Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 21,569.44 42.31 0.2  
1 NORTH 24 PARAGANAS Minakhan Barasat Division Kachurhula Zone-I Piped Water Supply Scheme , SM/13522 New Formal work order for Laying of DI rising main, DI/UPVC distribution pipe line, Providing Functional Household Tap Connection, Protection works for different dia. UPVC/DI distribution pipeline by UC bullah/Bamboo pile at different places, Construction of 100 cum capacity CWR, pipe connection and cost of pipes, specials, Construction of switch room cum chlorine room with sanitary & water supply arrangement i/c plinth protection at PH No.-1 (Size-5.40x3.60 mtr.) & PH No-2 (Size-3.60x3.00 mtr.) for Kachurhula w/s scheme (Z-I), Minakhan Block under Hasnabad Sub-Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000126/2023-2024 1693/BD 07/06/2023 360 TRISHA ENTERPRISE & CO. 166.10 36.49 21.97 16
2 NORTH 24 PARAGANAS Minakhan Barasat Division Kachurhula Zone-I Piped Water Supply Scheme , SM/13522 New Acceptance cum work order for Sinking of 1 Nos. 300.00 mtr. Deep 100 X 50 mm. dia. Trial-cum-production Tube well fitted with Indian Mark - II pump with PVC pipe & strainers at T/W site-1 for Kachurhula w/s scheme (Zone-II), Minakhan block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer ORD/001105/2023-2024 1190/HSD 22/09/2023 10 ROY CHOWDHURY CONSTRUCTION. 2.63 0.88 33.46 100
3 NORTH 24 PARAGANAS Minakhan Barasat Division Kachurhula Zone-I Piped Water Supply Scheme , SM/13522 New Acceptance cum work order for Sinking of 2 nos. 300 mm. x 200 mm. dia. 250 mtr deep Tubewell by D.R. Rig method at PH No.-1 & 2 with PVC pipe & strainer having 300mm dia 48 mtr. long housing pipe & 200mm dia 30 mtr. long filter for Kachurhula w/s scheme (Zone-I), Minakhan block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer ORD/001768/2023-2024 553/BD 22/02/2024 45 SAHA CONSTRUCTION & CO 33.41 0.00 0 0
4 NORTH 24 PARAGANAS Minakhan Barasat Division Kachurhula Zone-I Piped Water Supply Scheme , SM/13522 New Acceptance cum work order for Installation of scheme information board at different villages of various PWSS of Hasnabad block within Hasnasbad Sub-Division under Barasat Division, P.H.E.Dte. (Part-H). Assistant Engineer Junior Engineer ORD/001942/2023-2024 273/HSD 06/03/2024 10 S.M.TRADERS. 0.88 0.44 50 100
5 NORTH 24 PARAGANAS Minakhan Barasat Division Kachurhula Zone-I Piped Water Supply Scheme , SM/13522 New Acceptance cum work order for Survey, Design Drawing & DPR Preparation for NEW PWSS (KACHURHULA Z-I Water Supply Scheme) in MINAKHAN BLOCK under Barasat Division, PHE Dte Assistant Engineer Junior Engineer ORD/002717/2021-2022 280/HSD 09/02/2022 15 SRIJAN ECOLOGICAL UPLIFTMENT PVT.LTD. 4.50 4.50 100 1
6 NORTH 24 PARAGANAS Minakhan Barasat Division Kachurhula Zone-I Piped Water Supply Scheme , SM/13522 New Acceptance cum work order for Survey, Design Drawing & DPR Preparation for NEW PWSS (KACHURHULA Z-I Water Supply Scheme) in MINAKHAN BLOCK under Barasat Division, PHE Dte Assistant Engineer Junior Engineer ORD/002995/2021-2022 280/HSD 09/02/2022 15 SRIJAN ECOLOGICAL UPLIFTMENT PVT.LTD. 4.50 0.00 0 1
7 NORTH 24 PARAGANAS Minakhan Barasat Division Kachurhula Zone-I Piped Water Supply Scheme , SM/13522 New Material Requisition To Resource Division RTOR000210/2022-2023 892/BD 22/03/2023 Resource Division 17.66 0.00 0 0
8 NORTH 24 PARAGANAS Minakhan Central Drilling Kachurhula Zone-I Piped Water Supply Scheme , SM/13522 New Construction of Big Diameter Tube-Well by Deploying of Suitable Capacity Drilling Rig (Direct Rotary, Reverse Rotary, Odex Method) at Different Districts for Different Water Supply Schemes Including Procurement & Installation Pumping Machinery with All Allied Accessories at the Above Constructed Tube-Wells Under JJM Program throughout the State of West Bengal. (2ed call of NIET 25 of 2022-23) Assistant Engineer,Driller In Charge Junior Engineer ORD/000001/2023-2024 1415/CDD 21/09/2023 300 JHARGRAM SPV PRIVATE LIMITED 21,339.76 0.00 0 11
Total 21,569.44 42.31 0.2