Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 21,615.39 114.86 0.53  
1 NORTH 24 PARAGANAS Minakhan Barasat Division Phulbari Abad Piped Water Supply Scheme. , SM/12717 New Formal work order for Laying of DI rising main, DI/UPVC distribution pipe line, Providing Functional Household Tap Connection, Protection works for different dia. UPVC/DI distribution pipeline by UC bullah/Bamboo pile at different places, Construction of 150 cum capacity CWR , pipe connection and cost of pipes, specials, Construction of switch room cum chlorine room with sanitary & water supply arrangement i/c plinth protection at PH No.-1 (Size-5.40x3.60 mtr.) & PH No-2 (Size-3.60x3.00 mtr.) for Phulbari Abad w/s scheme, Minakhan Block under Hasnabad Sub-Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000117/2023-2024 1691/BD 07/06/2023 360 M/S B.K.ENTERPRISE. 252.21 110.04 43.63 80
2 NORTH 24 PARAGANAS Minakhan Barasat Division Phulbari Abad Piped Water Supply Scheme. , SM/12717 New Acceptance cum work order for Survey, Design Drawing & DPR Preparation for NEW PWSS (PHULBARI ABAD Water Supply Scheme) in MINAKHAN BLOCK under Barasat Division, PHE Dte. (PART-A) Assistant Engineer Junior Engineer ORD/002730/2021-2022 306/HSD 15/02/2022 15 SRIJAN ECOLOGICAL UPLIFTMENT PVT.LTD. 4.82 4.82 100 1
3 NORTH 24 PARAGANAS Minakhan Barasat Division Phulbari Abad Piped Water Supply Scheme. , SM/12717 New Material Requisition To Resource Division RTOR000218/2022-2023 886/BD 22/03/2023 Resource Division 11.94 0.00 0 0
4 NORTH 24 PARAGANAS Minakhan Central Drilling Phulbari Abad Piped Water Supply Scheme. , SM/12717 New Construction of Big Diameter Tube-Well by Deploying of Suitable Capacity Drilling Rig (Direct Rotary, Reverse Rotary, Odex Method) at Different Districts for Different Water Supply Schemes Including Procurement & Installation Pumping Machinery with All Allied Accessories at the Above Constructed Tube-Wells Under JJM Program throughout the State of West Bengal. (2ed call of NIET 25 of 2022-23) Assistant Engineer,Driller In Charge Junior Engineer ORD/000001/2023-2024 1415/CDD 21/09/2023 300 JHARGRAM SPV PRIVATE LIMITED 21,339.76 0.00 0 11
5 NORTH 24 PARAGANAS Minakhan Eastern Mechanical Phulbari Abad Piped Water Supply Scheme. , SM/12717 New Quotation for Service Connection Charges for PH- I under Fulbari Abad W/S Scheme in the district of North 24 Pgs. BILL/04869/2023-2024 BP-326-23-24 07/03/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 6.66 0.00 0 null
Total 21,615.40 114.86 0.53