Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9 1,008.74 712.37 70.62  
1 NORTH 24 PARAGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Bansghata to accommodate FHTC , SM/12276 Augmentation Acceptance cum work order for Construction of Boundary wall, Approach Road, Earth Filling and Construction of 3.60 mtr. X 3.00 mtr. size Guard Room with sanitary and water supply arrangement incl. plinth protection at OHR site of Basghata Water Supply Scheme, Bagdah Block within the jurisdiction of Bongaon Sub-Division under Barasat Division, P.H.E. Dte. Assistant Engineer ORD/000353/2024-2025 2358/BD 20/08/2024 60 MD.SALIM GAZI. 25.84 0.00 0 0
2 NORTH 24 PARAGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Bansghata to accommodate FHTC , SM/12276 Augmentation Acceptance cum work order for Sinking of 2 (two) no. 300 mm. x 200 mm. dia. 250 mtr deep Replacement Tubewell by D.R. Rig method with UPVC pipe & UPVC ribbed strainer at Augmentation of Bansghata Water Supply Scheme (H/W Site & 2nd T/W Site) under Bongaon Sub-Division, P.H.E. Dte. Assistant Engineer ORD/001156/2023-2024 518/BD 20/02/2024 60 M/S N.K. BUILDERS 30.51 0.00 0 0
3 NORTH 24 PARAGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Bansghata to accommodate FHTC , SM/12276 Augmentation Formal work order for Laying of Di rising main, DI/UPVC distribution pipe line and Providing (FHTC) for augmentation of Bansghata Water Supply Scheme, Bagdah Block, under Bongaon Sub-Division, PHE Dte. Assistant Engineer Junior Engineer ORD/001171/2022-2023 760/BD 10/03/2023 90 UMWELT ENGINEER PVT.LTD. 747.85 689.03 92.13 100
4 NORTH 24 PARAGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Bansghata to accommodate FHTC , SM/12276 Augmentation Acceptance cum work order for Renovation and repairing of Boundary wall at 1st Tube Well & 2nd Tube Well site and Construction of Approach Road at 1st T/W & 2nd T/W site under Augmentation of Bansghata water Supply scheme, Bagdah Block within jurisdiction of Bongaon Sub-Division, under Barasat Division P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001500/2023-2024 4471/BD 22/11/2023 23 ROY CHOWDHURY CONSTRUCTION. 12.67 9.13 72.06 73
5 NORTH 24 PARAGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Bansghata to accommodate FHTC , SM/12276 Augmentation Route Survey, Design Drawing & Preparation of DPR for Bansghata Water Supply Scheme in Bagdah Block within the Jurisdiction of Bongaon Sub-Division under Barasat Division, PHE Dte. Assistant Engineer Junior Engineer ORD/002790/2021-2022 142/BON 18/02/2022 15 SRIJAN ECOLOGICAL UPLIFTMENT PVT.LTD. 4.84 4.84 100 1
6 NORTH 24 PARAGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Bansghata to accommodate FHTC , SM/12276 Augmentation Material Requisition To Resource Division RTOR000006/2023-2024 1246/BD 25/04/2023 Resource Division 113.03 0.00 0 0
7 NORTH 24 PARAGANAS Barasat Division Augmentation of Ground Water Based Piped Water Supply Scheme for Bansghata to accommodate FHTC , SM/12276 Augmentation Material Requisition To Resource Division RTOR000094/2023-2024 1864/BD 23/06/2023 Resource Division 31.18 0.00 0 0
8 NORTH 24 PARAGANAS Eastern Mechanical Augmentation of Ground Water Based Piped Water Supply Scheme for Bansghata to accommodate FHTC , SM/12276 Augmentation Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.I & II (Replacement) under Bansghata W/S Scheme, District of 24 Pgs. (N). NIET No.- 26 of EE/EMD of 2022-23 (Sl. No.- 02) ORD/000010/2023-2024 1552/EMD 20/04/2023 30 TALUKDER & CO. 21.41 0.00 0 0
9 NORTH 24 PARAGANAS Eastern Mechanical Augmentation of Ground Water Based Piped Water Supply Scheme for Bansghata to accommodate FHTC , SM/12276 Augmentation Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.I & II (Replacement) under Bansghata W/S Scheme, District of 24 Pgs. (N). Assistant Engineer Junior Engineer ORD/001133/2023-2024 4725/EMD 04/08/2023 30 TALUKDER & CO. 21.41 9.37 43.76 80
Total 1,008.73 712.37 70.62