Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
9 | 23,597.11 | 263.85 | 1.12 | ||||||||||||||
1 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Gokna to accommodate FHTC , SM/13405 | Augmentation | Regarding Restoration charges for road damages. | BILL/03461/2023-2024 | BP-2023-24-830 | 15/03/2024 | EXECUTIVE ENGINEER BARASAT HIGHWAY DIVISION NO -I P.W. (ROADS) DIRECTORATE | 76.53 | 0.00 | 0 | 0 | ||||
2 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Gokna to accommodate FHTC , SM/13405 | Augmentation | Formal work order for Laying of DI/UPVC distribution pipe line and providing Functional Household Tap Connection for Augmentation of Gokna Zone-II water supply scheme in Baduria Block under Barasat Division, P.H.E Dte. | Assistant Engineer | Junior Engineer | ORD/000030/2023-2024 | 1301/BD | 26/04/2023 | 90 | J.D.J.ENTERPRISE. (TRADERS PVT.LTD) | 766.02 | 84.38 | 11.02 | 29 | |
3 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Gokna to accommodate FHTC , SM/13405 | Augmentation | Formal work order for Laying of DI/UPVC distribution pipe line and providing Functional Household Tap Connection for Augmentation of Gokna Zone-I B water supply scheme in Baduria Block under Barasat Division, P.H.E Dte. | Assistant Engineer | Junior Engineer | ORD/000128/2023-2024 | 1694/BD | 08/06/2023 | 90 | SUPRITI ENTERPRISE. | 581.97 | 106.92 | 18.37 | 20 | |
4 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Gokna to accommodate FHTC , SM/13405 | Augmentation | Hiring Diesel Luxury Car on daily basis for the supervision of work and office uses under Basirhat Sub-Division P.H.E. Dte. (Period: 01.07.2024 to 31.12.2024), Sl.No. - 02 | Assistant Engineer | Junior Engineer | ORD/000159/2024-2025 | 1018/BHTSD | 28/06/2024 | 184 | DEB KUMAR DAS. | 0.87 | 0.37 | 42.53 | 0 | |
5 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Gokna to accommodate FHTC , SM/13405 | Augmentation | Formal work order for Laying of DI/UPVC distribution pipe line and providing Functional Household Tap Connection for Augmentation of Gokna Zone-I A water supply scheme in Baduria Block under Barasat Division, P.H.E Dte. | Assistant Engineer | Junior Engineer | ORD/000172/2023-2024 | 1726/BD | 08/06/2023 | 90 | SUJIT KUMAR SAHA | 224.48 | 72.18 | 32.15 | 10 | |
6 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Gokna to accommodate FHTC , SM/13405 | Augmentation | Material Requisition To Resource Division | RTOR000025/2023-2024 | 1248/BD | 25/04/2023 | Resource Division | 520.48 | 0.00 | 0 | 0 | ||||
7 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Gokna to accommodate FHTC , SM/13405 | Augmentation | Material Requisition To Resource Division | RTOR000138/2023-2024 | 4424/BD | 10/11/2023 | Resource Division | 47.88 | 0.00 | 0 | 0 | ||||
8 | NORTH 24 PARAGANAS | Central Drilling | Augmentation of ground water based piped water supply scheme for Gokna to accommodate FHTC , SM/13405 | Augmentation | Construction of Big Diameter Tube-Well by Deploying of Suitable Capacity Drilling Rig (Direct Rotary, Reverse Rotary, Odex Method) at Different Districts for Different Water Supply Schemes Including Procurement & Installation Pumping Machinery with All Allied Accessories at the Above Constructed Tube-Wells Under JJM Program throughout the State of West Bengal. (2ed call of NIET 25 of 2022-23) | Assistant Engineer,Driller In Charge | Junior Engineer | ORD/000001/2023-2024 | 1415/CDD | 21/09/2023 | 300 | JHARGRAM SPV PRIVATE LIMITED | 21,339.76 | 0.00 | 0 | 11 | |
9 | NORTH 24 PARAGANAS | Eastern Mechanical | Augmentation of ground water based piped water supply scheme for Gokna to accommodate FHTC , SM/13405 | Augmentation | Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.II (Rep.) and IV (New) under Gokna W/S Scheme and Pump House No- II (Rep) under Arsula W/S Scheme District of 24 Pgs. (N) | ORD/001912/2023-2024 | 6735/EMD | 29/11/2023 | 30 | M.S. ENTERPRISE | 39.12 | 0.00 | 0 | 0 | |||
Total | 23,597.12 | 263.86 | 1.12 |