Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 533.4 299.11 56.08  
1 NORTH 24 PARAGANAS Barasat Division Augmentation of Hingalganj Piped water supply scheme Zone-II , SM/14513 Augmentation Acceptance cum work order for Sinking of 2 nos. 300 mm. x 200 mm. dia. 360 mtr deep Tubewell by D.R. Rig method at PH No.-5 & 6 with PVC pipe & strainer having 300mm dia 48 mtr. long housing pipe & 200mm dia 30 mtr. long filter for Augmentation of Hingalganj w/s scheme (Zone-II), Hingalganj block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer ORD/000735/2023-2024 2489/BD 18/08/2023 30 M/S DATTA ENTERPRISE. 51.63 19.38 37.54 100
2 NORTH 24 PARAGANAS Barasat Division Augmentation of Hingalganj Piped water supply scheme Zone-II , SM/14513 Augmentation Acceptance cum work order for Route Survey, Design Drawing & DPR Preparation for Augmentation of Hingalganj Zone - II Piped Water Supply Scheme under Barasat Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000772/2022-2023 636/HSD 08/04/2022 15 SRIJAN ECOLOGICAL UPLIFTMENT PVT.LTD. 4.39 4.39 100 0
3 NORTH 24 PARAGANAS Barasat Division Augmentation of Hingalganj Piped water supply scheme Zone-II , SM/14513 Augmentation Formal work order for Laying of UPVC/DI distribution pipe line and providing Functional Household Tap Connection for Augmentation of Hingalganj water supply scheme (Z-II), Hingalganj Block under Hasnabad Sub-Division, PHE Dte. Assistant Engineer Junior Engineer ORD/001161/2022-2023 700/BD 03/03/2023 90 M/S NIRMAN CONSTRUCTION. 313.44 265.94 84.85 40
4 NORTH 24 PARAGANAS Barasat Division Augmentation of Hingalganj Piped water supply scheme Zone-II , SM/14513 Augmentation Acceptance cum work order for Sinking of 2 nos. 300 mm. x 200 mm. dia. 360 mtr deep Tubewell by D.R. Rig method at PH No.-3 & 4 with PVC pipe & strainer having 300mm dia 48 mtr. long housing pipe & 200mm dia 30 mtr. long filter for Augmentation of Hingalganj w/s scheme (Zone-II), Hingalganj block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001680/2023-2024 527/BD 20/02/2024 45 UTPAL CONSTRUCTION & CO. 49.99 0.00 0 0
5 NORTH 24 PARAGANAS Barasat Division Augmentation of Hingalganj Piped water supply scheme Zone-II , SM/14513 Augmentation Acceptance cum work order for inking of 2 nos. 300 mm. x 200 mm. dia. 360 mtr deep Tubewell by D.R. Rig method at PH No.-1 & 2 with PVC pipe & strainer having 300mm dia 48 mtr. long housing pipe & 200mm dia 30 mtr. long filter for Augmentation of Hingalganj w/s scheme (Zone-II), Hingalganj block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001684/2023-2024 525/BD 20/02/2024 45 UTPAL CONSTRUCTION & CO. 49.99 0.00 0 0
6 NORTH 24 PARAGANAS Barasat Division Augmentation of Hingalganj Piped water supply scheme Zone-II , SM/14513 Augmentation Acceptance cum work order for 2 nos. pump connection at PH No.-5 & 6 in connection with Augmentation for Hingalganj w/s (Z-II) scheme, Hingalganj block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001845/2023-2024 271/HSD 06/03/2024 10 M/S RAJPATH CONSTRUCTION. 0.96 0.00 0 100
7 NORTH 24 PARAGANAS Eastern Mechanical Augmentation of Hingalganj Piped water supply scheme Zone-II , SM/14513 Augmentation Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.I, II, III, IV,V and VI (Zone-II) (Rep.) under Hingalganj Aug. W/S Scheme, Block- Hingalganj in District of 24 Pgs. (N) Assistant Engineer Junior Engineer ORD/001905/2023-2024 6773/EMD 29/11/2023 30 M.S. ENTERPRISE 63.00 9.40 14.92 32
Total 533.39 299.10 56.08