Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 68.5 8.15 11.9  
1 HOOGHLY Hooghly Division RETROFITTING WORKS FOR PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION (FHTC) WITHIN THE COMMAND AREA OF RADHABALLABHPUR WATER SUPPLY SCHEME , SM/07541 Retrofitting Providing 150 nos Functional Household Tap Connection (FHTC) within the command area of Radhaballvpur Water Supply Scheme Under Arambagh Sub-Division of Hooghly Division P.H.E Dte Assistant Engineer Junior Engineer (Civill) ORD/000269/2021-2022 2123/Hug 01/12/2021 20 SWASTIK ENTERPRISE 8.08 8.15 100.87 100
2 HOOGHLY Hooghly Division RETROFITTING WORKS FOR PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION (FHTC) WITHIN THE COMMAND AREA OF RADHABALLABHPUR WATER SUPPLY SCHEME , SM/07541 Retrofitting Providing 150 nos Functional Household Tap Connection (FHTC) within the command area of RADHABALLAVPUR Water Supply Scheme Under ARAMBAG Sub-Division of Hooghly Division P.H.E Dte Assistant Engineer,Assistant Engineer (Civil) Junior Engineer (Civill) ORD/000313/2021-2022 2232/Hug 15/12/2021 20 DREAM INFRASTRUCTURE 4.92 0.00 0 100
3 HOOGHLY Hooghly Division RETROFITTING WORKS FOR PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION (FHTC) WITHIN THE COMMAND AREA OF RADHABALLABHPUR WATER SUPPLY SCHEME , SM/07541 Retrofitting FHTC VCH/000533/2021-2022 null 23/07/2021 DOULPHIN ENTERPRISE (RANJIT KHANRA) 1.97 0.00 0 0
4 HOOGHLY Hooghly Division RETROFITTING WORKS FOR PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION (FHTC) WITHIN THE COMMAND AREA OF RADHABALLABHPUR WATER SUPPLY SCHEME , SM/07541 Retrofitting Placement of Fund VCH/002590/2021-2022 844368 19/01/2022 JAL JEEVAN MISSION WEST BENGAL ESCROW AC 11.53 0.00 0 0
5 HOOGHLY Hooghly Division RETROFITTING WORKS FOR PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION (FHTC) WITHIN THE COMMAND AREA OF RADHABALLABHPUR WATER SUPPLY SCHEME , SM/07541 Retrofitting FHTC VCH/002616/2020-2021 null 19/03/2021 DOULPHIN ENTERPRISE (RANJIT KHANRA) 42.00 0.00 0 0
Total 68.52 8.15 11.9