Sinking of tube-well, LDS, Rising Main, FHTC, Construction of 100 cum capacity RCC OHR with 20.0 mtr. with Staging height including soil investigation & construction of switch-rooms & boundary walls at different TW site under HARIPAL Block, District:- Hooghly [NEW SCHEME] Assistant Engineer (Civil) Junior Engineer (Civill) ORD/000270/2023-2024 2289/HUG 03/08/2023 270 TOTON MONDAL 213.81 78.26 36.6 50
2 HOOGHLY Haripal Hooghly Division GROUND WATER BASED RAJABALLABHBATI PIPED W/S SCHEME , SM/16136 New Preparation of DPR for different works for providing Functional Household Tap Connection (FHTC) of Rajballabhbati Piped Water Supply Scheme under Haripal Block, Hooghly District under Chandannagar Sub-Division, PHE Dte. (PART-A). Assistant Engineer (Civil) ORD/000765/2023-2024 149/Chan 16/02/2024 15 TECHVISION 0.84 0.42 50 98
3 HOOGHLY Haripal Hooghly Division GROUND WATER BASED RAJABALLABHBATI PIPED W/S SCHEME , SM/16136 New Material Requisition To Resource Division RTOR000290/2023-2024 1383/36/Hug 15/05/2023 Resource Division 3.33 0.00 0 0
4 HOOGHLY Haripal Hooghly Division GROUND WATER BASED RAJABALLABHBATI PIPED W/S SCHEME , SM/16136 New Material Requisition To Resource Division RTOR000460/2023-2024 3058/19/Hug 11/10/2023 Resource Division 3.33 0.00 0 0
5 HOOGHLY Haripal Electrical GROUND WATER BASED RAJABALLABHBATI PIPED W/S SCHEME , SM/16136 New Adhoc Payment to WBSEDCL against service connection BILL/01120/2023-2024 null 27/06/2023 WBSEDCL 104.27 0.00 0 0
6 HOOGHLY Haripal Electrical GROUND WATER BASED RAJABALLABHBATI PIPED W/S SCHEME , SM/16136 New Quotation Bill for New Service Connection at Rajballavbati W/S. Sch. TW-I BILL/04221/2023-2024 412 09/11/2023 WBSEDCL 6.55 0.00 0 0
7 HOOGHLY Haripal Electrical GROUND WATER BASED RAJABALLABHBATI PIPED W/S SCHEME , SM/16136 New Quotation for new service connection charge at Rajballabhbati PWSS, TW - II BILL/04485/2023-2024 528 15/12/2023 WBSEDCL 1.71 0.00 0 0
8 HOOGHLY Haripal Electrical GROUND WATER BASED RAJABALLABHBATI PIPED W/S SCHEME , SM/16136 New Supply, delivery & installation of submersible pumping machinery and other electrical/ mechanical equipments etc. including allied works for Rajaballabhbati water supply scheme, T.W. No. I & II, Block: Haripal, District- Hooghly under Electrical Division, PHE Dte. Assistant Engineer 2 Junior Engineer4 ORD/000033/2023-2024 1710/ED 18/04/2023 90 ELECTRICAL & MECHANICAL ENGINEERING CORPORATION 20.50 5.87 28.63 20
Total 354.33 84.56 23.86