Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
14 728 474.06 65.12  
1 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Khulna Bhanderkhali Zone-II to accommodate FHTC , SM/11699 Augmentation Acceptance cum work order for Construction of boundary wall at pond site for damaged portion & repairing of existing boundary wall at CWR site within Khulna Bhanderkhali w/s scheme (Zone-II), Sandeshkhali-II Block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer ORD/000298/2023-2024 2113/BD 19/07/2023 21 ANKUSH CONSTRUCTION & CO. 6.14 6.14 100 55
2 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Khulna Bhanderkhali Zone-II to accommodate FHTC , SM/11699 Augmentation Formal work order for Construction of 150 Cum capacity 20 mtr staging height R.C.C Over Head water Reservoir as per Departmental design, drawing and specification including bored pile & pile cap at Khulna Bhanderkhali (Zone-II) under Surface Based Water Supply Scheme Hasnabad under Hasnabad Sub-Division, PHE Dte. Assistant Engineer ORD/000321/2024-2025 2261/BD 12/08/2024 365 B.S.ENTERPRISE. (BASIRHAT) 115.79 0.00 0 0
3 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Khulna Bhanderkhali Zone-II to accommodate FHTC , SM/11699 Augmentation Formal work order for Laying of DI/UPVC distribution pipe line and providing Functional Household Tap Connection for Augmentation of Khulna Bhanderkhali W/S scheme (Zone-II), Sandeshkhali-II Block within Hasnabad Sub-Division, under Barasat Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/000663/2022-2023 2722/BD 14/09/2022 90 S.S.ENTERPRISE. (BAMANGACHI) 345.34 320.20 92.72 1
4 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Khulna Bhanderkhali Zone-II to accommodate FHTC , SM/11699 Augmentation Acceptance cum work order for Sinking of 1 no. 300 mm. x 200 mm. dia. 300 mtr deep Tubewell by D.R. Rig method with PVC pipe & strainer having 300mm dia 48 mtr. long housing pipe & 200mm dia 30 mtr. long filter for Augmentation of Khulna Bhanderkhali w/s scheme (Z-II), Sandeshkhali-II block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer ORD/000737/2023-2024 2491/BD 18/08/2023 30 M/S PROGATI ENTERPRISE. 26.89 20.57 76.5 100
5 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Khulna Bhanderkhali Zone-II to accommodate FHTC , SM/11699 Augmentation Acceptance cum work order for Protection works in different places for protection of different dia DI/UPVC rising/distribution pipe line by UC bullah/Bamboo pile for Augmentation of Khulna Bhandarkhali Zone-II w/s scheme, Sandeshkhali-II block under Hasnabad Sub- Division P.H.E. Dte. Assistant Engineer ORD/000848/2023-2024 2656/BD 01/09/2023 30 M/S DATTA ENTERPRISE. 58.87 58.07 98.64 85
6 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Khulna Bhanderkhali Zone-II to accommodate FHTC , SM/11699 Augmentation Acceptance cum work order for Sinking of 2 nos. 300 mm. x 200 mm. dia. 300 mtr deep Tubewell by D.R. Rig method with PVC pipe & strainer having 300mm dia 36 mtr. long housing pipe & 200mm dia 30 mtr. long filter for Augmentation of Khulna Bhanderkhali w/s scheme (Z-II), Sandeshkhali-II block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer ORD/001172/2022-2023 785/BD 13/03/2023 30 M/S NIRMAN CONSTRUCTION. 47.08 36.84 78.25 100
7 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Khulna Bhanderkhali Zone-II to accommodate FHTC , SM/11699 Augmentation Acceptance cum work order for 1 no. pump connection at PH No.-3 in connection with Augmentation for Khulna Bhanderkhali water supply scheme (Z-II) , Sandeshkhali-II block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001296/2023-2024 1418/HSD 06/11/2023 7 DEB PRASAD GHOSH. 0.93 0.93 100 100
8 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Khulna Bhanderkhali Zone-II to accommodate FHTC , SM/11699 Augmentation Acceptance cum work order for 2 nos. pump connection at PH No.-1 & 2 in connection with Augmentation for Khulna Bhanderkhali water supply scheme (Z-II) , Sandeshkhali-II block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001297/2023-2024 1419/HSD 06/11/2023 7 DEB PRASAD GHOSH. 0.96 0.96 100 100
9 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Khulna Bhanderkhali Zone-II to accommodate FHTC , SM/11699 Augmentation Material Requisition To Resource Division RTOR000090/2022-2023 3421/BD 23/11/2022 Resource Division 62.56 0.00 0 0
10 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Khulna Bhanderkhali Zone-II to accommodate FHTC , SM/11699 Augmentation Material Requisition To Resource Division RTOR000255/2022-2023 941/BD 22/03/2023 Resource Division 9.14 0.00 0 0
11 NORTH 24 PARAGANAS Eastern Mechanical Augmentation of ground water based piped water supply scheme for Khulna Bhanderkhali Zone-II to accommodate FHTC , SM/11699 Augmentation Quotation for Service Connection Charges for PH- I under Bhanderkhali W/S Scheme in the district of North 24 Pgs. JL No- 92, Plot No-1 & 65/264 BILL/04885/2023-2024 null 04/03/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 8.55 0.00 0 0
12 NORTH 24 PARAGANAS Eastern Mechanical Augmentation of ground water based piped water supply scheme for Khulna Bhanderkhali Zone-II to accommodate FHTC , SM/11699 Augmentation Quotation for Service Connection Charges for PH- III under Bhanderkhali W/S Scheme in the district of North 24 Pgs. JL No. 92, Plot No-112. BILL/04886/2023-2024 BP-321-23-24 07/03/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 6.02 0.00 0 0
13 NORTH 24 PARAGANAS Eastern Mechanical Augmentation of ground water based piped water supply scheme for Khulna Bhanderkhali Zone-II to accommodate FHTC , SM/11699 Augmentation Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.I & II (Zone-II) (Replacement) under Kulna-Bhanderkhali W/S Scheme District of 24 Pgs. (N). NIET No. 24 of EE/EMD of 2022-23 (Sl. No.- 09) Assistant Engineer Junior Engineer ORD/000831/2022-2023 36/EMD 03/01/2023 30 JAL PRAVAHIKA PVT. LTD. 26.49 24.17 91.24 100
14 NORTH 24 PARAGANAS Eastern Mechanical Augmentation of ground water based piped water supply scheme for Khulna Bhanderkhali Zone-II to accommodate FHTC , SM/11699 Augmentation Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.III (Zone-II) (Replacement) under Khulna-Bhanderkhali W/S Scheme District of 24 Pgs. (N). NIET No. 24 of EE/EMD of 2022-23 (Sl. No.- 10) Assistant Engineer Junior Engineer ORD/000832/2022-2023 37/EMD 03/01/2023 30 D.K. ELECTRIC 13.24 6.18 46.68 100
Total 728.01 474.06 65.12