Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
14 1,032.25 122.24 11.84  
1 HOOGHLY Singur Hooghly Division BASUBATI PIPED WATER SUPPLY SCHEME , SM/12365 New Sinking of 5 nos. 300 X200 mm dia Tube Well 210 mtr. Depth by D.R. Rig method using UPVC pipe (CD) and UPVC Deep Well Screen (RDS) at ATISARA, NANDA, NAWPARA,BASUBATI & ASTARA W/S Scheme underChandannagar Sub-Division of Hooghly Division, P.H.E. Dte.. Assistant Engineer (Civil) Junior Engineer (Civill) ORD/000203/2023-2024 1818/HUG 22/06/2023 45 OSMAN SEKH 80.85 0.00 0 100
2 HOOGHLY Singur Hooghly Division BASUBATI PIPED WATER SUPPLY SCHEME , SM/12365 New Construction of 500 cum capacity OHR with 20 mtr. staging height including Soil Investigation work, Laying Distribution System, Rising Main& Interconnection between O.H.R, TW No-I & II, Construction of 1 No 5.4M X 3.6M Switch Room with Sanitary and Water Supply Arrangements & Boundary Wall at Head Work Site, Construction of 1 No 3.6M x 3.0M Switch Room with Sanitary & Water Supply arrangement & Boundary Wall at 2nd T/W Site including Providing FHTC in BASUBATI Water Supply Scheme at SINGUR Block under Chandannagar Sub-Division of Hooghly Division, PHE Dte. Assistant Engineer (Civil) Junior Engineer (Civill) ORD/000747/2022-2023 683/Hug 10/03/2023 300 MINTU CHAKRABORTY 618.81 110.89 17.92 50
3 HOOGHLY Singur Hooghly Division BASUBATI PIPED WATER SUPPLY SCHEME , SM/12365 New Sinking of Five Nos. Big Dia Tube Well (300 mm X 200 mm) with supply of uPVC pipes & Strainer having depth upto180 Mtr at ATISARA, NANDA, NOWPARA, BASUBATI & ASTARA PWSS of CHANDANNAGAR Sub-Division under Hooghly Division, PHE Dte. Assistant Engineer (Civil) ORD/000784/2022-2023 878/HUG 27/03/2023 45 MS D.PALIT AND CO. 62.24 0.00 0 100
4 HOOGHLY Singur Hooghly Division BASUBATI PIPED WATER SUPPLY SCHEME , SM/12365 New Designing making and erection of Display Board using logo and tag line of Jal Jeevan Mission to the placed at different work sites and HGJ villages for awareness generation among the people in the district of Hooghly under Chandannagar Sub Division under Hooghly Division PHE Dte.(Basubati PWSS, Purushottampur PWSS, Nawpara PWSS, Bighati Z-II PWSS, Shibrambati Z-I PWSS, Sinhal Pathan PWSS) Assistant Engineer (Civil) Junior Engineer (Civill) ORD/000975/2023-2024 303/Chan 15/03/2024 7 AMBIAN INFRASTRUCTURE 0.95 0.00 0 100
5 HOOGHLY Singur Hooghly Division BASUBATI PIPED WATER SUPPLY SCHEME , SM/12365 New Material Requisition To Resource Division RTOR000130/2022-2023 2471/3/Hug 18/11/2022 Resource Division 19.58 0.00 0 0
6 HOOGHLY Singur Hooghly Division BASUBATI PIPED WATER SUPPLY SCHEME , SM/12365 New Material Requisition To Resource Division RTOR000158/2022-2023 01/11/Hug 02/01/2023 Resource Division 19.58 0.00 0 0
7 HOOGHLY Singur Hooghly Division BASUBATI PIPED WATER SUPPLY SCHEME , SM/12365 New Material Requisition To Resource Division RTOR000191/2022-2023 109/1/Hug 10/01/2023 Resource Division 55.09 0.00 0 0
8 HOOGHLY Singur Hooghly Division BASUBATI PIPED WATER SUPPLY SCHEME , SM/12365 New Material Requisition To Resource Division RTOR000206/2023-2024 1383/9/Hug 15/05/2023 Resource Division 19.93 0.00 0 0
9 HOOGHLY Singur Hooghly Division BASUBATI PIPED WATER SUPPLY SCHEME , SM/12365 New Material Requisition To Resource Division RTOR000406/2023-2024 3058/30/Hug 11/10/2023 Resource Division 19.93 0.00 0 0
10 HOOGHLY Singur Electrical BASUBATI PIPED WATER SUPPLY SCHEME , SM/12365 New Adhoc Payment to WBSEDCL against service connection BILL/01117/2023-2024 null 27/06/2023 WBSEDCL 94.34 0.00 0 0
11 HOOGHLY Singur Electrical BASUBATI PIPED WATER SUPPLY SCHEME , SM/12365 New Quotation for new service connection at Basubati W/S Sch, TW-I (Head Work site), Dist. Hooghly BILL/01916/2023-2024 90 13/07/2023 WBSEDCL 3.85 0.00 0 0
12 HOOGHLY Singur Electrical BASUBATI PIPED WATER SUPPLY SCHEME , SM/12365 New Quotation Bill for New Service Connection at Basubati W/S. Sch. TW-II BILL/04512/2023-2024 553 21/12/2023 WBSEDCL 2.59 0.00 0 0
13 HOOGHLY Singur Electrical BASUBATI PIPED WATER SUPPLY SCHEME , SM/12365 New Supply, delivery & installation of submersible pumping machinery and other electrical/ mechanical equipments etc. including allied works for Basubati water supply scheme, T.W. No.- I & II, Block: Singur, District- Hooghly under Electrical Division, PHE Dte. Assistant Engineer 2 Junior Engineer4 ORD/000130/2022-2023 3484/ED 30/12/2022 90 ASHUTOSH DAS & CO. 23.01 11.35 49.33 90
14 HOOGHLY Singur Electrical BASUBATI PIPED WATER SUPPLY SCHEME , SM/12365 New Supply, delivery & installation of submersible pumping machinery and other electrical/ mechanical equipments etc. including allied works for Basubati water supply scheme, T.W. No. III, Block: Singur, District - Hooghly under Electrical Division, PHE Dte. ORD/000873/2023-2024 3446/ED 11/08/2023 90 BISALAXMI ENTERPRISE 11.50 0.00 0 0
Total 1,032.25 122.24 11.84