Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
7 | 76.78 | 9.85 | 12.83 | ||||||||||||||
1 | HOOGHLY | Hooghly Division | Retrofitting Works for providing 1089 nos Functional Household Tap Connection(FHTC) within the Dakshinkul, Baganbati & Gazipur Mouza of Malia Water Supply Schem , SM/06765 | Retrofitting | Laying pipe line For damaged portion of MALIA Water Supply Scheme under Chandannagar Sub-Division of Hooghly Division P.H.E Dte. | Assistant Engineer (Civil) | Junior Engineer (Civill) | ORD/000389/2022-2023 | 2142/HUG | 26/09/2022 | 20 | WELFARE ENGINEER'S CO - OPERATIVE SOCIETY LTD | 4.95 | 4.95 | 100 | 100 | |
2 | HOOGHLY | Hooghly Division | Retrofitting Works for providing 1089 nos Functional Household Tap Connection(FHTC) within the Dakshinkul, Baganbati & Gazipur Mouza of Malia Water Supply Schem , SM/06765 | Retrofitting | Construction of 3.6 X 3.0 m Swicth Room with Additional Plinth Height along with laying DI rising main at 3rd boosting tubewell site for Malia Water Supply Scheme under Chandannagar Sub - Division, PHE DTE. | Assistant Engineer (Civil) | Junior Engineer (Civill) | ORD/000888/2020-2021 | 121/Chan | 24/02/2021 | 45 | M/S S.G. CONSTRUCTION | 4.97 | 4.90 | 98.59 | 100 | |
3 | HOOGHLY | Hooghly Division | Retrofitting Works for providing 1089 nos Functional Household Tap Connection(FHTC) within the Dakshinkul, Baganbati & Gazipur Mouza of Malia Water Supply Schem , SM/06765 | Retrofitting | Material Requisition To Resource Division | RTOR000033/2022-2023 | 1125/6/HUG | 06/06/2022 | Resource Division | 12.32 | 0.00 | 0 | 0 | ||||
4 | HOOGHLY | Hooghly Division | Retrofitting Works for providing 1089 nos Functional Household Tap Connection(FHTC) within the Dakshinkul, Baganbati & Gazipur Mouza of Malia Water Supply Schem , SM/06765 | Retrofitting | Material Requisition To Resource Division | RTOR000125/2021-2022 | 2197/HUG | 14/12/2021 | Resource Division | 1.59 | 0.00 | 0 | 0 | ||||
5 | HOOGHLY | Hooghly Division | Retrofitting Works for providing 1089 nos Functional Household Tap Connection(FHTC) within the Dakshinkul, Baganbati & Gazipur Mouza of Malia Water Supply Schem , SM/06765 | Retrofitting | FHTC | VCH/001919/2020-2021 | null | 15/02/2021 | PAUL CONSTRUCTION (RANJIT KUMAR PAUL) | 36.00 | 0.00 | 0 | 0 | ||||
6 | HOOGHLY | Hooghly Division | Retrofitting Works for providing 1089 nos Functional Household Tap Connection(FHTC) within the Dakshinkul, Baganbati & Gazipur Mouza of Malia Water Supply Schem , SM/06765 | Retrofitting | SURVEY | VCH/002112/2021-2022 | null | 28/01/2022 | SIKHA ENTERPRISE | 5.10 | 0.00 | 0 | 0 | ||||
7 | HOOGHLY | Hooghly Division | Retrofitting Works for providing 1089 nos Functional Household Tap Connection(FHTC) within the Dakshinkul, Baganbati & Gazipur Mouza of Malia Water Supply Schem , SM/06765 | Retrofitting | Direct purchase of land for Lakshmipur PWSS | VCH/002242/2021-2022 | 844321 | 09/11/2021 | HOOGHLY ZILLA PARISHAD | 11.85 | 0.00 | 0 | 0 | ||||
Total | 76.78 | 9.85 | 12.83 |